PLUMBERS LOCAL NO. 75, and Richard C. Lansing, Plaintiffs-Respondents,† v. John COUGHLIN, Secretary of Department of Industry, Labor & Human Relations, Defendant-Appellant.
No. 89-1155
Court of Appeals
Oral argument May 16, 1991.—Decided January 23, 1992.
481 N.W.2d 297
†Petition to review denied.
For the plaintiffs-respondents the cause was submitted on the briefs of Judith E. Kuhn of Plumbers Local 75 and Matthew R. Robbins and John J. Brennan of Previant, Goldberg, Uelmen, Gratz, Miller & Brueggeman, S.C. of Milwaukee and orally argued by Judith E. Kuhn.
Brief of amicus curiae submitted on behalf of Plumbing & Mechanical Contractors Association of Milwaukee & Southeastern Wisconsin (PMC) and orally argued by Thomas W. Godfrey of Godfrey, Trump & Hayes of Milwaukee.
Before Gartzke, P.J., Dykman and Sundby, JJ.
SUNDBY, J. The Department of Industry, Labor and Human Relations (hereafter “department” or DILHR) administers the Wisconsin Manufactured Building Program which it bases on its administrative
THE ISSUES
The ultimate issue is whether the department may approve manufactured housing for sale and installation in the state, irrespective of
The plaintiffs-respondents, Plumbers Local No. 75, and a Wisconsin-licensed journeyman plumber (“Plumbers“), contend that nothing in the department‘s administrative rules or the Manufactured Building Code makes
The Plumbers contend that the department may not enact an administrative rule which conflicts with state law. Therefore, the second sub-issue is whether the Manufactured Building Code authorized the department to adopt its administrative rules which it has interpreted as permitting it to approve, for sale and installation in the state, manufactured housing in which the plumbing has been installed without complying with
I. DEPARTMENT‘S CONSTRUCTION OF ADMINISTRATIVE RULES
We first examine how the department has construed its administrative rules as to one- and two-family and multifamily manufactured housing. The department has interpreted its administrative rules to authorize it to adopt and administer the Wisconsin Manufactured Building Program. Information Bulletin to Housing Manufacturers and Inspection Agencies, June 1989, DILHR, Safety & Buildings Division (hereafter “Information Bulletin“). The department describes the program as follows:
The program is intended to apply to manufactured “closed-panel” structures, which would be difficult to inspect after leaving the plant. However, the program may be used for open-panel structures as well. Assuming compliance with code requirements, a Wisconsin Insignia (label) would be affixed to the building. The local inspector at the installation site will accept the labeled building as being basically code-complying, and will normally inspect the on-site and other accessible work only.
Please note that various state and local trades licensing requirements do apply to any on-site work
and that any local building code requirements do apply to on-site work of multi-unit dwellings. [Emphasis added.]
Information Bulletin, Scope.
Section 8.b, Procedures, provides that “[o]n-site plumbing must be . . . installed by Wisconsin licensed plumbers.” Information Bulletin. For in-plant plumbing, however, plans must be submitted to the department‘s Plumbing Bureau as a Product Approval Application. Id. at sec. 8.a. Applying the principle that the expression of one excludes the other, Teamsters Union Local 695 v. Waukesha County, 57 Wis. 2d 62, 67, 203 N.W.2d 707, 710 (1973), we conclude that the department has interpreted its rules not to require that in-plant plumbing be installed by Wisconsin-licensed plumbers.
We next consider whether the department‘s construction of its administrative rules as authorizing it to adopt and administer the Wisconsin Manufactured Building Program is inconsistent with the language of the rules or clearly erroneous. See Pfeiffer v. Board of Regents, 110 Wis. 2d 146, 154-55, 328 N.W.2d 279, 283 (1983) (An administrative agency‘s interpretation of its own regulation is entitled to controlling weight unless inconsistent with the language of the regulation or clearly erroneous).
