FINDINGS OF FACT, CONCLUSIONS OF LAW AND ORDER OF JUDGMENT
This is a partial takings case. Plaintiffs Portland Natural Gas Transmission System and Maritimes & Northeast Pipeline, L.L.C. (collectively “Portland”) have acquired temporary and permanent easements to install, operate and maintain interstate natural gas pipelines across land in Haverhill, Massachusetts owned by WBC Extrusion Products, Inc. (“WBC”) pursuant to the Natural Gas Act, 15 U.S.C. § 717f(h). After a bench trial, the Court finds that the plaintiffs must compensate defendants for the partial taking in the amount of $148,206.00, plus interest from the date of taking.
I. FINDINGS OF FACT
A. The Taking
On July 31, 1997, the Federal Energy Regulatory Commission authorized Port-'
On July 9, 1999, the Court issued an unopposed Order of Taking by which Portland acquired permanent and temporary easements described in the Condemnation Complaint (Docket # 17) to construct, operate and maintain the gas pipeline on WBC’s property. In total, the permanent easements spanned 2.37 acres, and the temporary easements encompassed 2.2 acres.
To build the pipeline, which has a 30" diameter, Portland destroyed trees and other foliage, excavated along the entire length of the easements acquired, assembled the pipeline and then buried it. Portland requires a minimum of a 3-foot soil cover over the pipe.
B. The Property
In 1985, Wolf Jachimowiez, the principal shareholder and officer of WBC Extrusion Products, purchased land in Haverhill to construct a plant for his company, which manufactures packaging material. The property was desirable because it has good access to major travel routes and is close to New Hampshire. In addition, the City of Haverhill is pro-development, erecting few hurdles to permitting.
WBC’s land consists of approximately 76 acres divided into two parcels. Parcel 1, known as the ‘WBC Industrial Park,” contains 58.54 acres. (Def.Ex. 17, Vol.I, p. 32). On September 24, 1986, the City approved the WBC Industrial Park subdivision which created eight industrial lots in Parcel 1. (Ex. 4) As of July 1999, only one of the eight lots (designated as Lot 7) was occupied by WBC. The other seven lots were vacant, raw land, but up for sale. Parcel 2 encompasses 19 acres and is not a part of the WBC Industrial Park. Consisting mostly of wetlands and without street frontage, Parcel 2 was a non-buildable, non-conforming lot as of July 1999.
The easements affect three portions of the WBC property.
• Lot 1, 9.29 acres in size, is encumbered with a permanent easement of 1.21 acres and a temporary easement of 1.01 acres.
• Lot 8, which encompasses 11.36 acres, contains a permanent easement of 0.69 acres and a temporary easement of 0.58 acres.
• Parcel 2, which spans 19.20 acres, is subject to a permanent easement of 0.47 acres and a temporary easement of 0.51 acres.
The WBC Industrial Park caters to a niche market of high-end industrial facilities conforming to high aesthetic standards, and bars lower-cost industrial structures. To achieve this goal, WBC established an Owner’s Association jn May 1999 which adopted a set of restrictive covenants on lot development and operation that run with the land. The preamble provides that they were adopted “[t]o encourage, enhance and protect the value, attractiveness and desirability of the Park as a first class industrial park development. ...” Article Five of the Covenants contains specific restrictions on use of the Park, including a provision requiring that site engineering, use, landscape and signage plans be submitted to and approved
C.Marketing
WBC hired John Chiungos, a commercial real estate broker, to sell the lots. In his opinion, the park was desirable because it was well located, and municipal utilities (except for sewage disposal) were available. As of July 1999, the market for industrial properties was improving because the excess inventory of existing buddings had been absorbed, and firms were looking for buildable land.
Chiungos’ sales efforts met with mixed success. Although WBC received an offer on Lots 3 and 6 before July 1999, the deal did not close. Lots 4 and 5 sold after July 1999. As of the time of trial, WBC had received an offer on Lot 2, but had not yet decided whether to accept it. Meanwhde, WBC received no offers at all on Lots 1 and 8 either before or after July 1999. Indeed, Chiungos received no inquiries whatsoever about Lot 1, although he did show Lot 8 several times.
