Opinion
Under General Statutes § 52-584a (a), 1 no action against an architect, professional engineer or land surveyor to recover damages for any defect in the design, planning or construction of an improvement to real property may be brought more than seven years after substantial completion of such improvement. The plaintiff, Plato Associates, LLC, appeals 2 from the judgment of the trial court rendered in favor of the defen dants, Environmental Compliance Services, Inc. (ECS), and its manager, Michael E. Hopkins. The plaintiff contends that the trial court incorrectly concluded, first, that the limitation period contained in § 52-584a (a) is inapplicable to its breach of contract and negligence claims against the defendants and, second, that the plaintiffs claims are time barred by the statutes of limitation applicable generally to breach of contract and negligence claims. We conclude that the limitation period of § 52-584a (a) applies to the plaintiffs claims and, further, that the defendants have failed to establish that the plaintiffs claims are untimely under that statute. Accordingly, we reverse the judgment of the trial court.
The following undisputed facts and procedural history are relevant to our resolution of this appeal. In 2000, the plaintiff applied for a loan from New Haven Savings Bank (bank) to finance the acquisition of and improvements to real property located at 4 Pin Oak Drive
3
in the town of Branford (town). As a condition of the loan, the bank required an environmental site assessment (assessment) of the property so it could be determined whether the property constituted an “establishment” under the Connecticut Transfer Act (act), General Statutes § 22a-134 et seq.
4
The
On January 18, 2001, ECS issued a report, which was signed by Hopkins, a licensed professional engineer, in which the defendants concluded that the property was not an “establishment,” as that term is defined under the act.
5
In reliance on the report, the plaintiff purchased
the property and closed on a construction mortgage in the amount of $2,833,000. The first advancement under the loan totaled $1,952,000, which went toward the purchase of the property. At the time of the purchase, buildings and other improvements on the property were under construction
The plaintiff commenced this action on August 31, 2007, claiming that the defendants had breached the parties’ contract and that they had been negligent in their performance of the 2000 environmental assessment by failing to identify the property as an establish ment. The defendants filed a motion for summary judgment, claiming that the plaintiffs breach of contract claims were barred 7 by the six year limitation period contained in General Statutes § 52-576 (a) 8 and that its negligence claims were barred by the respective three and two year limitation periods of General Statutes §§ 52-577 9 and 52-584. 10
In response to the defendants’ motion for summary judgment, the plaintiff maintained, contrary to the position advanced by the defendants, that the seven year limitation period of § 52-584a (a) applies to all of the plaintiffs claims because the defendants had performed professional services in connection with improvements to real property. In particular, the plaintiff asserted that the defendants’ services were performed in connection with the plaintiffs purchase of and subsequent improvements to the property and with the improvements to the property that the defendants themselves made on September 19,2000, when they installed two monitoring wells to evaluate the environmental condition of the
property. The plaintiff maintained, therefore, that the seven year limitation period of § 52-584a (a) began to run, at the earliest, on September 19, 2000, and, consequently, its action, which had been commenced on August 31,2007, was
The defendants countered that § 52-584a (a) did not apply to the plaintiffs claims because (1) the defendants had not provided professional engineering services as contemplated by the statute, and (2) the defendants’ activities were not performed in connection with an improvement to real property within the meaning of § 52-584a (a). In support of their contentions, the defendants relied on the affidavit of Hopkins, in which he stated that “[t]he . . . [assessment did not involve any professional engineering services” or “improvement^]” to the property. Rather, the sole purpose of the . . . [assessment was to identify and record existing, potential or suspected conditions that may impose an environmental liability to, or restrict the use of, the property. The sole purpose of the monitoring wells and borings, both intended to be temporary structures, was to accomplish the overall purpose of . . . [the environmental assessment]. Neither the monitoring wells nor the borings increased [the] value [of] the property.”
