Irwin A. POPOWSKY, Consumer Advocate, Petitioner v. PENNSYLVANIA PUBLIC UTILITY COMMISSION, Respondent.
docket nos. C-20028361, C-00015377 and C-20028177
Commonwealth Court of Pennsylvania
Decided July 13, 2004
853 A.2d 1097
Accordingly, we affirm the opinion of the trial court.
ORDER
AND NOW, this 12th day of July, 2004, the decision of the Court of Common Pleas of Northampton County in the above-captioned matter is affirmed.
Irwin A. POPOWSKY, Consumer Advocate, Petitioner v. PENNSYLVANIA PUBLIC UTILITY COMMISSION, Respondent.
Commonwealth Court of Pennsylvania.
Argued March 31, 2004.
Decided July 13, 2004.
Wayne T. Scott, Harrisburg, for respondent.
Anthony C. DeCusatis, Philadelphia, for intervenor, PA-American Water Co.
BEFORE: COLINS, President Judge, and MCGINLEY, Judge, and SMITH-RIBNER, Judge, and PELLEGRINI, Judge, and COHN, Judge, and SIMPSON, Judge, and LEAVITT, Judge.
OPINION BY Judge LEAVITT.
Irwin A. Popowsky, Consumer Advocate (Consumer Advocate), petitions for review of an adjudication of the Public Utility Commission (PUC) that adopted the recommendation of the Administrative Law Judge (ALJ) to dismiss three complaints filed against Pennsylvania-American Water Company (the Utility).1 The complain
BACKGROUND
Cindy Parks (Parks) initiated this case on May 3, 2001, by filing a complaint with the PUC averring that her hometown of Hickory, located in the Township, lacks public water that surrounding areas enjoy. Parks requested that the Utility be required to provide public water to all the residents of Hickory. Reproduced Record at 1a (R.R.-). The Utility filed an answer generally denying the allegations and requesting the PUC to dismiss Parks’ complaint.
Rick Minutello (Minutello) filed a complaint on July 18, 2002, in which he averred that the Utility planned to service all the homes on his street but refused to service his home. He requested that the PUC add his name to any litigation involving the Utility and its “refusal to service my growing area with water.” R.R. at 14a. The Utility filed an answer to the Minutello complaint denying the allegations,2 and asserting that the Utility was willing to implement an existing plan to provide water service to the Township if the terms and conditions of Rule 27 of the Utility‘s tariff3 were satisfied. Under the Tariff, contributions in aid of construction (customer contribution)4 would have to be made by each resident in the Township desiring service.
The Consumer Advocate intervened on behalf of Parks and filed its own complaint on August 21, 2002, alleging an inadequate water supply and poor water quality in the Township. It requested the PUC to order the Utility to provide an adequate supply of quality water to the Township without customer contribution. The Consumer Advocate also asserted that the Utility was in violation of Section 1501 of the Public Utility Code,
Because the parties failed to reach a settlement, the ALJ conducted evidentiary hearings in Hickory and in Harrisburg. The ALJ took evidence on the questions of whether the project sought by the complainants was actually needed and whether it could be done by the Utility economically.
Township residents testified that their well water was inadequate in quality and quantity. They attributed the water degradation to malfunctioning septic systems, the use of Township land by livestock and the history of underground mining in the area. The Township lacks public sewers and only recently has begun to permit on-lot sewage treatment systems. Residents also testified that some wells produce insufficient water for normal household use, and that at least one house was destroyed by fire when firefighters ran out of water while trying to extinguish the flames. Water for fighting fires is brought in by tanker trucks; the need for fire hydrants was supported by the Township‘s Director of Public Safety. The lack of a water system has adversely affected property values and stymied development, according to the residents who testified.7
The Township did not participate in the hearings before the ALJ. The record showed, however, that in 1989 the Township obtained public funding to partner with the Utility to install a water supply system in the Township. However, the plan was withdrawn by the Township Supervisors in the face of strong public opposition and litigation initiated to halt the project. This experience was in stark contrast to other projects in Washington County, where the townships and the Utility worked together to extend water lines to previously unserved residents. By partnering with these other townships,8 the Utility was able to extend its water lines without the need for customer contribution.
