54 W. Va. 272 | W. Va. | 1903
Lead Opinion
The Fairmont Plumbing Cpmpany and L. E. Carr entered into a written contract by which said company contracted to construct and complete a plumbing system and hot water heating plant in a certain house belonging to said Carr in Fairmont for a
I will not argue the caso upon the volume of depositions of conflicting evidence. As in other cases several times stated the design in requiring of this Court written opinions is not to detail evidence going to establish facts, but to state ultimate facts, so far as necessary to make intelligible the principles of law ruling the case. The judge of'the circuit court found that the execution of the contract was delayed to the damage of the defendant, and also that the work was never completed as demanded by the contract, and its execution defective. We cannot upon conflicting evidence reverse this finding. I regard the finding correct. But if this were not so, there is a legal principle which would affirm the decree. The contract provides for partial payments during the execution of the work, and then says, “The final payment shall be made when the work is completed satisfactory to owner and architect.”
The owner and architect condemned the work as incomplete and defective and complained of delay; they both expressed dissatisfaction with it repeatedly; the architect refused to give an order for final payment; and both owner and architect, under oath as witnesses, continue to express dissastifaction and say that the work was delayed to the loss of the defendant, ill-executed and incomplete. It does not appear that this dissatisfaction of owner and architect was fraudulent or collusive, but I think well grounded. Under the clause of the contract just stated, upon authorities given in Barrett v. Coal Company, 51 W. Va. 416, the decision of the circuit court must stand.
Decree affirmed.
Rehearing
ON REHEARING.
A petition for rehearing calls for an extension of the above opinion. That the principle stated in it is sound as regards sale
How to the authorities. Whilst some what variant, the weight of them supports this view. In 6 Cyc. 88 we find it stated that it has been held by eminent courts that in special building contracts the builder cannot recover anything, unless he has performed the work according to contract; but that the later rule is not to allow the owner to keep the work and not pay anything, but recovery of the. real worth of the work done may be had by showing substantial performance; but' this is added: “The doctrine, however, of ‘substantial performance’ does not apply when the omissions or departures from the contract are intentional, or so substantial as not to be capable of remedy, so that an allowance out of the price would not give the owner what he contracted for, or where the contract must be performed to the satisfaction of the owner or architect.” Hote, that the last clause makes such a contract as we have in hand an exception from the rule of “substantial performance.” Why? Because so the parties wrote their contract, and courts cannot make a new or different one. This contract, is in this respect not different from
There being no difference in this respect between contracts touching chattels and building contracts, I feel authorized to repeat the statement in the original opinion, that in the application of the clause that the work should be satisfactory to the architect, the cases of Barrett Coal Co., 51 W. Va. 416, and Osborne v. Francis, 38 Id. 312, are binding authority. I will add that I can not see any logical difference, in principle, between the case before us, and the case where the certificate or decision of an engineer is made by the contract final and conclusive as to the completion of the work, or its character, or even its quantity. He
A unmber of cases lajr down this principle. Kidwell v. Railroad Co., 11 Grat. 676; B. & O. R. Co. v. Polly Woods, 14 Id. 447; Chicago. R Co. v. Price, 132 U. S. 185; Kilberg v. U. S. 97 U. S. 398.
There are some cases adverse to the position taken in this opinion, but not many or sound. Some seeming to be such on first blush are not when, scrutinized. I now refer to some cases cited for the Plumbing Company. In Pope Iron Co. v. Best, 14 Mo. App. 502, the contract guaranteed “the furnace to work satisfactorily.” The court said that did hot mean that it would work to satisfaction of the defendant, but to work reasonably well. A great difference. The contract was satisfied if the furnace worked well in the opinion of the jury. That is only the usual contract. This contract says the satisfaction of the defendant and architect must be attained, not that of a jury. Shupe v. Collender, 15 Atl. 405, has no application. It only holds that where a purchaser of an article is not satisfied, this does not disable him from keeping it and recouping the price for defect under tire warrant. Hawkins v. Graham, 14 Am. St. R. 422, does not fit this case. The contract said that the heating apparatus should be of first class workmanship, and in “the event of the system proving satisfactory”, to be paid for, not saying proving satisfactory to the plaintiff; and further, it added the words “or the work demonstrated.” The court said this offered an alternative ; that is, it let in proof of the sufficiency, and did not limit to the defendant’s approval. Carrol v. Welch, 26 Texas 147, involved no clause such as does this case; nor did Nelson Co. v. Mitchell, 38 Mo. App.; nor Fleshman v. Miller, Id. 177. Chism v. Shipper, 51 N. J. Law 1, 14 Am. St. R. 668, fully recognizes the force of the clause in question as above stated, but holds that a fraudulent withholding of approval defeats it, which we do not
Wyckoff v. Meyers, 44 N. Y. 143, holds thatwhen the certificate is given it binds the owner of the building in the absence of fraud. It is authority for the contention of this opinion. Smith v. Brady, also cited for the appellant, according to the syllabus in 72 Am. D. 442, says that when a contract requires “complete performance or the production of an architect’s certificate of performance”, there can be no recovery, “unless such performance is proved or such' certificate produced.” Of course, because by the contract either answers. But the case in the state report, 17 N. Y. 173, shows that the syllabus is not at all as given in 72 Am. D.; the contract- was not as there given. It is a strong case for the position I have taken. Buildings were to be built “to the entire satisfaction of architects”, and balance of pajunent “when all the work shall be completed and certified by the architects.” The opinion says". “Assuming that the contracts had been so far performed as to justify the plaintiff in treating them as substantially executed, as I incline to think they were, yet the final payment for the work was to be made when it was completed and a certificate of the architects to that effect ob
Thus, it appears that onfy fraud can excuse the plaintiff from meeting the satisfaction of Mrs. Carr and the architect. There is no proof of fraud. The evidence shows that the architect and Mrs. Carr’s son acted bona jide. The contract demanded that the heating apparatus should give 70 degrees in zero weather. It was tested when the themometer was 2 or 3 degrees above zero, and it furnished heat only up to 48 or 50 degrees. Complaint was made of insufficient heat by the tenants. The store rooms and barber shop and upper rooms were worthless without adequate heat. The fine new house would be greatly damaged by this defect. The c®mpany would not test the heat, though, re
Affirmed.