The trial court granted the defendants’ motion for summary judgment. In doing so, the court rejected the defendants’ first contention, namely, that the defen
dants had not provided professional engineering services, concluding, rather, that the affidavits and other materials submitted by the parties in connection with the summary judgment motion gave rise to a genuine issue of material fact concerning that claim. The court agreed, however, with the defendants’ second contention that their activities were not performed in connection with an improvement to real property within the meaning of § 52-584a (a). Relying on this court’s decision in
Grigerik
v.
Sharpe,
The plaintiff contends that the trial court properly concluded that there exists a genuine issue of material fact as to whether the defendants provided professional engineering services in performing the assessment in 2000 but that the court misinterpreted
Grigerik
in concluding that the defendants’ services were not performed in connection with an improvement to real property within the meaning of § 52-584a (a). In support of the latter claim, the plaintiff contends that the defendants’ services were performed not only in connection with improvements to the property that the plaintiff itself undertook but also in connection with the defendants’ installation of the two monitoring wells. The defendants do not defend the trial court’s reading of Grigerik
11
but claim, instead, that the judgment of the
trial
We begin our analysis with the well established standard of review. “Practice Book § 17-49 provides that summary judgment shall be rendered forthwith if the pleadings, affidavits and any other proof submitted show that there is no genuine issue as to any material fact and that the moving party is entitled to judgment as a matter of law. In deciding a motion for summary judgment, the trial court must view the evidence in the light most favorable to the nonmoving party. . . . The party moving for summary judgment has the burden of showing the absence of any genuine issue of material
Section 52-584a (a) provides in relevant part: “No action ... (1) to recover damages (A) for any deficiency in the design, planning, contract administration, supervision, observation of construction or construction of, or land surveying in connection with, an improvement to real property . . . shall be brought against any architect, professional engineer or land sur veyor performing or furnishing the design, planning, supervision, observation of construction or construction of, or land surveying in connection with, such improvement more than seven years after substantial completion of such improvement. ...” Thus, by its plain terms, § 52-584a (a) applies to any action for damages against an architect, a professional engineer or a land surveyor for deficiencies in, among other things, the design, planning, supervision or construction of an improvement to real property. We conclude that whether the plaintiffs claims fall within the purview of § 52-584a (a) is a disputed factual issue that is not appropriate for summary judgment.
We first address the defendants’ claim that the trial court improperly concluded that there is a genuine issue of material fact as to whether their services constituted professional engineering services. The defendants contend that the trial court improperly determined that Hopkins’ status as a professional engineer was sufficient to raise a disputed factual issue as to whether the defendants’ services constituted professional engineering services so as to bring the plaintiffs claims within the purview of § 52-584a (a). In support of this claim, the defendants rely on the affidavit of Hopkins, in which he states that the assessment of the property “did not involve any professional engineering services.”
The plaintiff contends that the trial court properly determined that there is a genuine issue of material fact concerning whether the defendants’ services involved professional engineering services because Hopkins, who manages ECS, reviewed the final report and represented himself in that report as a professional engineer. The plaintiff further contends that the defendants’ assessment of the property, as well as the services performed in connection therewith, falls within the scope of the work done by a “professional engineer,” as that term is defined statutorily, and, consequently, there exists a genuine issue of material fact as to whether the defendants’ services constituted professional engineering services for purposes of § 52-584a (a). We agree with the plaintiff. 12
Under General Statutes § 20-299 (1), a “professional engineer” is defined as “a
We next address the defendants’ claim that they are entitled to summary judgment because they did not perform services in connection with an improvement to real property within the meaning of § 52-584a (a) but, rather, in connection with the plaintiff’s application for a bank loan. The defendants further contend that, contrary to the contention of the plaintiff, the monitor ing wells were not improvements to property because they did not add value to the property. We disagree.
