201 Mo. App. 8 | Kan. Ct. App. | 1919
— This is an action to recover unpaid broker’s commissions claimed to be due under a contract made by the American Surety Company with' an insurance broker, Edward E. Porterfield, Jr., relative to the latter’s procuring, and placing with defendant, the contract or right to furnish any part of the Bond required of the contractor selected to erect the new Missouri State Capitol.
After the broker bad performed bis part of the contract and, has received^ from defendant a part of
The Eorty-sixth General Assembly of Missouri by an Act approved March 24, 1911 (Laws 1911, p. 108), authorized the erection of a State Capitol and created a “State Capitol Commission Board” with power to prepare plans, submit bids and award a contract for the erection of said building; all of which things were duly and regularly done, and the “John Gill and Sons Company,’ a corporation, was awarded the contract. The law provided, and the contract required, that the contractor give a bond for the faithful performance of its contract, the latter fixing the penal sum of the bond to be given at one million,- three hundred and fifty thousand dollars. The contract was formally awarded to said John Gill & Sons Company November 21, 1913.
Prior to and at this time young Porterfield was busy on his own account as an insurance broker, endeavoring to secure the right to furnish said bond. With' "matters in this shape, Valentine, the resident. Vice President of the defendant at Kansas City, communicated with young Porterfield over the telephone and the latter was employed to get the bond or any part thereof for the defendant Surety Company. This telephone contract was on the 25th of November, 1913, confirmed by a letter from said Valentine which, among other things, stated that “if this Company acts a.s
There is no question but that young Porterfield performed hi's part of the broker’s contract and succeeded in obtaining one-third of said bond to be placed with the defendant Surety Company. Neither is there any controversy over the fact that the annual premiums charged by and paid to said defendant was $4517 and thirty-five per cent, of this sum or $1581 was paid by defendant each year to young Porterfield and his assignee up to November 28, 1916, as herein-above stated.
The application to the defendant Surety Company for the bond in question, which was the contract the broker was' to obtain for defendant, was signed by the Contractor on November 26, 1913. In it the Contractor agreed and bound itself to pay in advance to defendant the original premium or charge for ■ executing such obligation and continuing the same' in force for one year, and that it would “thereafter pay a like sum, annually, in advance, until the Surety shall be discharged and released from any and all responsibility upon each
The contract for the erection of the Capitol building was, concurrently with the Contractor’s bond, executed November 28, 1913. The former was very long containing, many things the Contractor was to do, not only with reference to the erection of the building-complete in every respect and of its necessary equipment and accessories with materials of the very best quality in strict accord with the plans and specifications, but also with reference to the payment for all materials and of all subcontractors, laborers and other employees, the obtaining of releases therefrom, the correction of imperfections, etc., all of which were declared to be essential parts of the contract. The contract further provided that time was of the essence thereof and that the building should be completed by July 1, 1916, and if if not completed by that date the Contractor should pay the State $250 per day liquidated damages for the failure to complete the same within that time, but provision was made whereby in case of failure to complete, from any cause entirely beyond the control of the Contractor, the State Capitol Commission Board would grant an extension of time. The contract required that the Bond given by the - Contractor should “guarantee the faithful, prompt and efficient performance by the Contractor herein of all of the covenants, the agreements, undertakings, conditions and requirements of this contract on the part of -the Contractor or of any sub-contractor’s assignee of the contract, according to the strict terms of this contract, or according to any change or modification thereof c- addition thereto, that may be made, as herein provided.” : 1
The building was not completed by July 1, 1916. However, it seems that extensions were asked and granted, and the record shows that finally an extension was granted by the Board from May 15 to August 22, 1917.