The properties had certain characteristics which limited their marketabdity before the installation of the pipeline. First, the upscale covenants precluded metal buildings and outside storage and required compliance with other aesthetic limitations. In the estimation of Chiungos, compliance with the covenants would increase the costs of construction on the WBC Properties by five to ten dollars per square foot. Second, competitive developments had lots nearby with municipal sewer hookup. Although it had other utilities, WBC did not have a municipal sewer connection and therefore relied on an on-site septic tank. Finady, the access road to Route 121, Hill-dale Avenue, was deficient because until 1999, it was a gravel road. It was impassable in the wintertime prior to June 1998, and not adequately upgraded untd 2000.
Nonetheless, with a booming economy and limited inventory in the area, the owners of WBC apparently wore rose-colored glasses when pricing the two encumbered lots, even after news of the pipeline had been leaked. The prices listed for the lots increased steaddy and, in fact, rather dramatically after 1998:
List Price Lot 1 Lot 8
6/98 $295,000 $165,000
1/1/99 $380,000 $230,000
12/99 $480,000 $310,000
6/1/00 $510,000 $350,000
D.Highest and Best Use
As of the date of the taking, the highest and best use of Lots 1 and 8 is as industrial lots. The highest and best use of Parcel 2 is as open space, its current use.
E.Requirements
As part of its operation and maintenance of the pipeline, Portland adopted a set of rules for construction activity in the vicinity of the pipeline, related facilities and rights of way. These rules of Portland are entitled “Requirements for Construction On or Near Company Facilities,” dated August 24, 1998 (“Requirements”). The Requirements further define the scope of the easement taken. Insofar as the Requirements limit the private use of Lots 1 and 8 of the WBC Industrial Park, they diminish their market value.
Among those rules imposed by the Requirements are the fodowing:
§ 2.3 Copies of any proposed plans or drawings for work within the pipelineright of way shall be submitted to [Portland] for review.
§ 3.1 No building or obstruction may be erected within the pipeline easement. ...
§ 3.5 No drainage swales and no reductions in grade are permitted on the pipeline easement without prior written approval from [Portland]....
§ 3.6 Proposed grades shall not exceed maximum allowable slopes of 4:1 parallel to the pipeline(s) and 8:1 perpendicular to the pipehne(s).
§ 3.8 Parking areas should be planned so as to avoid covering the pipeline easement if at all possible.
§ 3.9 No roads, driveways, foreign lines, or utilities may be installed parallel to the pipeline(s) within the pipeline easement....
§ 3.13 If, in the sole judgment of [Portland], the ... developer’s proposed plans necessitate the installation of casing pipe and/or other alterations ... to protect [Portland’s] pipehne(s), the ... owner[,] and/or developer shall pay [Portland] the estimate cost prior to [Portland] beginning the alterations.
Section 6.4 of the Requirements also provides that Portland may set additional requirements at any time:
Approval by [Portland] of the proposed design drawings does not relieve the landowner/developer from further compliance with any and all Company specifications ... [Portland] reserves the right to set forth additional requirements if deemed necessary, (emphasis added).
The Requirements potentially affect use of the land beyond the pipeline easement itself. Section 5.1.1 requires notification of any blasting proposed within “300 feet of [Portland’s] facilities.”
Portland paints itself as the picture of flexibility in applying the Requirements and insists that it would permit certain uses, such as parking lots or access roads, on or near the pipeline easement. Nonetheless, as it concedes, it would have to do a project-by-project review to ensure safe and effective operation of the pipeline. Thus, from the viewpoint of the prospective purchaser, the Requirements introduce a hassle factor which would affect the purchase price.
II. RULINGS OF LAW
A. Applicable Law
The Takings Clause of the Fifth Amendment prohibits the government from taking private property for public use without just compensation.
Palazzolo v. Rhode Island,
Although condemnation of private property under the Natural Gas Act is a matter of federal law, 15 U.S.C. § 717f(h) provides that a federal district court must look to and apply the “practice and procedure” followed in similar proceedings in the courts where the property is situated. Generally speaking, state law governs compensation issues in eminent domain proceedings involving private interests.