The rules of administration and enforcement as to one- and two-family housing are contained in the Uniform Dwelling Code, Wis. Adm. Code chs. ILHR 20 to 25.3 Subchapter V, secs. ILHR 20.12 to 20.17, governs
The administration and enforcement rules on which the department relies to include multifamily manufactured housing in the Manufactured Building Program are contained in Wis. Adm. Code secs. ILHR 50.06(2) and 50.125, of the Commercial Building Code.5
Inspection procedures are prescribed in Wis. Adm. Code ch. ILHR 26 and subchapter II, ch. ILHR 81. Wisconsin Adm. Code ch. ILHR 26 establishes the stan
Sections ILHR 81.301 to 81.40, establish the standards and procedures for certification of plumbing inspectors and independent plumbing inspection agencies for enforcement of the state plumbing code for one- and two-family dwellings, including one- and two-family manufactured dwellings. Section ILHR 81.301. Manufacturers of multifamily manufactured housing must contract with the department or an independent inspection agency to conduct in-plant inspections. Sections ILHR 50.18(2), 51.01(71p) and 51.01(79a).7
In order to participate in Wisconsin‘s Manufactured Building Program, a manufacturer must complete a number of steps based on a national model developed by the National Bureau of Standards, “Model Documents for the Evaluation, Approval, and Inspection of Manufactured Buildings,” NBS Building Science Series 87, U.S. Dep‘t of Commerce (July 1976).8 Information Bulletin, Authority. These documents are incorporated in the Uniform Dwelling Code by sec. ILHR 20.24(3). As listed in the department‘s Information Bulletin, the steps include: (1) Submitting building plans, specifications and calculations to the department for examination and approval; (2) For in-plant plumbing work, submitting plans to the department‘s Plumbing Bureau as a Product Approval Application; (3) Submitting a compliance assurance manual9 to the department for approval; (4) In-plant inspections by the department or a certified inspection agency; and (5) On-site inspections by the local inspections department.
Assuming compliance with code requirements, the manufacturer may affix the Wisconsin insignia to manufactured buildings and building material. Information
The effect of the insignia is stated in Wis. Adm. Code sec. ILHR 20.15 as follows:
(2) Manufactured dwellings and manufactured building components bearing the Wisconsin insignia are deemed to comply with this [uniform dwelling] code, except as to installation site requirements, regardless of the provisions of any other ordinance, rule, regulation or requirement. [Emphasis added.]
(3) Manufactured dwellings and components bearing the Wisconsin insignia may be manufactured, offered for sale and shall be entitled to be installed anywhere in Wisconsin where the installation site complies with the other provisions of this [uniform dwelling] code.
Section ILHR 20.15 applies only to one- and two-family manufactured housing. However, the Wisconsin insignia must be placed on department-approved multifamily manufactured housing. Section ILHR 50.125. In administering the Manufactured Building Program, the department gives the same effect to the Wisconsin insignia when attached to multifamily manufactured housing as when it is attached to one- and two-family manufactured housing. The department has construed secs. ILHR 20.15 and 50.125 to make local and state trades
The Uniform Dwelling Code requires that one- and two-family manufactured dwellings be provided with plumbing systems in accordance with chs. ILHR 25, and 82 to 84. Section ILHR 25.01. The Wisconsin Manufactured Building Program requires that all plumbing comply with the Wisconsin Plumbing Code (ILHR 81-85). Information Bulletin, Procedures sec. 1.c. This requirement extends to multifamily manufactured housing governed by the Commercial Building Code.
We conclude that the department‘s construction of its administrative rules relating to one- and two-family and multifamily manufactured housing as authorizing it to adopt and administer the Wisconsin Manufactured Building Program is neither inconsistent with the language of the rules or clearly erroneous.
II. LEGISLATIVE AUTHORITY
The remaining question is whether the legislature authorized the department to adopt the rules which it has construed to permit it to adopt and administer the Wisconsin Manufactured Building Program. The Plumbers cite
The Plumbers assert that whether the Manufactured Building Code permits the department to adopt administrative rules which make
The executive secretary of the department was a member of the governor‘s task force which recommended enactment of the One- and Two-Family Dwelling Code and the Manufactured Building Code. Report of Task Force on Building Codes at i (Sept. 24, 1970), files of
We conclude that because of these unique circumstances and the department‘s extensive experience in applying the state plumbing code to manufactured housing, we must give the department‘s construction of the Manufactured Building Code the highest level of deference courts give to agency interpretations of statutes. See Sauk County v. WERC, 165 Wis. 2d 406, 413, 477 N.W.2d 267, 270 (1991) (if agency‘s experience, technical competence and specialized knowledge aid the agency in interpreting and applying statute, its conclusions are entitled to deference).
