49 N.J.L. 411 | N.J. | 1887
The opinion of the court was delivered by
The plaintiffs’ declaration is in covenant upon a contract, under seal, between themselves and the defendant. It consists of three counts, to which the defendant has interposed a single demurrer. We do not deem ourselves called upon to deal with the various matters discussed in the briefs of counsel, except so far as is necessary for the giving of judgment upon the demurrer, because the real rights of the parties can be better determined when the circumstances on which they depend shall be disclosed by evidence.
By the contract, dated November 12th, 1879, as set out in the declaration, the plaintiffs agreed to grade certain lands of the defendant at Point Pleasant, under the supervision and direction of a surveyor selected by the defendant, and the defendant covenanted, “in consideration of the faithful performance of the specified work,” to pay the plaintiffs eighteen cents per cubic yard for the sand and clay removed, in manner following : first, by assigning a certain bond and mortgage for $2500; second, by conveying a certain tract of land valued at $2500; third, by assigning other mortgages to the amount of $1750; fourth, by giving orders for guano, at $15 per ton, to an amount necessary to complete payment for three-fourths
With regard to the $1600 payable in cash, the foregoing facts make out a clear case for the plaintiffs. The opposing suggestion, that the right to have the cash paid monthly, and to the extent of one-fourth of the work done, rests, not upon the specialty, but on the subsequent mutual agreement, which was not under seal and therefore cannot support an action of covenant, is not tenable. The obligation to pay is created by the sealed instrument; the subsequent agreement merely fixes the amount and time of the payment. It is as if the covenant had been to pay as the defendant should, from time to time, approve of and accept the work done; no breach of the covenant could be shown without resort to the approval and acceptance ; but when these appeared, the obligation of the covenant, before inchoate, would become complete and actionable. The case is not one where a parol contract is made in substitution for or variation of a specialty; it is merely one where some act, in pursuance of the covenant, is needed to give pre
But with regard to the non-delivery of orders for guano, the plaintiffs’ position is very different. The general covenant of the defendant to pay is “ in consideration of the faithful performance of the specified work ” by the plaintiffs. This on its face imports an obligation to pay only when the work, i. e., the whole work, is performed. 1 Chitty on Pleading 322. So far as relates to the cash payments, this general covenant is clearly modified by the agreement to pay in instalments; but I have not found any tangible modification of it with regard to the securities and orders which were to be given for three-fourths of the work. There is indeed a clause in the agreement that the defendant shall be at liberty to retain, as collateral security, such of the securities mentioned as it may elect; but this seems too vague to support, an obligation to deliver the guano orders on any other condition than the completion of the work. To make out a breach of this covenant, therefore, the plaintiffs must aver entire performahce by themselves or something which legally absolves them therefrom. Complete performance is not pretended, but legal release is claimed. .
The first count founds this claim of legal release upon the failure of the defendant to pay the plaintiffs what was due under the contract prior to September 23d, 1881, by reason
The second count bases the claim of release upon the fact that on September 23d, 1881, while the plaintiffs were ready and willing to complete the work, and tendered themselves so, the defendant notified them to remove all their implements from the land to be graded, and compelled them to do so and to discontinue the work. This fact, I think, constitutes a legal excuse. It shows unequivocally that the defendant intended to abandon the contract, and absolutely prevented the plaintiffs from completing the work. 1 Chitty on Pleading 326. This was equivalent to performance by the plaintiffs of the condition precedent, so far as that was essential to the right of recovery (Shinn v. Roberts, Spen. 435; Shinn v. Haines, 1 Zab. 340), and they became entitled to the stipulated price for the work done, or to damages for the nonpayment thereof. The second count, in my opinion, shows a breach by the defendant in regard both to the cash payment, and to the guano orders.
The defendant’s objection that the contract, as set out on oyer, contains other terms than those appearing in the declaration, is unimportant, because the omitted stipulations afford no answer to the case of the plaintiffs as made in their pleading. 1 Chitty on Pleading 434.
The plaintiffs are entitled to judgment for damages on both breaches.