B. Partial Takings
As the parties agree, since the taking is located in Massachusetts, the Court relies on the Massachusetts law of eminent domain to determine just compensation in this condemnation action. Mass. Gen. L. ch. 79, § 12, which governs partial takings, provides:
The damages for property taken under this chapter shall be fixed at the value thereof before the recording of the order of taking, and in case only part of a parcel of land is taken there shall be included damages for all injury to the part not taken caused by the taking....
“As a general rule, in the case of a partial taking, the landowner is entitled to compensation measured, not by the fair market value of the portion taken, but by the diminution in the fair market value of his land caused by the partial taking.”
Kane v. Hudson,
Value of entire parcel before taking minus value of remainder area after taking, equals just compensation; value of land taken plus (value of remainder area before taking minus value of remainder area after taking) equals just compensation.
Julius L. Sackman, 4A
Nichols on Eminent Domain,
§ 1402[l][b] (rev.3d ed.2001). The measure of damages is generally the fair market value of the land immediately before the taking minus its fair market value immediately after the taking.
See Hero Int’l Corp. v. Commonwealth,
C. Fair Market Value
Fair market value is defined as “the highest price which a hypothetical willing buyer would pay to a hypothetical willing seller in an assumed free and open market” when the property has been exposed to the market for a reasonable period of time.
See Newton Girl Scout Council, Inc. v. Massachusetts Turnpike Auth.,
Some courts have held that “any factor,' including public fear, which impacts on the market value of land taken for a public purpose may be considered to explain the basis for an expert’s valuation opinion. Whether this fear is objectively reasonable is irrelevant to the issue of full compensation in an eminent domain proceeding.”
Florida Power & Light Co. v. Jennings,
Other courts, in the same or similar circumstances, have held that the anticipation of increased interference or potential hazards on the land remaining after a taking, which one court has labeled “stigma damages,” can be considered in assessing severance damages.
See, e.g., Vector Pipeline, L.P., v. 68.55 Acres of Land,
D. Easements
Simply put, the measure of value in condemnation proceedings where the estate taken is less than the fee or absolute ownership, such as an easement, is the difference between the fair market value with and without the burden.
See United States ex rel. Tennessee Valley Auth. v. Robertson,
“The landowner is entitled to assume, in the condemnation suit, that the taking authority will make the full use ‘physically possible of any easement or land described in the taking certificate.’ ” 4A
Nichols,
at § 14A.06[3] (quoting
2,953.15 Acres of Land v. United States,
The taking authority is free to limit the scope of access either before the taking or, with the landowner’s agreement, after the taking.
Mugar v. Massachusetts Bay Transp. Auth.,
To calculate the value of the property actually taken as a result of the permanent easements, the Court must consider not only the market value of the property and the amount of land taken, but also the percentage of the original bundle of ownership rights that the owner retains on the encumbered land.
See, e.g., United States v. 122.63 Acres of Land,
Takings of temporary easements are measured differently. A landowner must be compensated for the loss of use of property taken by a temporary easement and any impairment of access to the property during the period of construction.
Miczek v. Commonwealth,
32 Mass.App. Ct. 105, 108,
E. Miscellaneous
Damages are to be measured as of the date of the taking, which in this case is July 9, 1999.
United States v. 50 Acres of Land,
The Fifth Amendment and Massachusetts law require the payment of interest as an element of just compensation when the date of taking of the property precedes the payment of the award.
See Smyth v. United States,
III. DISCUSSION
With these general principles in mind, I turn to the valuation of the takings.
A. Per Acre Value of the Lots in July 1999
The first step in the analysis of fair market value is to determine the per acre value of Lot 1, Lot 8, and Parcel 2 in July 1999. Mr. Peter E. Stanhope, the real estate appraiser relied upon by WBC, calculated the per-acre value of Lot 1 to be $57,000.00 (rounded from $56,973.00), based on a comparison of the property with similar lots in the region. Using a similar method, Mr. Steven R. Foster, the real estate appraiser relied upon by Portland, estimated the per-acre value of Lot 1 to be $50,000.00.