With respect to the economics of the water project sought by the complainants, the Consumer Advocate offered evidence to show that there were 568 potential water customers in the Township. This number was based upon the results of a survey of 701 residents. Of 530 residents who responded, 430 (or 81%) stated that they would connect to the public water system if customer contribution was not required. From these survey results, the Consumer Advocate “extrapolated” an estimated total of 568 customers in the Township. R.R. 857a.
The Utility produced evidence to show that the project would cost $6.3 million.9 Using the criteria in the PUC‘s regulation
Evidence was also produced to show the actual amount of the customer contribution for the project as calculated under the regulations and under Rule 27 of the Utility‘s tariff.13 Assuming the project would service 744 residential customers, each customer would have to contribute $2,255. Customers would be able to finance this payment by paying the Utility a one-third down payment and paying the balance over three years at an interest rate equal to the Utility‘s cost for long-term debt. The Utility also identified three banks in Washington County offering home equity loans at 4.75%.14 The pre-tax cost of the loan would be less than $30 per month. This, along with the average monthly water bill, would approximate the costs of the complainants’ present on-site water systems.
The ALJ concluded that the residents of the Township needed a dependable source of water; however, he concluded that this need did not translate into a duty by the Utility to extend its service without customer contribution. The ALJ rejected both the Consumer Advocate‘s estimate of 568 customers and the Utility‘s estimate of 74415 customers as mere speculation. The ALJ found that the number of bona fide applicants was unknown. In fact, not a single person had applied for service in the Township. The ALJ, thus, concluded that (1) the complaints were governed by the line extension regulations; (2) under those regulations, service could not be provided
The Consumer Advocate filed exceptions to the ALJ‘s Initial Decision, and the Utility filed reply exceptions. The PUC entered an Opinion and Order on August 8, 2003, denying the exceptions filed by the Consumer Advocate and adopting the ALJ‘s Initial Decision.17 This appeal followed.18
On appeal,19 the Consumer Advocate challenges the PUC‘s decision that Township residents must contribute to the cost of extending the Utility‘s main to the Township. His appeal raises six issues that may be summarized as follows: (1) whether the PUC erred in its application of the line extension regulation, thereby violating definitive Pennsylvania case law holding that a utility must bear the capital expense of extending service where there is a public need for that service; (2) whether the PUC improperly nullified its duty to adjudicate complaints by accepting the Utility‘s interpretation of Rule 27 of its Tariff; and (3) whether the PUC‘s adjudication is supported by substantial evidence. We consider these issues seriatim.
I.
The gravamen of the Consumer Advocate‘s appeal is that the PUC‘s line extension regulations are unlawful, as applied by the PUC in this case. It is undisputed that these regulations were adopted in compliance with the substantive and procedural requirements of the
These regulations, found at
The PUC spent three years finalizing the line extension regulations. They express the PUC‘s definitive statement of the “reasonable conditions” under which a public utility must provide main extensions to bona fide service applicants.25 In adopting these conditions, the PUC balanced the interests of the bona fide service applicants, the utility, and the utility‘s existing customers, explaining as follows:
In other words, the claim of an individual seeking the line extension must be balanced against the right of the public utility to remain financially viable and the right of existing customers to avoid subsidizing uneconomic line extensions for new customers.... Thus, the purpose of this rulemaking is to create a fair, reasonable and predictable economic standard to address this regulatory problem that will eliminate uncertainty and greatly reduce the litigation in this area.
27 Pa. B. 799, 800 (1997) (emphasis added). In short, new customers will be required to contribute to the cost of a utility‘s extension where necessary to protect that utility‘s existing customers from excessive rates or to preserve the financial viability of the utility.
