190 Iowa 1340 | Iowa | 1921
— A petition for change of road location, signed by the required number of citizens, was filed with the board of-
The county engineer, upon the direction and order of the board, made a survey of the proposed road, located same, and filed his report thereon. Subsequently to the filing of the engineer’s report, plaintiff filed his claim for damage with the board in the sum of $300, which claim was allowed by the board in the sum of $475. Subsequently, plaintiff filed an amendment to his claim, asking that the board set aside its former order and grant a rehearing on the question of his damage, which was denied. During the proceedings, no complaint was made by plaintiff as to the sufficiency of the petition asking for a change and relocation of the highway.
It is the contention of appellant that the petition for relocation filed with the board is insufficient, and that no commissioner was appointed by the board to locate the highway. The answer and return of the writ by defendants alleged that the return of the auditor shows that the board followed the provisions of Sections 1527-rl et seq., Supplemental Supplement to the Code, 1915; that a notice was served upon plaintiff, Polk; that, subsequently thereto, and within the time fixed by law, plaintiff filed a claim with the board; that, prior to the filing of said claim by plaintiff, the report of the county engineer was on file in the auditor’s office, showing the precise location of the highway; and that the plat accompanying said report showed the location of said highway from the beginning and end thereof, in so far as the board of supervisors acted or pretended to act under the petition filed; that, on the day fixed for hearing by the board, plaintiff presented his claim in the matter of his
Section 1527-rl, Supplemental Supplement to the Code, 1915, provides:
“Ten freeholders of any county by a petition to the board of supervisors of said county or the county engineer may, at any time, recommend the expediency and advisability of changing the course of any part of any road or stream within any county, in order to avoid unnecessarily expensive bridges, grades or railroad crossings, or to straighten any road, or to cut off dangerous corners on the highway or to widen any road above statutory width, or for the purpose of preventing the encroachment of a stream upon a public highway, specifying clearly the change recommended, and whether any part of any highway already established should be vacated and abandoned, and what part. The board may, thereupon, order the engineer to make a survey and report on such proposed change, and in order to comply with such order, the engineer shall have a right to enter upon the premises proposed to be taken and make said survey. If, from a consideration of the survey and report on such proposed change, the board deems the change advisable, it shall have power to buy such right of way and take conveyance thereof in the name of the county and to pay for the same out of either the county road or bridge fund or out of both of said funds, as may appear advisable.”
The petition might have been drawn with more certainty as
No portion of the alleged abandoned highway was affected by the resolution of the board of supervisors, and no portion of the abandoned highway affected any record owner other than the plaintiff, Polk.
A substantial compliance with the provisions of the statute is required, but it is not necessary to follow the precise language of the statute in drafting petitions for the establishment or relocation of roads and highways. A petition is sufficient if it follows the- statutory form in substance, expressing with reasonable certainty the action desired. Harris v. Board of Supervisors, 88 Iowa 219, 223; Lehmann v. Rinehart, 90 Iowa 346, 349; McCollister v. Shuey, 24 Iowa 362.
The record in the instant case shows' a compliance with the
The relief demanded was understood by every party in interest, and no irregularities or nonconformities to the statutory requirements in the relocation of a road are disclosed by this record. The judgment of the trial court is, therefore,— Affirmed.