103 A.D.2d 825 | N.Y. App. Div. | 1984
— In a claim to recover damages for breach of a public construction contract, the State of New York appeals from a judgment of the Court of Claims (Weisberg, J.), dated March 16,1983, which was in favor of claimant Port Chester Electrical Company, Inc. (Port Chester) in the principal sum of $116,737.51. 11 Judgment modified, on the facts, by reducing the amount awarded to the principal sum of $111,375.84. As so modified, judgment affirmed, with costs to the State, and matter remitted to the Court of Claims for entry of an appropriate amended judgment. H Claimant is an electrical contractor, which, in 1975 was awarded a contract by the State for electrical work on the renovation of the Bear Mountain Inn, located in Bear Mountain State Park, Bear Mountain, New York. Several other contracts were awarded at the same time to other contractors. The job was completed behind schedule. 11 After completing the work, Port Chester filed a claim against the State in the Court of Claims. Port Chester successfully argued that the State breached its contract by failing to properly plan and co-ordinate the work of the prime contractors. Port Chester alleged this failure resulted in extraordinary delay and that as a consequence it incurred excess costs in performing the work. After trial, the court found delay and interference on the part of the State and, utilizing the total cost theory of damages, awarded damages in the sum of $155,650.01, which it apportioned 75% against the State and 25% against another contractor, resulting in an award of $116,737.51, U On this appeal, the State concedes liability but disputes the damage award. Initially, the State contends that the Court of Claims improperly used the total cost theory. We disagree. Where a claimant sets forth its actual costs, together with any allowance for overhead and profit without regard to bid figures, such a theory of damages has been sanctioned (see Fehlhaber Corp. & Horn Constr. Co. v