The Consumer Advocate contends that this “break-even analysis,” which is the foundation of the line extension regulations, is not reasonable. He contends Section 1501 has been interpreted to require a utility to provide safe and adequate service to an area lacking public water without customer contribution where a public need exists. In other words, need alone is a sufficient basis for requiring the Utility to extend its water mains without charging any of the expense to the new customers, other than a monthly water bill. The PUC rejected this argument in its adjudication, noting it has consistently held that public need does not invalidate the regulation‘s requirement for customer contribution in some circumstances.26 PUC Opinion and Order at 5, 6.
To advance his “public need” argument, the Consumer Advocate relies principally upon the holding in Ridley Township v. Pennsylvania Public Utility Commission, 172 Pa.Super. 472, 94 A.2d 168 (1953).27
In Ridley, twelve homeowners sought an extension of a public water utility‘s facilities to a residential section of a township, a part of which was already served by the utility. In addition, the township requested the installation of fire hydrants. Despite evidence showing that the extension would entail the expenditure of less than one-fourth of one percent (0.25%) of the company‘s current and accrued assets, the PUC concluded that it was “not economically feasible” for the utility to extend its mains and did not require the extension. Ridley, 94 A.2d at 170. The service applicants appealed, and the Superior Court reversed. It found that under the Public Utility Code,28 a utility may not serve only the presently profitable territory covered by its franchise. The Superior Court reasoned as follows:
A public utility cannot collect the cream in its territory and reject the skimmed milk.... If a portion of the territory served is not profitable, but the entire service produces a fair return on the investment, the utility may still be required to serve the unprofitable portion, if the rendering of such service does not result in an unreasonable burden on its other service.
...
Ordinarily, it is not the business of the citizen or consumer to construct any part of a utility‘s system. There are, doubtless, instances where, under special circumstances, warranted by the evidence, the Commission may, in the exercise of its administrative discretion, withhold exercise of its power unless patrons offer to participate in the cost of construction.... But no inflexible rule can be laid down; participation in construction costs cannot be exacted indiscriminately; and it cannot be required upon a mere showing that an extension will not immediately produce an adequate profit.
Ridley, 94 A.2d at 171 (emphasis added) (citations omitted). Thus, the Superior Court held that affected members of the public “are entitled to fire protection and domestic water service without subsidizing a large and prosperous utility,” but it also clarified that customers may be required to participate in the cost of the construction of service extensions in appropriate circumstances. Ridley, 94 A.2d at 172.
The PUC and the Utility contend, and we agree, that Ridley does not stand for the broad proposition that utilities must provide service without customer contribution unless it would cause the utility material, economic harm.29 Ridley expressly
In any case, Ridley is not dispositive because it was decided prior to the promulgation of the line extension regulations, which govern customer contribution to extensions. The fact that a prior appellate case may support a narrow interpretation of a statutory provision does not bind the agency to that interpretation. A regulation must be followed even if prior case law supports a narrower interpretation. Elite Industries, Inc. v. Pennsylvania PUC, 574 Pa. 476, 483, 832 A.2d 428, 432 (2003).
Section 1504 of the Public Utility Code gives the PUC the express power to prescribe by regulations “just and reasonable standards ... to be furnished, imposed, observed and followed by any or all public utilities.” Rohrbaugh v. Pennsylvania Public Utility Commission, 556 Pa. 199, 206, 727 A.2d 1080, 1084 (1999) (quoting
The Commission‘s regulations are binding on this Court as long as they conform to the Commission‘s grant of delegated power, are issued in accordance with the proper procedures, and are reasonable. Moyer v. Berks County Board of Assessment Appeals, 803 A.2d 833, 842 (Pa.Cmwlth.2002) (citing Pennsylvania Human Relations Commission v. Uniontown Area School District, 455 Pa. 52, 313 A.2d 156 (1973)). When reviewing an agency‘s interpretation of its own regulations,30 courts follow the following two-step analysis:
First, the administrative interpretation will be given controlling weight unless it is plainly erroneous or inconsistent with the regulation. Second, the regulation must be consistent with the statute under which it is promulgated.
