The Fifth Amendment permits the federal government to take personal property for public use, but requires payment of “just compensation.” Plaintiffs-appellants, Portland Natural Gas Transmission System and Maritimes & Northeast Pipeline, L.L.C. (“the Pipeline Companies”), took by eminent domain temporary and permanent easements on land in Haverhill, Massachusetts owned by defendant-appellee, WBC Extrusion Products, Inc. (“WBC”), to construct, operate and maintain a pipeline as permitted by the Natural Gas Act, 15 U.S.C. § 717f(h). A bench trial was held in the United States District Court for the District of Massachusetts to determine the amount of compensation due. The court determined that WBC was entitled to $152,677 plus interest. The Pipeline Companies appeal, claiming that the amount is not justified by the evidence produced at trial. We affirm.
I.Background
The facts of this dispute are detailed in the district court’s opinion,
Portland Natural Gas Transmission Sys. v. 19.2 Acres of Land,
II.Standard of Review
We review the district court’s findings of facts, including the amount of compensation due, for clear error. Fed. R.Civ.P. 52(a);
S. Nat. Gas Co. v. Land, Cullman County,
As this case is fact intensive, we note that the appellant has a difficult task of overcoming the trial court’s findings. Determining the value of real estate is not a science, and the decision of a lower tribunal is ordinarily not disturbed unless “grossly inadequate or excessive.” 4A Julius L. Sackman, Nichols on Eminent Domain § 17.1[4], 23.01 (rev.3d ed.2001) (hereinafter Nichols on Eminent Domain ).
III.Discussion
The land taken by the Pipeline Companies is in Massachusetts, and the
the value [of the land] before the recording of the order of taking, and in case only part of a parcel of land is taken there shall be included damages for all injury to the part not taken caused by the taking or by the public improvement for which the taking is made.
Mass. Gen. Laws ch. 79, § 12 (2002). Therefore, although the easement did not abrogate all of WBC’s bundle of rights, WBC is entitled to compensation for the decrease in value of the land encumbered by the easement as well as the decrease in value of the other land on the lots, or the “remaining land.” In addition, WBC is entitled to compensation for the temporary easement, or the two years when the Pipeline Companies were using part of WBC’s land for construction of the pipeline. The compensation awards for these three areas — the encumbered land, the remaining land, and the land temporarily taken — are the subject of this appeal.
A. Encumbered and Remaining Land
In 1998, the Pipeline Companies promulgated “Requirements for Construction On or Near Company Facilities” (the “Requirements”) to protect their pipelines from encroachment and disturbance caused by construction activity on or near the easement. WBC claimed that the easement together with the Requirements rendered the permanent easement area worthless.
2
The Pipeline Companies’ expert testified that the encumbered land was still useful and retained fifty percent of its value. The district court found that the Requirements diminished the value of the encumbered land beyond the Pipeline Companies’ suggestion of fifty percent. The court found that “a potential buyer who has read [the Requirements] would be likely to fear a substantial degree of infringement on the land encumbered by a permanent easement,” and determined that the encumbered land was reduced in value by seventy-five percent.
Portland Natural Gas,
1. Unfair Surprise
The Pipeline Companies claim that the effect of the Requirements on the value of the land was not litigated and was not considered an issue by the Pipeline Companies, and that they were therefore unfairly surprised and prejudiced when the district court awarded damages based on the Requirements. Appellants assert that the unfair surprise necessitates a new trial and that the district court lacked authority to enter judgment on the issue because it had not been squarely litigated. 3
The record indicates that the parties addressed the Requirements issue in their motions and papers before the court. WBC stated that the Requirements diminished the value of the land in question, while appellants emphasized that the effect of the Requirements can only be determined on a case by case basis. A motion in limine discussed and included the Requirements.
The Requirements issue also consumed extensive time at trial. In his opening statement, WBC’s counsel stated that the Requirements would be discovered by a reasonably prudent buyer, and that the “nub of the dispute” was what that buyer would do when faced with the Requirements. The Requirements were introduced into evidence without objection and outlined by Franklin Gessner, a witness for appellants. The Pipeline Companies’ expert, Steven Foster, had not been provided with the Requirements before making his estimation of damages, and stated that his figures might have been different had he considered the Requirements. The judge directly asked Foster several questions about a possible diminution associated with the increased construction costs and the hassle of dealing with the Pipeline Companies due to the Requirements. Foster responded that “on a rational level ... there would be [diminution],” although stating that he did not have market data to verify the judge’s intuition. Finally, during appellants’ closing argument, the judge stated that “the ordinary and reasonable person reading [the Requirements] would read them and say: I’ve got to worry about them.” With the plethora of evidence to the contrary, the Pipeline Companies’ argument that they were prejudicially surprised when the court determined diminution in value based on the effect of the Requirements must fail.