Since at least 1966, the installation of plumbing in prefabricated and manufactured buildings has been reviewed and approved on a “product approval” basis. Affidavit of James A. Sargent, director, Bureau of Plumbing, DILHR. The administration of the plumbing code was transferred from the Department of Health and Social Services to DILHR effective April 30, 1980. Section 643, ch. 221, Laws of 1979. Thus, the plumbing section of DHSS became a division of DILHR. When the Manufactured Building Code was enacted,
Robert G. DuPont, Product Review and Support Division chief, DILHR, avers that one reason for adopting the administrative practice of reviewing the installation of plumbing in manufactured housing on a product approval basis was to avoid discriminating against Wisconsin manufacturers. DuPont Affidavit, para. 5. The agencies concluded that an out-of-state manufacturer could not be required to employ a Wisconsin-licensed plumber because
Whether the agencies correctly adopted this administrative practice prior to enactment of the Manufactured Building Code and the administrative rules implementing the Code is no longer important. What is important is that the department brought this long-standing administrative construction and its perception of the law to the deliberations of the governor‘s Task Force and to the drafting of the Manufactured Building Code and the administrative rules. Therefore, its conclusion that the Code authorized it to adopt administrative rules permitting it to approve manufactured housing for sale and installation in the state, irrespective of the licensing requirements of
The Manufactured Building Code was enacted as the second part of Wisconsin‘s two-part attack on the housing crisis which then existed. Chapter 405, Laws of 1975. The first part was the One- and Two-Family Dwelling Code,
The Plumbing Subcommittee reported to the Task Force as follows:
We must recognize the fact that factory-built homes, apartments and commercial buildings are becoming a way of life. We must certify all phases of construction in the factory so that this system will work. This probably will necessitate crossing state lines so that factory products sold in Wisconsin and produced in other states can be approved.
Task Force Report at 54. This concern was echoed in the report of the One- and Two-Family Building Code Subcommittee. Id. at 43-46.
The Task Force accepted these recommendations of the subcommittees. It recommended legislation to provide a state-level product acceptance and approval procedure following national consensus standards. Task Force Report at viii. The Task Force stated: “This will mean implementing a procedure of certification of manufactured buildings and building components. Such a procedure should include a system of allowing reciprocal approval with other state governments within the marketing area of the product.” Id. at ix.
The Manufactured Building Code and the One- and Two-Family Dwelling Code were not, however, self-executing.
The Dwelling Code Council was a broad-based committee including representatives of building trade labor organizations, building inspectors and manufactured housing representatives. Environmental Impact Statement, Proposed Uniform Dwelling Code, Code Development Section, Safety & Buildings Division, DILHR (Jan. 1979), Dwelling Code Council files.
The department held workshops on the proposed Uniform Dwelling Code throughout the state for interested organizations. Chapters IND 20-25, Vol. I, Dwelling Code Council Files. The department solicited and received comments from organizations and affected entities such as the Wisconsin Towns Association, the County Boards Association, the League of Wisconsin Municipalities, the Wisconsin Society of Architects and the Wisconsin Building Inspectors Association. Id. The department prepared an environmental impact statement on the Uniform Dwelling Code and held public hearings on its report. Id.
On May 24, 1979, the secretary of the department sent the Uniform Dwelling Code to the legislature. Chapters IND. 20-25, Vol. I, DILHR, Dwelling Code Council Files. Each house held hearings on the proposed Uniform Dwelling Code. Id. The assembly Committee on
Thus, the Uniform Dwelling Code was drafted in cooperation with the department by a council having considerable expertise, was reviewed by interested organizations, presented to the legislature for its review, and subjected to numerous public hearings. No interested organization or individual objected that the Uniform Dwelling Code exceeded the authority delegated by the legislature to the Dwelling Code Council and the department.
The provisions of the Commercial Building Code relating to multifamily manufactured housing were not included in the Uniform Dwelling Code. We have been unable to determine whether such provisions were recommended to the department by the Dwelling Code Council. However, an interdepartmental memo dated May 31, 1979, indicates that housing manufacturers requested that they be permitted to attach the Wisconsin insignia to department-approved multifamily manufactured housing. Chapters IND 20-25, Vol. I, Dwelling Code Council files. The department drafted proposed rules “modeled after the [Manufactured Building Code] [which] blend[] with our current administrative procedures and approvals.” Id.