The Court finds Portland’s estimate of $50,000.00 for Lot 1 more reasonable. The list price for Lot 1 was $380,000.00 on January 1, 1999, and $480,000.00 on December 1, 1999 — the two bookend listing dates closest to the date of the taking, July 9, 1999. When divided by the total acreage of 9.29 acres, these figures translate into per-acre prices of $40,904.00 and $51,668.00, respectively. If the Court were to accept WBC’s analysis, the adjusted value of Lot 1 would be substantially more than its listing price for either of the two dates adjacent to the date of the taking. There is no evidence that WBC deliberately set the list price of Lot 1 below its true market value; that WBC ever discounted the list price to reflect the (actual or expected) effect of the taking; or that properties similar to Lot 1 were likely to sell for more than their list prices during the same time period. Moreover, there was a lack of demand for these lots that would affect the hypothetical purchaser’s assessment of their market value. Finally, Lot 5 was sold by deed dated April 3, 2000 for the list price. Therefore, the Court finds Portland’s estimate a more credible estimate of market value for Lot 1.
Mr. Stanhope, WBC’s expert witness, calculated the per-acre value of Lot 8 to be 65% that of Lot 1, yielding a value of $37,000.00 based on his estimates.
Finally, based on a comparison of the property with similar lots in the region, Mr. Stanhope calculated the per-acre value of Parcel 2 to be $983.00 per acre. The plaintiffs presented no evidence to the contrary, and the Court has no information before it regarding the list price of this lot. The Court finds the value of Parcel 2 to be $983.00 per acre.
B. Permanent Easements
Although it is clear that the plaintiffs’ easement rights extend far enough to enable them to “construct, operate and maintain an interstate natural gas pipeline” on WBC’s land, the inherent imprecision of this standard makes the degree of potential infringement on property rights difficult to ascertain. The parties’ estimates of the percentage diminution in value of the land burdened by the permanent easement differ substantially.
Defendants place considerable emphasis on the construction Requirements which, they argue, render the encumbered land all but worthless to WBC. They argue that since there is no delineated limitation to the easement rights taken, the Requirements must be construed broadly in assessing damages. In sum, defendants contend that the correct percentage diminution is 100%, and in any event should be adjudged no less than 90%.
Portland consistently downplays the Requirements, arguing that many of the Requirements are waivable or impose little de facto burden. For example, Mr. Frank Gessner, the right-of-way manager for the pipeline, testified that Portland tried to be responsive to the needs of lot owners and in many cases could accommodate parking lots, small shrubbery, or extra cover in the easement area on a case-by-case basis. Arguing that the easement areas could still be utilized for “parking, access, and open space as well as for floor area and lot coverage calculations” after the taking, and that any buildings constructed could be shifted outside of the easement area, the plaintiffs urge that the property interest being taken by the easement represents no more than 50% of the original property value.
The Court is persuaded that regardless of the “true” burden imposed by the Requirements, a potential buyer who has read them would be likely to fear a substantial degree of infringement on the land encumbered by a permanent easement. Even the plaintiffs’ expert, Mr. Foster, conceded that the Requirements (the existence of which he was unaware before trial) could reduce the value of the easement property by as much as 75%. Yet to assume that the defendants’ rights would be almost entirely extinguished — as the defendants insist — is also unwarranted. The evidence demonstrates (and the Requirements do not contradict) that the encumbered areas could be used as a parking lot or open space — likely uses even without the permanent easements — with relatively little interference. In light of these considerations, the Court finds the percentage of ownership rights taken by the plaintiffs on the land covered by the easement to be 75%.
The diminution in value of WBC’s property as a result of the permanent ease-
D. The Remainder
Finally, this Court must determine the diminution in value (if any) of the remaining property. Once again, the parties present dramatically opposing estimates of the dollar value of the property interests taken. Defendants, in rebanee on Mr. Stanhope’s report — that in turn relied on conceptual site plans prepared by Ja-By engineering — contend that the easements on Lots 1 and 8 effectively reduced the footprint (in square feet) of the buildings that those lots can accommodate. Specifi-caby, they hypothesize that the maximum budding size on Lot 1 was reduced from 80,500 to 61,250 square feet, while the maximum size on Lot 8 was reduced from 67,400 to 36,000 square feet. (Def. Ex. 17, Vol. II, Addenda pp. A33-A36.). In contrast, the plaintiffs, relying on the report of Mr. Foster — who, in turn, relied on conceptual site plans by EarthTech — assert that the presence of the easements does not alter the maximum building size on either lot. (Foster Rep. p. A-3 — A-4.)