2. Impact of the Requirements
Under Massachusetts law, WBC is entitled to recover for all incidental effects of the public improvement that impair the value of its land.
Roman Catholic Bishop v. Commonwealth,
The trier of fact is “authorized to determine damages in an amount to which no expert testified by rejecting the precise amounts to which each expert testified.”
Nichols on Eminent Domain
§
17.1; see also Loschi v. Mass. Port Auth.,
A reading of the Requirements supports the court’s determination that the Requirements would decrease the price a reasonable buyer was willing to pay for the land. The Requirements provide that the encumbered land may not be used for structure, storage, or trees. Further, a landowner must submit proposed plans to the Pipeline Companies for authorization before beginning any work on or near the easement. Approval is also required for many other uses that would commonly be undertaken on a vacant industrial lot, including grade reduction, movement of heavy equipment across the easement, installation of electrical cables, power lines, and telephone lines, and blasting and excavation. Finally, the Pipeline Companies “reserve[ ] the right to set forth additional requirements if deemed necessary.”
The Pipeline Companies assert that the Requirements do not impact the land’s value because prospective buyers may choose to use the land in a way that conforms with the Requirements. We find the existence of such a buyer doubtful given the breadth of the Requirements and appellants’ discretion to modify them as it wishes. In addition, prospective owners would have to deal with the added burden of obtaining approval from the easement holder before undertaking any work on the vacant lot. The inference that the Requirements impact the property’s value is common sense: if a similarly-situated industrial lot exists that is free from the pipeline easement and the Requirements that go along with it, a potential buyer will likely forego the WBC lot in favor of the unencumbered lot. Therefore, WBC must lower its price to attract buyers. This is a logical consideration, and the fact that no expert spelled out this exact argument does not mean the judge could not arrive at it on her own.
The court heard conflicting evidence regarding the extent of the impact of the easement and Requirements on the land. The Pipeline Companies’ expert testified based on “experience and judgment” that the encumbered land was reduced in value
In light of all the evidence, the district court, acting as fact-finder, “made its determination[ ] based on its reasonable assessment of the conflicting evidence before it.”
Northeast Drilling, Inc. v. Inner Space Servs., Inc.,
B. Temporary Easement
WBC’s expert opined that the temporary easement effectively delayed the sale of, and any development on, the lots for the full two-year period. He testified that developers had verified this hypothesis, stating that so long as unencumbered lots were available, buyers would go elsewhere. The Pipeline Companies urged the court to simply award the rental value for those sections of each lot taken temporarily. The court did so but also awarded six months rental value for all of Lots 1 and 8. The Pipeline Companies challenge this additional award.
Compensation for a temporary taking is generally determined by “(1) ascertaining the value of the property for the period it is held by the condemnor; (2) ascertaining the difference in the value of the property before and after the taking; or (3) looking at the fair market rental value of the property during the time it was taken.” Nichols on Eminent Domain § 12E.01[1].
We find the district court’s determination a reasonable ascertainment of the value of the property taken. The court heard testimony that prospective buyers desire to begin construction within twelve months, and the court found that construction on WBC’s land generally would begin within eighteen months of purchase. Because the Pipeline Companies required access to a portion of the land, development likely could not begin until the end of the temporary easement. Thus, a potential buyer would wait until six months after the temporary taking had begun before purchasing the property, or would adjust his offer to reflect this waiting time.
IY. Conclusion
We affirm the decision of the district court determining just compensation. Costs are granted to appellee.
Notes
. The federal eminent domain statute involved here provides that "[t]he practice and procedure in any action or proceeding for [eminent domain] in the district court of the United States shall conform as nearly as may be with the practice and procedure in similar action or proceeding in the courts of the State where the property is situated.” 15 U.S.C. § 717f(h). Perhaps surprisingly, several circuits have read the phrase "practice and procedure” to encompass state substantive law as well as formal practice.
See, e.g., Columbia Gas Transmission Corp. v. Exclusive Natural Gas Storage Easement,
. The district court’s determinations that the highest and best use of Lots 1 and 8 is industrial use, and the highest and best use of Parcel 2 is open land, as well as its determination of the per acre value of the land, are not challenged.
. We note, without reaching the issue, that appellants' failure to ask for a continuance may be fatal to their claim of unfair surprise.
See United States v. Díaz-Villafañe,