As we previously have indicated, in support of its objection to the defendants’ motion for summary judgment, the plaintiff submitted the affidavit of Perlman, in which he stated that the assessment was integral to the plaintiffs plan to acquire and improve the property. Specifically, he
We also agree with the plaintiff that there exists a genuine factual issue as to whether the monitoring wells constituted improvements to property within the meaning of § 52-584a (a) such that the seven year limitation period of that statute began to run, at the earliest, on September 19, 2000. The defendants contend that the wells were not improvements because they added no value to the property and because they were installed solely for the purpose of assisting the plaintiff in securing a bank loan. In light of our conclusion that there is a disputed factual issue as to whether the defendants’ services were rendered in connection with an improvement to real property, we address only the defendants’ claim that the wells did not add value to the property and, therefore, did not constitute an improvement to property within the meaning of § 52-584a (a).
“In
Grigerik
v. Sharpe, [supra,
Applying this definition of “improvement to real property” to the facts of the present case, we cannot conclude as a matter of law that the monitoring wells were not an improvement to property for purposes of § 52-584a (a). The wells were constructed of PVC screen and casing pipes that were two inches in diameter, and the wellheads were “finished protective steel hand boxes in concrete collars” that were placed in the ground. For the same reasons that we conclude that there exists a genuine issue of material fact as to whether the defendants’ services were performed in connection with improvements to real property, we reject the defendants’ contention that the monitoring wells added no value to the property as a matter of law. Perlman’s affidavit states that the plaintiff would not have been able to secure financing to purchase the property without the defendants’ assessment of the property, which required installation of the monitoring wells. We agree with the plaintiff that this evidence gives rise to a genuine issue of material fact as to whether the wells increased the property’s value or enhanced its utility so as to bring the plaintiffs claims within the seven years statute of limitations contained in § 52-584a (a).
The judgment is reversed and the case is remanded for further proceedings according to law.
In this opinion the other justices concurred.
Notes
General Statutes § 52-584a (a) provides: “No action or arbitration, whether in contract, in tort, or otherwise, (1) to recover damages (A) for any deficiency in the design, planning, contract administration, supervision, observation of construction or construction of, or land surveying in connection with, an improvement to real property; (B) for injury to property, real or personal, arising out of any such deficiency; (C) for injury to the person or for wrongful death arising out of any such deficiency, or (2) for contribution or indemnity which is brought as a result of any such claim for damages shall be brought against any architect, professional engineer or land surveyor performing or furnishing the design, planning, supervision, observation of construction or construction of, or land surveying in connection with, such improvement more than seven years after substantial completion of such improvement.”
The plaintiff appealed to the Appellate Court from the judgment of the trial court, and we transferred the appeal to this court pursuant to General Statutes § 51-199 (c) and Practice Book § 65-1.
We hereinafter refer to this particular property as the property throughout this opinion.
“The [act] subjects transferors of establishments to reporting, investigation and remediation requirements that depend on the environmental condition of the property being transferred. See General Statutes § 22a-134a. The transferor makes the report on one of several forms, which are defined terms under the statute as Forms I, II, HI and IV. See General Statutes § 22a-134 (10) through (13) (defining form contents).” (Internal quotation marks omitted.)
Northeast Ct. Economic Alliance, Inc.
v.
ATC Partnership,
General Statutes § 22a-134 (3) defines “establishment” as “any real property at which or any business operation from which (A) on or after November 19,1980, there was generated, except as the result of remediation of polluted soil, groundwater or sediment, more than one hundred kilograms of hazardous waste in any one month, (B) hazardous waste generated at a different location was recycled, reclaimed, reused, stored, handled, treated, trans ported or disposed of, (C) the process of dry cleaning was conducted on or after May 1, 1967, (D) furniture stripping was conducted on or after May 1, 1967, or (E) a vehicle body repair facility was located on or after May 1, 1967
The report provided in relevant part: “The [property] does not appear to be an [establishment (subject to the [act]). Based on these findings, the overall environmental risk associated with the [property] appears to be low. No additional investigation is recommended at this time.” The report further provided: “The phase I portion of this assessment was performed in accordance with American Society for Testing and Materials Standard E1527-00 . . . and the Connecticut Transfer Act Site Assessment Guidance Document. The phase II portion included the collection and analysis of six soil samples. The scope of this assessment included:
“[1] visually inspecting the property,
“[2] reviewing ‘standard’ published state and federal environmental site inventories and databases . . .
