—In an action, inter alla, to recover damages for breach of contract, the plaintiff appeals from an order of the Supreme Court, Kings County (Carson, J.), dated July 8, 1998, which, inter alia, granted that branch of the defendant’s motion which was for leave to serve an amended answer asserting the affirmative defense of Statute of Limitations, and thereupon granted that branch of the defendant’s motion which was for summary judgment dismissing the complaint.
Ordered that the order is affirmed, with costs.
The Supreme Court did not improvidently exercise its discretion in granting that branch of the motion of the defendant, New York City School Construction Authority (hereinafter the Authority), which was for leave to serve an amended answer to assert, inter alla, an affirmative defense based on the Statute of Limitations (see, CPLR 3025 [b]; Fahey v County of Ontario,
The defendant moved for summary judgment dismissing the complaint on the grounds that the notice of claim was not timely filed and, in any event, that the complaint was time-barred. In order for a notice of claim to be timely, it must be filed within three months after the accrual of the claim (see, Public Authorities Law § 1744 [2] [i]). Further, the timely filing of a notice of claim is a condition precedent to the commencement of an action against the Authority (see, Public Authorities Law § 1744; G.A. Contrs. v Board of Educ.,
The plaintiffs remaining contention is without merit. Sullivan, J. P., Friedmann, Feuerstein and Smith, JJ., concur.