Moyer, 803 A.2d at 844. The PUC‘s interpretation of the line extension regulations is not clearly erroneous, and the regulation is consistent with the interpretation of Section 1501 of the Public Utility Code announced in Ridley and in subsequent case law.
The PUC, like any other agency, cannot ignore or fail to apply its own regulations, and those persons subject to the
Accordingly, we hold that the PUC did not err in its application of the line extension regulations to these circumstances and that the regulations do not conflict with Section 1501 of the Public Utility Code. The complaints were properly dismissed on this basis.
II.
The Consumer Advocate contends that the PUC has limited all line extension disputes to the “sole factor” of the “break-even analysis” codified in the regulations. He argues that this approach effectively precludes the filing of individual complaints under Sections 1505 and 701 of the Code,31 and, thus, it unlawfully restricts or nullifies the adjudicatory responsibilities with which the PUC has been charged by the legislature.
The Consumer Advocate advances a somewhat contradictory argument. First, he maintains that the PUC relinquished all discretion by adopting a rigid interpretation of the line extension regulations that makes the “break-even analysis” the determinative factor for customer contribution. Next, the Consumer Advocate argues that the PUC erred by not exercising its discretion to waive the requirements of the regulations based upon the “dire need” of the residents of the Township. More to the point, the Consumer Advocate‘s argument that the PUC has abdicated its responsibility to adjudicate consumer complaints is simply a rephrasing of its initial argument: where public need is established, the utility must bear all the costs of extending service.
The regulations promulgated by the PUC establish a workable and practical standard for line extensions. It establishes the maximum investment that the PUC can require a utility to invest in an extension.32 The regulations may generate factual disputes regarding the application of the regulation in a particular case and that, in turn, will generate the need for an adjudicatory action by the PUC. The fact that the PUC has established standards that give meaning to the requirement in Section 1501 that a utility establish “reasonable conditions” for extending service is not an abdication of responsibility. To the contrary, giving precision to what otherwise may be characterized as an open-ended statute33 is a
III.
Finally, the Consumer Advocate contends that the decision of the PUC is not supported by substantial evidence. The Consumer Advocate asserts that the PUC capriciously disregarded the evidence that showed there were hundreds of bona fide applicants in the Township. Further, there was no evidence that to require the Utility to spend $6.3 million would materially handicap the Utility.34 The Consumer Advocate also argues that even using the formula in the regulation, the evidence in the record supports the conclusion that the Utility could have constructed the project on a “break-even” basis.
The Consumer Advocate relies upon the “least-cost” principle to determine the cost of the construction and financing of the Township‘s water project. The “least-cost” approach35 would establish that the Utility could cover the costs of the project. This argument is grounded in the assumption that the Utility could obtain a low-interest loan from Penn Vest. A 1.387% interest rate for a Penn Vest loan, instead of the Utility‘s 4.85% weighted cost of debt, would change the outcome using the formula in the regulation. By using the Penn Vest interest rate in place of the Utility‘s 4.85% interest rate, the project would break even at 401 customers.
The ALJ and the PUC rejected the “least-cost” approach because it was inconsistent with the regulation. “Targeting” low cost debt to particular extensions would be unfair to other bona fide applicants that did not qualify for Penn Vest. PUC Opinion and Order at 12. Further, the PUC found that interest under a Penn Vest loan is 2.427%, not 1.378%, as asserted by the Consumer Advocate. Id.36 As noted by the Utility, using 2.427% in the formula and assuming 568 customers, the total of the resulting investment would be $5,183,000, far short of the $6.3 million needed for the project.
However, the ALJ found that there were no bona fide applicants, which renders the “least-cost” approach an abstract exercise. The ALJ rejected the number of applicants advanced by the Consumer Advocate at the hearings that was extrapolated from its survey. The ALJ found that because residents of the Township previously opposed the installation of a public water system, and the Township has not mandated connection to the proposed system, the number of residents posited by the Consumer Advocate was too speculative to use.