On September 8, 1917, the State Capitol Board, conditionally accepted said building with the exception of the things above specified and the replacing of certain cracked stones in the building with proper stones. The order of conditional acceptance recited that none of the provisions or requirements of the original contract, plans, specifications or bond, with reference to the exterior walls or any other part of said building, were waived, and that the conditional acceptance should not become effective until the consent in writing of the Contractor’s Sureties had been obtained, nor until the Contractor should obtain and deliver the releases hereinabove mentioned. Both the Contractor and the Board 'expressly stipulated that the bond should remain and continue in force to guarantee the performance of those things which were required to be performed within one year from the date of the acceptance, to-wit, September 8, 1917. This conditional acceptance was agreed to by the defendant Surety Company on September 12, 1917. The Board, on the 28th of September, 1917, waived all claim upon the Contractor for the $250 a day specified as liquidated damages for failure to complete the building in the time specified by the contract. (The court permitted the defendant to show that this $250 a day feature
Up to tbe time suit was brought no order of tbe Board was made discharging tbe Contractor’s bond or relieving tbe Contractor or its sureties from any further liability upon tbe contract or bond. Consequently, there is no -question but that tbe bond was in force throughout tbe year involving tbe commission for which suit is brought, namely, from November 28, 1916, to November 28, 1917.
The answer of defendant, among other things, set up that it “agreed to and did not charge or- collect any premium or premiums on said bond for a longer period than three years” and that “no premiums on said bond for the year beginning November 28, 1916, or for any time subsequent to that date, have been charged, paid, or collected by or remitted to this defendant.”
The evidence on both sides disclosed that defendant, at the solicitation of the contractor, relieved and excused the Contractor from further payments of premiums after November 28, 1916. The defendant was not compelled to forego such premiums but did so for reasons of its own and without consulting the broker or obtaining his consent thereto. t .
The case then, to restate it in a condensed form, is one wherein a broker has been employed to procure for defendant the contract or right to furnish the suretyship on a certain required bond, and the terms of the broker’s employment are that he is to “be paid a commission of thirty-five per cent, on the original premium and all renewal premiums received by this company as long as the bond remains in force” and that too whether the broker’s contemplated connection with the Company “continues throughout the life of the said bond or not.” The broker, concededly, obtained the contract for the suretyship, said contract expressly binding the one seeking the bond to pay the original premium on the date of the execution thereof which would continue the bond in force for a
Defendant’s position, when stated in its bare a:p.d plainest terms, is that as the broker’s contract says he was to get thirty-five per cent, “on the original and all renewal premiums received by this Company,” the contract should be regarded as rigidly limited to a strict.and literal interpretation of the word “received.“ Under this interpretation if the Company did not actually receive or collect a premium the broker was not entitled to his per centage thereon, even though the fact that the premium was not received was due wholly to the voluntary renunciation thereof by the Company. It is not conceived that the contract should be interpreted to mean that the obligation to pay the broker’s commission was to be left to the Company’s voluntary choice or volition, nor is this view in anywise weakened by the further provisions that the broker was to be paid his commissions ‘ ‘ as long as the' bond remains in force” and he Avas to receive his commissions whether his contemplated' connection with the Company continued “throughout the life of the said bond or not.” Similar contracts in reference to broker’s commissions have not been so interpreted. In Knisely v. Leathe, 178 S. W. 453, 455, the broker was employed to procure a contract, of sale which he did, and his commissions
In Currier v. Mutual Reserve, etc., Assn., 108 Fed. 737, the agent’s contract was that no commissions under the contract should be payable to plaintiff “unless the payment from which the same is to be allowed [i. e. premiums] has been received in cash” by the defendant. It was held that since the agent had performed his services and obtained the contracts he was employed to secure, the defendant principal could not escape payment of the commissions by refusing to enforce the contracts it had. To the same effect are the following authorities: Goldsberry v. Thomas, 178 Mo. App. 334, 338; Knisely v. Leathe, 256 Mo. 341, 372 (first appeal); Webster v. Meyers, 52 Mo. App. 338, 341; Reed v. Union Central Ins. Co., 61 Pac. 21, 23; Ketcham v.