“[3] reviewing historic aerial photographs, Sanborn Eire Insurance Company maps, and published city street directories,
“[4] searching [state department of environmental protection] files pertaining to the [property] and selected abutting properties, including the following programs: Waste Engineering and Enforcement Division, Permitting, Enforcement and Remediation Division, Underground Storage Tank Bureau, Hazardous Waste Manifest Program, and Water Compliance Unit,
“[5] reviewing public records at the [town] [conservation [d]epartment, [f]ire [m]arshall’s office, [engineer’s office], [cjlerk’s office and tax assessor’s office . . .
“[6] reviewing published or publicly available background information sources (soil surveys, water quality maps, topographic maps, geological references, wetland maps, etc.), and
“[7] collecting and analyzing soil samples from six borings.”
We note that the sparse record in this case contains no explanation of the status or nature of the improvements that the plaintiff has made to the property since it was purchased. Nevertheless, the defendants do not dispute that such improvements have been made.
Hopkins also claimed in the motion that he was entitled to summary judgment on the breach of contract claim on the ground that he never had entered into a contract with the plaintiff. The plaintiff did not oppose the granting of summary judgment with respect to its breach of contract claim to the extent that such claim pertained to Hopkins’ performance in an individual capacity.
General Statutes § 52-576 (a) provides in relevant part: “No action for an account, or on any simple or implied contract, or on any contract in writing, shall be brought but within six years after the right of action accrues . . . .”
General Statutes § 52-577 provides: “No action founded upon a tort shall be brought but within three years from the date of the act or omission complained of.”
General Statutes § 52-584 provides in relevant part: “No action to recover damages for injury to the person, or to real or personal property, caused by negligence . . . shall be brought but within two years from the date when the injury is first sustained or discovered or in the exercise of reasonable care should have been discovered, and except that no such action may be brought more than three years from the date of the act or omission complained of . . .
We agree with the plaintiff that the trial court misinterpreted
Grigerik
in concluding that the defendants were entitled to summary judgment. In
Grigerik,
we were required to determine whether § 52-584a applies to an
action against an engineer for negligent design of a septic system and negligent soil testing even though the septic system never was built. See
Grigerik
v.
Sharpe,
supra,
In light of our discussion in Grigerik, it is abundantly clear that § 52-584a (a) applies principally when the intended improvement to real property is completed and that the seven year limitation period begins to run upon substantial completion of that improvement. We therefore agree with the plaintiff that the trial court improperly granted the defendants’ motion for summary judgment on the ground that the plaintiff was required but failed to allege and prove that an improvement to property could not be completed as a result of the defendants’ alleged negligence and breach of contract. Indeed, as we previously have indicated, the defendants do not contend otherwise.
We note that both the defendants and the plaintiff agree that, in order for § 52-584a to apply to the plaintiffs claims, the plaintiff must establish that the defendants’ services constituted professional engineering services. We do not read the statutory language as imposing such a requirement. Kather, as we previously have explained, the statute authorizes actions against “professional engineers] ” for deficiencies in the “the design, planning, contract administration, supervision, observation of construction or construction of, or land surveying in connection with, an improvement to real property . . . .” General Statutes § 52-584a (a). There is no requirement that the services performed by the engineer constitute professional engineering services. On appeal, however, both the defendants and the plaintiff have framed the issue before this court as requiring a determination of whether the trial court properly determined that a genuine issue of material fact exists as to whether the defendants’ services constituted professional engineering services. We therefore address the issue as framed by the parties.
Although § 20-299, by its terms, applies to chapter 391 of the General Statutes, that chapter governs the licensing of professional engineers. Insofar as chapter 391 is a licensing statute, we can perceive no reason why the definition of “professional engineer” contained in that chapter should not also inform our understanding of that term for purposes of § 52-584a (a).
