Opinion
There are two issues in these cross-appeals from a judgment in favor of Matthew Poire against C.L. Peck/Jones Brothers Construction Corporation, Inc. (Peck/Jones) for injuries suffered in a construction accident. Peck/Jones argues the trial court erred by refusing to reduce the judgment by an offset for amounts paid to plaintiff by settling defendants. Plaintiff argues that he was entitled to costs, including expert witness fees, under Code of Civil Procedure section 998 1 , because his judgment was more than his statutory offer to settle. He contends that the trial court erred in concluding that the amount of workers’ compensation benefits received by a plaintiff must be deducted from the judgment before determining whether plaintiff received a more favorable result within the meaning of section 998.
We conclude that Peck/Jones was entitled to an offset under established precedent interpreting section 877, subdivision (a). We also conclude that Mr. Poire was entitled to expert witness fees and costs under section 998.
Factual and Procedural Summary
In February 1990, the University of California, Los Angeles Medical Plaza and adjacent facilities were under construction. Peck/Jones was the general contractor on the project. Mr. Poire was employed by Merco Construction Engineers, the contractor for site development and landscape work. Tri-County Sandblasting Corporation was the sandblasting subcontractor. Morley Construction Corporation was another general contractor for construction of an adjacent below-grade parking facility.
Plaintiff walked down a plank ramp running from a window in the medical building to the ground level below. He slipped on sand and fell to *1836 the ground, sustaining injuries. An action for personal injuries on behalf of Mr. Poire and for loss of consortium by his wife, Brenda Poire, was brought against Peck/Jones, Morley, and Tri-County. 2
Merco’s insurer intervened for workers’ compensation benefits paid plaintiff. Before trial, Peck/Jones purchased the workers’ compensation lien in the amount of $82,424.48. Thereafter, plaintiff served an offer to compromise pursuant to section 998 on Peck/Jones, offering to settle the action for $149,999.99. The offer was not accepted.
Morley settled with plaintiff for $30,000 and Tri-County settled with him for $15,000. Each settling defendant brought a motion for determination that its settlement was in good faith (§ 877). Both motions were granted.
Trial proceeded against Peck/Jones. The jury returned a special verdict, awarding plaintiff $202,000 in economic damages and $83,000 in noneconomic damages. The jury apportioned fault as follows: Mr. Poire, 20 percent; Peck/Jones, 40 percent; Merco, 40 percent; Morley, 0 percent; and Tri-County, 0 percent.
The parties proposed alternative judgments based on the special verdict, with different calculations of the damages awarded. Judgment on special verdict awarded plaintiff $114,000 plus interest against Peck/Jones.
Peck/Jones moved to set aside the judgment (§§ 663, 663a) on the following grounds: (1) that it was entitled to a setoff for the settlements paid by Morley and Tri-County under section 877, subdivision (a); (2) the court misapplied Proposition 51 (Civ. Code, § 1431.2) in the award of noneconomic damages; and (3) the date from which interest on the judgment ran was incorrect. Plaintiff filed an application for expert witness costs and fees under section 998.
The trial court denied both posttrial motions. It found “there should be no set-off to defendant for the settling defendants who were found by the jury to have no liability.” In denying plaintiff’s motion for expert witness costs and fees, the trial court concluded “it would be unfair and unequitable to apply the Manthey
[Manthey
v.
San Luis Rey Downs Enterprises, Inc.
(1993)
The trial court entered an amended judgment on a form supplied by counsel for plaintiff. The amended judgment awarded damages as follows:
“1. Plaintiff’s total economic damages $202,000.00 “2. Less plaintiff’s comparative negligence (20%) - 40,400.00 “3. Less full amount of benefits paid under Workers Compensation system - 82,424.48 “4. Add defendant C.L. Peck/Jones Brothers Construction Corporation’s share of noneconomic damages (40% x $83,000.00) + 33.200.00 “5. Net monetary judgment gainst Defendant C.L. Peck/Jones Brothers Construction Corporation $ 112.375.52’
Peck/Jones filed its notice of appeal and Mr. Poire filed his notice of cross-appeal.
I
Section 877 Setoff
Is a nonsettling defendant entitled to a setoff from plaintiff’s award of economic damages in the amount of settlements paid prior to trial by other defendants, despite the jury’s finding that the settling defendants had no fault for plaintiff’s injuries? The answer requires examination of two independent statutory schemes—section 877 and Civil Code section 1431.2, the latter a provision of the Fair Responsibility Act of 1986 (popularly known as Proposition 51). As we shall explain, we conclude that a setoff is required under section 877 because Proposition 51 did not change the law with respect to economic damages.
Section 877 provides in pertinent part: “Where a release, dismissal with or without prejudice, or a covenant not to sue or not to enforce judgment is given in good faith before verdict or judgment to one or more of a number of tortfeasors claimed to be liable for the same tort ... it shall have the following effect: ["ftl (a) It shall not discharge any other such party from liability unless its terms so provide,
but it shall reduce the claims against the others in the amount stipulated by the release, the dismissal or the covenant, or in the amount of the consideration paid for it whichever is the
greater.”
*1838
(Italics added.) “ ‘[T]he major goals of the [legislation enacting section 877] are, first, equitable sharing of costs among the parties at fault, and second, encouragement of settlements.’ [Citation].)”
(Tech-Bilt, Inc.
v.
Woodward-Clyde & Associates
(1985)
Civil Code section 1431.2. provides in pertinent part: “(a) In any action for personal injury . . . , based upon principles of comparative fault, the liability of each defendant for non-economic damages shall be several only and shall not be joint. Each defendant shall be liable only for the amount of non-economic damages allocated to that defendant in direct proportion to that defendant’s percentage of fault, and a separate judgment shall be rendered against that defendant for that amount.” (Italics added.)