The line extension regulations define a “bona fide service applicant” as “[a] person
A bona fide service applicant under Rule 27 of the Utility‘s Tariff is specifically limited to a person who has applied for water service to an existing structure that is either the primary residence or place of business of the applicant and is located within the company‘s certificated service territory. In addition, the applicant must file a signed application for a new street service connection, extend the service line to the curb line of the premises, agree to separate any existing private well system from the public water system, and request water service to begin immediately upon installation of the street service connection. These tariff requirements for a bona fide applicant are absolute; deviation from an approved tariff is not permitted under any pretext. Philadelphia Suburban Water Company v. Pennsylvania Public Utility Commission, 808 A.2d 1044, 1054-1055 (Pa.Cmwlth.2002).
We cannot substitute our judgment for the factfinder. There was no evidence that a Penn Vest loan was available for the project sought by the complainants. Notably, no one from Penn Vest testified at the hearing. We agree also with the ALJ that the number of residents that would connect to the system was speculative. The
Accordingly, the Consumer Advocate‘s claim that the PUC‘s adjudication is not supported by substantial evidence must be rejected.
CONCLUSION
The Consumer Advocate believes that where a need for public utility service is demonstrated, then a utility must invest in an extension of service even where the utility will experience a negative return on this investment. This shortfall would have to be borne by the utility‘s shareholders or by its existing customers, who already generate profits for the utility. The Consumer Advocate may disagree with the reasonableness of the standards adopted by the PUC in its line extension regulation, but he cannot show that the PUC had exercised its statutory authority unlawfully. The standards adopted by the PUC, after much care and research, balance the competing interests affected by a service extension. We hold that the line extension regulations do not conflict with Section 1501 of the Public Utility Code,
For these reasons, we affirm the adjudication of the PUC.
ORDER
AND NOW, this 13th day of July, 2004, the order of the Public Utility Commission dated August 8, 2003, in the above-captioned matter is affirmed.
DISSENTING OPINION BY Judge SMITH-RIBNER.
I respectfully dissent from the majority‘s decision to affirm the order of the Public Utility Commission (Commission) because its application of the line-extension regulations at
Every public utility shall furnish and maintain adequate, efficient, safe, and reasonable service and facilities, and shall make all such repairs, changes, alterations, substitutions, extensions, and improvements in or to such service and facilities as shall be necessary or proper for the accommodation, convenience, and safety of its patrons, employees, and the public.... Such service and facilities shall be in conformity with the regulations and orders of the commission.
When interpreting Section 1501 and its predecessor statute,1 the appellate courts
In the “break-even” formula contained in
Here, the Commission‘s application of its regulations categorically excludes public need as an independent factor in determining whether customer contributions may be assessed for the benefit of the Pennsylvania-American Water Company (PAWC), and in doing so the Commission contravenes the mandate of Section 1501 of the Public Utility Code that a public utility “shall make all such repairs, changes, alterations, substitutions, extensions, and improvements in or to such service and facilities as shall be necessary or proper for the accommodation, convenience, and safety of its patrons, employees, and the public.” By entirely excluding public need from its consideration, the Commission has applied its regulations in a manner that represents an abuse of discretion and reversible error.
This conclusion does not advance the notion that a public utility must extend service in all cases no matter what the cost or foreclose the notions that the costs of an extension project may in some cases outweigh any professed public need for increased service or that the Commission may employ its break-even analysis in esti
Ordinarily, it is not the business of the citizen or consumer to construct any part of a utility‘s system. There are, doubtless, instances where, under special circumstances, warranted by the evidence, the Commission may, in the exercise of its administrative discretion, withhold exercise of its power unless patrons offer to participate in the cost of construction. But no inflexible rule can be laid down; participation in construction costs cannot be exacted indiscriminately; and it cannot be required upon a mere showing that an extension will not immediately produce an adequate profit. (Citation omitted.)