The Court finds that the defendants have not carried their burden of showing, by a preponderance of the evidence, that the existence of the easements would reduce the maximum building size on Lot 1 or Lot 8. The experts’ projections concerning the size of the buddings which could be constructed consistent with the easement, the Requirements and market demand are too conjectural and hypothetical. 1
However, there is little doubt that the easements have caused diminution in the value of the remaining land. A reasonable buyer, after reading the “Requirements for Construction on or Near Company Fa-cihties,” would almost certainly anticipate that budding in the vicinity of the easement areas of Lots 1 and 8 would involve extra administrative “hassle,” and possible extra construction expenditures. For example, the Requirements contain restrictions on slope grading (Paragraph 3.6), crossing the pipeline with heavy equipment (Paragraph 3.7), storage facdities (Paragraph 3.11), and the timing of pipeline excavation (Paragraph 3.14).
Portland’s repeated attempts to downplay the importance of these Requirements — and to suggest that in practice, they impose only a trivial degree of inconvenience — are unpersuasive. Potential buyers may reasonably fear that the presence of underground pipelines on their property may make commercial construction more costly and inconvenient on the adjacent land.
See e.g., Clifford v. Algonquin Gas Transmission Co.,
The Court finds that the sole proven damages resulting from the permanent taking are the “stigma damages” associated with building on the unaffected land in Lots 1 and 8. In light of the likely effect of the Requirements on potential construction, the Court estimates a diminution of market value equal to 10% of the total value of the remaining land (i.e., that portion not subject to the permanent easement). For Lot 1, therefore, damages are calculated to be $40,400.00 (8.08 acres x $50,000/acre x 0.10). For Lot 2, severance damages are calculated to be $82,010.00 (10.67 acres x $30,000/acre x 0.10). Because Parcel 2 is not considered buildable land, there are no severance damages. Total damages to the remainder therefore amount to $72,410.
E. Temporary Easements
Although both experts agreed that the temporary easements lasted two years, they disagreed on the methodology for valuing them. WBC’s expert, Mr. Stan-hope, assumed that “[t]he effect of the temporary easement is the extension of the development of the subject by the legal two-year period of the temporary easement.” (Def.Ex. 17, Vol.I, p. 49). This is because typically buyers would (1) purchase a substitute property, (2) delay their purchase until the disruption is concluded, or (3) pay a discounted price to reflect the loss in utility during the easement term. He uses a discounted cash flow analysis of the three lots to show the market value effect of this two-year delay. After factoring in “holding costs,” an annual 3% appreciation rate, and the weighted average cost of capital, Mr. Stanhope estimates the value of the temporary easements on all three lots to be $103,116.00.
This valuation approach, while reasonable, has the following flaw. Even if a buyer had been prepared to purchase the lots on the date of the taking (which is dubious given the scant market interest in the lots), it is implausible that construction would have begun on the very same day the property was purchased. In the best of circumstances, there would be a substantial time lag between the purchase of property and beginning of construction. Even without an easement, a purchaser of raw land would have to expect up to eighteen months from the time of purchase until construction commenced. In light of the evidence (albeit sparse) that construction projects can take twelve to eighteen months of planning before the first shovel goes into the ground, there is simply no evidence in the record to support the assumption that the temporary easements probably caused a two-year delay in development.
Plaintiffs’ expert, Mr. Foster, took a different tack to valuation, stating: “The valuation of temporary easements is generally based on the income which would be required to support the market value of the underlying land. The total damages for one temporary easement are calculated using this income or rent and the length of time the easement will be [in] effect.” (Foster Report at 56). To calculate the value of the temporary easements on each lot, Mr. Foster multiplies the per-acre value of the land covered by the temporary easement by an annual rate of return of 10%.