The defendant sought to prove that a custom existed among surety companies 'whereby, in case the completion of a building is delayed through' no fault the contractor and no increased liability is incurred by the delay, no further annual premiums are charged during the additional time the bond is continued in force by reason of such delay. The alleged custom sought to be shown was not, primarily and directly, a custom among brokers and their principals whereby the former did not receive commissions on premiums voluntarily released for cause; but a custom on the part of Surety Companies in their dealings with contractors obtaining such companies as their surety, to waive the payment of premiums due for the time covered by delay in the completion of a building where the delay was without fault of the contractor and no increased liability was placed on the surety by reason of the delay. It will be observed, however, that the contract between the defendant Surety Company and the Contractor herein (which was the object for which the broker was employed and of the services which he rendered), was a straight, clear, out-and-out obligation on the part of the contractor to pay annual premiums so long as the bond remained in force. There was nothing therein providing for a release or adjustment of premiums due. Hence, in any suit based on such contract, no custom could be allowed to prevail over the explicit terms of the written agreement to pay. [Heffernan v. Neumond, 198 Mo. App. 667, 680; State ex rel. v. Public Service Comm., 269 Mo. 63, 75.] In other words, the defendant Surety Company could not have been compelled, by reason of any such alleged custom, to relieve the contractor from the payment of any premiums. Such a custom, even if pleaded and proven, would have proved unavailing to the contractor. Since the employment
It is argued that both the contractor’s contract to build the Capitol and the bond show that it was not contemplated that the bond would'' be in effect for a longer period than two-and-one-half years, and that whether the custom claimed was shown to be a custom in the legal sense or not, it should have been admitted as bearing upon what the broker and defendant meant when they made their contract. But the building contract, the contract for suretyship and the bond itself ail showed, and it was clearly in contemplation, that the bond might well continue in force much longer than that, and the contract with the broker also shows that such possibility was clearly in view. Consequently, anything short of a custom in the legal sense cannot be relied upon to enter into and form a part of the written contract between the broker and the defendant. If said contract was dealing with the broker’s right, to commissions on premiums which, under certain circumstances, might or might not be charged and collected by the Surety Company according as it saw fit, then, in order to escape the payment of the commission on premiums thus foregone, the Suretv Comnanv should have inserted a provision to that effect. [Heffernan v. Neumond, supra.] Instead of that the defendant contracts to pay a commission of thirty-five per cent, on
The contention that the agency contract young Porterfield made with defendant on December 4, 1913, superseded or merged the contract sued on, is wholly untenable. They were wholly separate and distinct, each dealt with different matters, and the agency contract in no way referred to the other contract which dealt solely with the obtaining of the State Capitol Bond. The two contracts show on their face- that they are separate, and the conceded conduct of the parties show the.y intended them to be separate. The .broker’s contract says-he was to receive commissions throughout the life of the bond regardless of whether he was in the company’s employ or not, the agency contract says the termination of his agency terminates his interest in commissions. The plaintiff’s assignor ceased to act as agent under the agency contract in February, 1914, and yet the Company continued to pay the commissions due under the broker’s contract concerning the State Capitol Bond during 1914, 1915 and 1916 to November 28th of that year. “Before one contract is merged in another the last must be between the same parties as the first, must embrace the same subject-matter and must have been so intended by the parties.” [13 Corpus Juris., 598; Maddins Admrs. v. Edmundson, 10 Mo. 643, 647.] The parties to the contract have, by their course of conduct, disclosed their own construction thereof, and. this should be followed. [Knisely v. Leathe, supra, 1. c. 458; Miller v. Pepperling, 185 Mo. App. 222, 228; St. Joseph Union Depot Company v. Chicago, etc., R. Co., 131 Mo. 291, 305.] Besides,, the broker’s contract was fully consummated before the agency contract was made. The former was, therefore, not merged into the latter. [England v. Houser, 163 Mo. App. 1, 8.]
But, without regard to all this and even if the admission of the evidence complained of was technically erroneous, we are of the opinion that it should not affect the case or cause a reversal of the judgment. This for the reasons following: The suit is upon au admitted written contract, and performance thereof by the broker on his part is conceded. It is also beyond question that the bond was in force during the time sued for; that the suretyship contract which was the object of the broker’s employment obligated the building contractor to pay premiums as long as the bond was in force; and the broker’s contract provided that the broker was to be paid commissions “as long as the bond remains in force” no matter whether the contemplated connection of the broker “continues throughout the life of the said bond or not.” It is, furthermore, beyond question that while the defendant did not “receive” the premium on which the commission sued for is based, yet the only reason was because the defendant made no charge against the Contractor therefor and did not see fit to enforce the contract which the broker’s services obtained for it. There was, therefore, an absolute failure to make out any of the pleaded defenses to the contract sued on. Hence, the plaintiff was entitled to a directed verdict. [Knisely v. Leathe, supra, l. c. 461.] This being so, the question of error in the admission of the testimony above considered is not material, since the plaintiff was not helped by it nor was the defendant harmed.
The judgment is affirmed.