Our Supreme Court thoroughly examined the legislative history of Civil Code section 1431.2. in
Evangelatos
v.
Superior Court
(1988)
The interplay between section 877 and Civil Code section 1431.2. has been examined by a number of courts. (See
Conrad
v.
Ball Corp.
(1994)
Peck/Jones argues that it is entitled to a setoff of 70.88 percent of the settlements because the percentage of the jury’s award of total damages ($285,000) attributable to economic damages ($202,000) is 70.88, under the formula adopted in Espinoza v. Machonga, supra, 9 Cal.App.4th at p. 277.) Mr. Poire argues that Peck/Jones is not entitled to any setoff for the $45,000 in settlement proceeds from Morley and Tri-County because the jury found these defendants had no fault. The trial court adopted this position in denying the setoff.
As we have seen, Proposition 51 did not change the traditional rules of joint liability with respect to an award of economic damages, as opposed to noneconomic damages. Therefore, we must examine whether a setoff under section 877 is available where the settling defendant is ultimately found to have no fault.
In
Knox
v.
County of Los Angeles
(1980)
The appellate court reversed, reasoning that section 877 “does not require any defendant to prove that settling codefendants were in fact liable, only that they were ‘claimed to be liable’ for the same tort. The trial court’s purported finding that ‘[t]here was no participation by [the market] in the arrests’ is, therefore, irrelevant, even if it is construed as a finding that Market Defendants were not joint venturers, coconspirators, and instigators of the arrest. This is clear from the decision of our Supreme Court in
American Motorcycle Assn.
v.
Superior Court
(1978)
The
Knox
court also relied on
Jaramillo
v.
State of California
(1978)
The Ninth Circuit, applying California law, reached the same result in
Vesey
v.
United States
(9th Cir. 1980)
On appeal, the plaintiffs argued that no setoff should have been allowed because the airline was found not liable. (
At oral argument, Mr. Poke’s counsel suggested that Peck/Jones should have sought an allocation between economic and noneconomic damages at the section 877.6 hearing. We take this argument to be that the failure of
*1841
Peck/Jones to do so constituted a waiver of its right to raise the issue later. If this is the argument made by Mr. Poire, we disagree. What is significant is the jury’s allocation of damages. In
Conrad
v.
Ball Corp., supra,
We conclude the trial court erred in rejecting Peck/Jones’s request for a setoff from the award of economic damages for the amount paid by the settling codefendants. We apply the formula developed by the court in
Espinoza
v.
Machonga, supra,
II
Section 998
In his cross-appeal, Mr. Poire argues that the trial court erred in deducting the amount of the workers’ compensation lien purchased by Peck/Jones from the judgment before determining that Peck/Jones obtained a more favorable judgment than the settlement offered within the meaning of section 998. The trial court denied Mr. Poke’s application for expert witness fees and costs based on this calculation.
Section 998, subdivision (d) provides: “If an offer made by a plaintiff is not accepted and the defendant fails to obtain a more favorable judgment, the court in its discretion may require the defendant to pay a reasonable sum to cover costs of the services of expert witnesses, who are not regular employees of any party, actually incurred and reasonably necessary in either, or both, the preparation or trial of the case by the plaintiff, in addition to plaintiff’s costs.” In
Culbertson
v.
R.D. Werner Co., Inc.
(1987)
Peck/Jones argues that Manthey should not be applied retroactively to this action. The case was decided on June 16, 1993. That was after the accident and after the section 998 offer in this case, but only a short time before the judgment was entered. The trial court expressly declined to give Manthey retroactive effect. Mr. Poire argues that Manthey does not fall within the narrow exceptions to the general rule that decisions are to be applied retroactively. 3
“Judicial decisions, particularly those in tort cases, are generally applied retroactively.
(Newman
v.
Emerson Radio Corp.
(1989)
We follow the reasoning of the Manthey court in concluding that the section 998 determination should be made before workers’ compensation benefits are deducted from the judgment. Our conclusion is not altered by Peck/Jones’s reliance on Engle v. Endlich, supra, 9 Cal.App.4th 1152. That opinion does not address the issue presented in Manthey. We see no reason not to apply the general rule of retroactivity to this case. The trial court erred in ruling that Mr. Poire is not entitled to expert witness fees and costs under *1843 section 998 because the correct amount of the judgment, before reduction for the amount of workers’ compensation benefits paid, is as follows:
Economic damage award Minus plaintiff’s comparative negligence (20% x $202,000) Minus setoff for settlements by other defendants Total economic damages = Plus Peck/Jones’s share of noneconomic damages Total amount of judgment before workers’ compensation deduction = $202,000.00 - 40,400.00 - 31.896.00 $129,704.00 33.200.00 $162,904.00
This amount exceeds the $149,999 settlement offer made pursuant to section 998. We remand the matter to the trial court for its exercise of discretion (§ 998, subd. (d)) as to Mr. Poire’s entitlement to recover expert fees and costs.
Disposition
The judgment is reversed and the matter remanded for further proceedings consistent with the opinions expressed in this decision. Each party is to bear its costs on appeal.
Hastings, J., and Klein (Brett), J., * concurred.
Notes
All further statutory references are to the Code of Civil Procedure unless otherwise stated.
We are informed that Mrs. Poire’s action for loss of consortium was dismissed before trial.
Mr. Poire does not challenge the amount of the credit for the workers’ compensation lien. (Cf.
Engle
v.
Endlich
(1992)
Judge of the Municipal Court for the Los Angeles Judicial District sitting under assignment by the Chairperson of the Judicial Council.