The Court finds that Mr. Foster’s general approach — which calculates the rental value of the land affected by the temporary easement — is the more appropriate method to calculate the value of the temporary easements. Because the record does
The fair rental value of the temporary easement on Lot 1 is found to be $5050.00 (1.01 acres x $50,000.00/acre x 0.10) MULTIPLY BY 0.9 BECAUSE OF PERMANENT 10% DIMINUTION in 1999 and $5202.00 in 2000 (incorporating Mr. Stanhope’s assumption of 8% real appreciation), for a two-year total of $10,252.00. Using identical logic, the fair rental value of the temporary easement on Lot 8 is found to be $1740.00 (0.58 acres x $30,000/acre x 0.10) MULTIPLY BY 0.9 BECAUSE OF PERMANENT 10% DIMINUTION in 1999, and $1792.00 in 2000, for a two-year total of $3582.00. Mr. Stan-hope’s report stated that speculative land parcels such as Lot 2 did not appreciate over this period. Therefore, the fair rental value of the temporary easement on Parcel 2 is found to be $50.00 (0.51 acres x $983/aere x 0.10) in both 1999 and 2000, for a total of $100.00. The total value of the temporary easements, therefore, amounts to $13,884.
The one problem with Foster’s methodology is that it ignores the effect of the temporary easements on Lots 1 and 8 as a whole — i.e., development on both lots was essentially prevented for the entire two-year period. According to the covenants, construction on the buildings had to begin eighteen months after the hypothetical purchase. Therefore, because construction on the pipeline would delay construction of the buildings, a prospective purchaser would factor into the price a delay in development of at least six months. Using the rental approach, WBC must be compensated for the impact of the partial taking on the remainder of Lots 1 and 8 (i.e., the portion not encumbered by the easements) by calculating the value of the use of the lots for the six months of dead time. This amounts to $21,321 for Lot 1 (8.28 acres outside easement) x ($50,000/ acre) x (10 percent annual return / 2) x (1.03 adjustment for real appreciation) CALCULATE SEPARATELY FOR 25% OF PORTION B ACREAGE, AND 90% OF PORTION C ACREAGE, THEN ADD THEM TOGETHER; and $16,655 for Lot 8 (10.78 acres outside easement) x ($30,000/acre) x (10 percent annual return / 2) x (1.03 adjustment for real appreciation). CALCULATE SEPARATELY FOR 25% OF PORTION B ACREAGE, AND 90% OF PORTION C ACREAGE, THEN ADD THEM TOGETHER; The impact on the partial taking on the land not directly encumbered by the easement, therefore, totaled $37,976 for the six-month period. Because Lot 2 is unbuilda-ble, speculative land, there are no additional damages for the area outside the temporary easement.
Summing the figures calculated from the preceding analysis, the total compensation for the two-year temporary easements on WBC Property comes to $51,860.
E. Calculation of Interest
On July 9, 1999, this Court granted Portland condemnation rights to permanent and temporary easements across WBC’s property. Based on the preceding analysis, the total fair market value of the property interests taken (temporary easements, permanent easements, and diminution of value of the remainder) is found to be $152,677.00. WBC is entitled to interest on the damage award accruing from the date of the taking, July 1999, until the date of judgment.
See R.H. White Realty Co., Inc. v. Boston Redevelopment Auth.,
ORDER
This Court ORDERS that the plaintiffs shall pay the defendants $152,677.00 plus interest from the date of the taking.
SO ORDERED.
Notes
. In their proposed exhibits submitted to the court on November 9, 2001, Defendants submitted an Amendment to Mr. Stanhope’s Appraisal Report substantially revising their estimates of the before and after values of lots 1 and 8. In a pre-trial motion filed November 13, plaintiffs, vehemently asserting unfair surprise, argued that the report should be excluded for failure to comply with Fed.RCiv.P. 26(a)(2)(c). This Court granted the plaintiffs’ motion and excluded the supplementation because it was untimely disclosed and because the tardy disclosure would unfairly prejudice Portland.