On the record before the Court, there can be little doubt that those portions of Mt. Pleasant Township requesting service are in need of a public water system. The record contains abundant evidence of contaminated wells and of inadequate supplies of water for drinking and fire protection. The degree of public need in this case is not one of mere accommodation or convenience but one affecting public health and safety, and the Commission erred in concluding that absent customer contributions PAWC need not extend water service to the affected area. Instead, the Commission should have granted a waiver of its regulations and then determined the degree of service extension required. The Commission‘s order should be vacated and the case remanded for determination of those requirements.
President Judge COLINS joins in this dissent.
Seneca Lyn GAYLORD, a minor, by her parents and natural guardians, Jennifer GAYLORD and Robert Gaylord, and Jennifer Gaylord and Robert Gaylord, individually, Appellants v. MORRIS TOWNSHIP FIRE DEPARTMENT a/k/a Morris Fire Department.
Commonwealth Court of Pennsylvania.
Argued June 10, 2004.
Decided July 13, 2004.
Notes
Duty of public utility to make line extensions.
Each public utility shall file with the [PUC], as part of its tariff, a rule setting forth the conditions under which facilities will be extended to supply service to an applicant within its service area. Upon request by a bona fide service applicant, a utility shall construct line extensions within its franchised territory consistent with the following directives:
(1) Line extensions to bona fide service applicants shall be funded without customer advance if the annual revenue from the line extension will equal or exceed the utility‘s annual line extension costs.
(2) If the annual revenue from the line extension will not equal or exceed the utility‘s annual line extension costs, a bona fide service applicant may be required to provide a customer advance to the utility‘s cost of construction for the line extension. The utility‘s investment for the line extension shall be the portion of the total construction costs which generate annual line extension costs equal to annual revenue from the line extension. The customer advance amount shall be determined by subtracting the utility‘s investment for the line extension from the total construction costs.
(3) The utility‘s investment for the line extension shall be based on the following formula, where X equals the utility‘s investment attributed to each bona fide applicant:
X = [AR-OM] divided by [I + D]; and,
AR = the utility‘s annual revenue
OM = the utility‘s operating and maintenance costs
I = the utility‘s current debt ratio multiplied by the utility‘s weighted long-term debt cost rate
D = the utility‘s current depreciation accrual rate
Every public utility shall furnish and maintain adequate, efficient, safe, and reasonable service and facilities, and shall make all such repairs, changes, alterations, substitutions, extensions, and improvements in or to such service and facilities as shall be necessary or proper for the accommodation, convenience, and safety of its patrons, employees, and the public. Such service also shall be reasonably continuous and without unreasonable interruptions or delay. Such service and facilities shall be in conformity with the regulations and orders of the commission. Subject to the provisions of this part and the regulations or orders of the commission, every public utility may have reasonable rules and regulations governing the conditions under which it shall be required to render service. Any public utility service being furnished or rendered by a municipal corporation beyond its corporate limits shall be subject to regulation and control by the commission as to service and extensions, with the same force and in like manner as if such service were rendered by a public utility. The commission shall have sole and exclusive jurisdiction to promulgate rules and regulations for the allocation of natural or artificial gas supply by a public utility.
27. MAIN EXTENSIONS FOR BONA FIDE SERVICE APPLICANTS
27.1 General Provisions
* * *
(A) (2) When the costs of the main extension exceed the Company Contribution ... then such extension will be made under and pursuant to the terms of an Extension Deposit Agreement for Bona Fide Service Applicant.... The construction of facilities to serve such Bona Fide Service Applicant will not commence until an Extension Deposit Agreement for Bona Fide Service Applicant has been executed and all applicable terms and conditions therein have been satisfied by the Applicant. The introductory rate on a Penn Vest loan is 1.378% but, thereafter, the interest rate increases to 2.774%, which makes the average 2.427%.
* * *
(B) The Company shall have exclusive right to determine the type and size mains to be installed and the other facilities required to render adequate service.
Average Annual Revenue minus $__________
Operation and Maintenance Expenses $__________
Subtotal $__________
Divided by Depreciation Rate and weighted cost of debt. __________%
Company Investment $__________
Rule 27(D) (2), Supp.No. 151, Tariff Water-Pa. P.U.C. No. 4.