The department held two hearings, one in Madison and one in Wausau. The hearing notice stated that the hearings were on “proposed amendments [which] deal
The intensive public and legislative scrutiny given the Uniform Dwelling Code was not given the provisions of the Commercial Building Code relating to multifamily manufactured housing. Apparently such scrutiny was not considered necessary for two reasons. First, the rules affected a “relatively small number of manufactured buildings for housing . . . .” Fiscal Estimate on effect of proposed rules (Oct. 16, 1979), DILHR, Dwelling Code Council files. Second, the department already had in place a plan approval function and inspector certification program which the department considered could be modified as needed to administer and enforce the proposed rules. Id. Nonetheless, the public and legislative scrutiny of the proposed rules relating to multifamily manufactured housing was adequate to alert the department if the proposed rules were not consistent with the legislative purpose.
In this case, we defer not only to the department‘s experience, technical competence and specialized knowledge, but to the experience, competence and knowledge of the Dwelling Code Council. We have previously noted that the initial council was a broad-based committee. In carrying out its responsibilities under
When the highest level of deference is accorded an administrative agency‘s construction of a statute, we will sustain the agency‘s construction unless it is irrational or inconsistent with the purposes of the statute. Sauk County v. WERC, 165 Wis. 2d at 413, 477 N.W.2d at 270; DILHR v. LIRC, 161 Wis. 2d at 246, 467 N.W.2d at 550. A statute shall be construed to give effect to its leading idea. State v. Okray Produce Co., 132 Wis. 2d 145, 150, 389 N.W.2d 825, 827 (Ct. App. 1986). The Task Force Report makes clear that the leading idea of the One- and Two-Family Dwelling Code and the Manufactured Building Code was to provide quality housing at a reasonable cost to a population “increasing at an alarming rate.” Task Force Report at 1; see also Task Force Report at 13, 22 and 23. The Task Force concluded that to accomplish that objective, it was necessary to allow manufactured housing manufacturers to take advantage of the economies of mass production. Task Force Report at 3, 7, 10-12. Plainly, the Dwelling Code Council and the department considered that that objective would be frustrated if manufacturers were required to employ Wisconsin-licensed plumbers super
The Task Force also concluded that the state-level certification procedure should include a system of allowing reciprocal agreements with other states within the manufacturer‘s marketing area. Task Force Report at ix.
If
If
The Dwelling Code Council and the department have construed the Manufactured Building Code to authorize the department to issue or recognize an insignia of compliance which allows the sale and installation in the state of manufactured housing in which the plumbing has been installed by persons who are not licensed under
By the Court.—Judgment reversed.
Since at least 1975, the department has not applied
The legislature has concluded that to protect the safety of Wisconsin residents, plumbing must be installed under the supervision of persons who have had extensive training in the proper installation of plumbing equipment—Wisconsin licensed master plumbers. See
Given a specific statutory requirement, and other legislation which addresses a different subject, a court would usually conclude that the legislature, aware of the master plumber requirement of
Rather than focus on whether
The subject of this lawsuit is the interpretation of
The department‘s interpretation of
The majority cites no Wisconsin cases for the proposition that an agency‘s construction of a statute warrants nearly conclusive deference where the agency participates in the drafting of a statute. The department‘s involvement in pending legislation affecting the department is not unique. Most agencies do the same thing.
The majority also ignores a part of the Manufactured Building Code which indicates that the legislature was aware of chapter 145‘s existence, and required the department to enact rules which assured compliance with chapter 145.
The department shall:
. . .
(2) Adopt rules for the examination of plans and specifications and for periodic in-plant and on-site inspections of manufacturing facilities, processes, fabrication, assembly and installation of manufactured buildings to ensure that examinations and inspections are made in compliance with the rules . . . for indoor plumbing adopted by the department under ch. 145. [Emphasis added.]
One of the rules for indoor plumbing adopted by the department under chapter 145 is Wis. Adm. Code sec. ILHR 82.40(9):
PIPING BY PLUMBER. In accordance with ch. 145, Stats., piping which conveys water for human use or consumption, or to plumbing fixtures and plumbing appliances of every description, shall be installed by persons licensed by the department.
