148 N.Y.S. 568 | N.Y. Sup. Ct. | 1914
The plaintiff herein has performed work for the defendant New York State Construction Company under a contract for a public improvement. On or about April 8, 1913, the plaintiff filed a notice of lien for the moneys to become due under its contract, but it allowed this lien to lapse on July eighth. Thereafter it filed the notice of the lien which it now seeks to' foreclose. In the meanwhile several other lienors had filed notices of lien, and the defendants Alfred R. Sax and Coal and Iron National Bank had filed several assignments of money to become due under the contract made by the city with the State Construction Company. These liens and assignments
Ordered accordingly.