Had the legislature intended that the Manufactured Building Code‘s insignia plan supplant
The effect of the majority‘s decision is to substitute the department‘s “compliance assurance program” in place of licensed plumber supervision, and to substitute its view of the need for licensed plumbers for a contrary legislative determination. The “compliance assurance program,” however, is concerned with design, not fabrication integrity. The best plans, specifications and calculations can be rendered unsafe by an untrained assembly line worker. A “compliance assurance program” is merely a model document to evaluate, approve and inspect a manufactured building. See Wisconsin Adm. Code sec. ILHR 20.24(3).
Were I writing for the majority, I would conclude that the legislature‘s plainly demonstrated intent was that plumbing, in all dwellings, be installed under the supervision of Wisconsin licensed master plumbers.
Notes
(a) “Manufactured building” means any structure or component thereof which is intended for use as a dwelling and:
- Is of closed construction and fabricated or assembled on-site or off-site in manufacturing facilities for installation, connection, or assembly and installation, at the building site; or
- Is a building of open construction which is made or assembled in manufacturing facilities away from the building site for installation, connection, or assembly and installation, on the building site and for which certification is sought by the manufacturer.
(b) “Manufactured building” does not mean any manufactured home or mobile home under s. 101.91 or any building of open construction which is not subject to par. (a)2.
(1)(a) No person may engage in or work at plumbing in the state unless licensed to do so by the department. A master plumber may work as a journeyman. No person may act as a plumbing apprentice or pipe layer unless registered with the department.
. . .
(2) No person shall install plumbing unless at all times a licensed master plumber is in charge, who shall be responsible for proper installation. Licenses shall be issued only to individuals and no license shall be issued to or in the name of any firm or corporation. No such license shall be transferable. It is unlawful for any licensed master plumber to allow the use of his license, directly or indirectly, for the purpose of obtaining local permits for others or to allow the use of his license by others to install plumbing work. [Emphasis added.]
Id. at 155, 328 N.W.2d at 283.An administrative agency knows the specific purposes of the regulations it has promulgated. Moreover, an agency has a certain expertise in the area it is called upon to regulate. Thus we believe that an agency is in the best position to interpret its own regulations in accordance with their underlying purposes.
Section ILHR 20.02 (intro) provides:The purpose of this code is to establish uniform statewide construction standards and inspection procedures for one- and 2-family dwellings and manufactured buildings for dwellings in accordance with the requirements of ss. 101.60 and 101.70, Stats.
Section ILHR 20.05(2) provides:The provisions of chs. ILHR 20 to 25 shall apply to the construction and inspection procedures used for all new one- and 2-family dwellings, manufactured buildings for dwellings and newly constructed community-based residential facilities providing care, treatment and services for 3 to 8 unrelated adults.
The provisions of this code shall not apply to residences occupied by 3 or more families living independently or occupied by 2 such families and used also for business purposes.
This part [subchapter V] shall govern the design, manufacture, installation and inspection of manufactured dwellings, manufactured building systems and the components of the building systems displaying the Wisconsin insignia.
Section ILHR 50.125 (intro.) provides:Pursuant to s. 101.75(2), Stats., all manufactured multi-family dwellings approved by the department shall be deemed to comply with the requirements of all building ordinances and regulations of any local government except those related to zoning and siting requirements including, but not limited to, building setback, side and rear yard requirements and property line requirements.
A Wisconsin insignia shall be installed on a manufactured multi-family dwelling approved by the department and inspected at the manufacturing plant.
Section ILHR 51.01(71p) provides:Manufacturers of multi-family dwellings shall contract with the department or an independent inspection agency to conduct in-plant inspections to assure that the manufactured multi-family dwellings are in compliance with the plans approved by the department. All inspections shall be performed by a certified inspector or independent inspection agency.
Section ILHR 51.01(79a) provides:Independent inspection agency means any person, firm, association, partnership or corporation, other than a municipal corporation, certified by the department to perform certified inspections under this code.
Manufactured multi-family dwelling means any structure or component which is intended for use as a multi-family dwelling and for which certification is sought by the manufacturer, and which is of open or closed construction, fabricated or assembled on-site or off
-site in manufacturing facilities for installation, or assembly and installation at the building site. For purpose of this code, a manufactured multi-family dwelling means 3 or more living units attached together, or 2 or more living units and a business occupancy attached together.