143 N.Y.S. 609 | N.Y. Sup. Ct. | 1911

HENDRICK, J.

In this action to foreclose a mechanic’s lien, defendants Vanderbilt, the owner, and Jacob & Youngs, Incorporated, the contractor, have no pecuniary interest. The liens have been transferred from the property to the bond given by defendant National Surety Company. Defendants A. P. Bigelow & Co. and the Russell & Erwin Company did not appear at the trial. Defendant Relyea, trustee in bankruptcy of subcontractor Maher, may also be ignored. We have left the plaintiff and four other lienors and a fund of about $9,000 still in the hands of the contractors. That fund must be distributed among these five lienors, and the question presented is how it shall be divided. The principal lienor is A. W. Burritt & Co.

[1] This company has a claim larger than the fund on hand and claims the whole of it. The lien filed amounted to $10,419.26. The company has withdrawn an item of $10.75 and another for $250. I am satisfied that these were included through inadvertence and that they do not vitiate the lien. Ringle v. Wallis Iron Works, 149 N. Y., 439, 44 N. E. 175; Aeschlimann v. Presbyterian Hospital, 165 N. Y. 296, 59 N. E. 148, 80 Am. St. Rep. 723.

[2] One objection to this claim is made in common by several of the other lienors. It is not stated, however, more clearly than by counsel for this company, who sums it up in this single question:

“Suppose in the case of Herrmann & Grace v. City of N. Y., 130 App. Div. 531 [114 N. Y. Supp. 1107], affirmed 199 N. Y. 600 [93 N. E. 376], the American Radiator Company had made the radiators for the particular structure so as to fit in the different window recesses, and of special and suitable sizes for the different rooms, or of special designs, would the court in that case have held that company any less a materialman because it made special radiators for a special building?”

The Burritt & Co. lien is not for labor and materials but for materials only. If the question quoted should be answered in the negative, this company is entitled to preference over prior liens for both labor and material, for that has been so adjudicated. Herrmann & Grace Co. v. City of N. Y., 130 App. Div. 531, 114 N. Y. Supp. 1107, *612affirmed 199 N. Y. 600, 93 N. E. 376; Hedden Const. Co. v. Proctor & Gamble Co., 62 Misc. Rep. 129, 114 N. Y. Supp. 1103. The question quoted is substantially the question presented here, except that the material is different. Burritt & -Co. supplied doors and other trim manufactured for this particular improvement in accordance with special designs. They were not carried in stock by the company; they could not be purchased from drummers in the trade; they are not staple articles carried by any class of tradesmen. If they had been, the company would be entitled to judgment. 130 App. Div. 531, 114 N. Y. Supp. 1107, supra. On the other hand, our doubts would be resolved if the company had come into the house with its workmen and fabricated the doors and other trim in & room adjacent to that-where they were to be hung or attached. The company would then be a subcontractor, as distinguished from a simple materialman. Now, where lies the difference in principle? In one case the company contracts to manufacture interior trim on the premises and in the other at their manufactory. In both cases the articles are specially adapted to that one particular purpose; in neither are they of any substantial value as trim in any other building. The Municipal Building now under construction on Chambers street will consist mainly of steel and stone fitted elsewhere; each beam and block being placed where the designers planned while the steel was pig iron and the stone was in the quarry. If a lien were filed, should it be for material or for both labor and material ? I feel constrained to hold that Burritt & Co. were subcontractors and furnished for this building both labor and materials. What, then, is the status of the company? It cannot have a lien for material only, and it has filed no lien for labor and material. If a lien for labor and material is filed, the lienor, it seems to me, could not recover for material only, as that would give him an advantage over prior lienors claiming for both labor and material. But the converse does not seem to follow. I shall hold that Burritt & Co. are entitled to stand in their order of priority as a lienor for labor and material. Burritt & Co. make another point which requires notice.

[3] About a week before any of the liens were filed, it obtained from Mr. Maher, the subcontractor, an order on the contractor for $9,600. This was not an assignment of the entire balance but authority to the contractors to pay that sum out of the balance to become due “prior to any claims I may have on. said moneys.” That lacks something even of an equitable assignment. It seems to be an order on a fund which should také precedence of any other order Maher might give, but it does not purport to effect any inchoate rights in the fund possessed by other lienors. Without pausing to inquire what rights are obtained by an assignee of part of a fund, we pass on to the reply made by the contractor. This states that there is apparently enough money to cover the order and the samé would be credited, but—

“it is distinctly understood and agreed between us that if there should be any charges against his account of which we do not know at the present time, they shall be deducted before paying you the amount of the order. The reason for making this special arrangement is that the amount appearing to Mr. Maher’s credit is less than §125 more than the amount of the order, and we wish to protect ourselves in the matter.”

*613If Burritt & Co. had sued the contractor on that order, it seems doubtful whether they could recover. Just what is meant by “charges” is not clear. The company, however, did not obtain payment but proceeded to file a lien and are asking foreclosure in this action. Nor did the company surrender any of its rights. It has not, therefore, brought itself within the facts of the case which is invoked. Harvey v. Brewer, 178 N. Y. 5, 70 N. E. 73. The company suggests that section 15 of the Eien Law (Consol. Laws 1909, c. 33), declaring such orders void if not filed with the county clerk, has no application to the order in question, because this was not drawn upon an owner but upon a contractor. That does not seem to be strictly correct. Van Kannel Revolving Door Co. v. Astor, 119 App. Div. 214, 104 N. Y. Supp. 653. In the absence of authority, I am inclined to follow the meaning which seems to lie on the face of section 15 of the Lien Law and to rule against this company’s contention. No special objection is made to this company’s lien for $250 and that will be allowed.

[4] The notice of lien filed by the Hasbrouck Flooring Company contains no description except as follows:

“The labor performed and the materials furnished, and the agreed price and value thereof, are as follows, respectively, $3,645.03.”

The amount unpaid is $977.03. The colienors challenge the sufficiency of this notice on the ground that it does not describe the materials furnished and the work performed, either separately or both together. This company contends that a description is unnecessary, as that is impliedly stated in the title of the corporation. Unless a more persuasive answer can be found, I fear that the objection must be sustained. Any one passing the windows of a dairy company or a tea company will see many articles exposed for sale that have not the remotest connection with either tea or dairy products. This company cites a case in which a statement appears in the opinion arguendo that the notice is required for the benefit of the owner. Vogel v. Luitwieler, 52 Hun, 184, 5 N. Y. Supp. 154. But this particular statute appears to place no limitation upon the purpose to be served by its different provisions. A lienor may rely upon it as well as an owner.

[5] Subdivision 4 of section 9 provides that “the labor performed or to be performed, or materials furnished or to be furnished, and the agreed price or value thereof,” shall be stated in the notice of lien. It is sometimes held that such notices must conform to the statute in order to confer jurisdiction on the court. Davidsburgh v. Knickerbocker Life Ins. Co., 90 N. Y. 526.

[6] It is also held that the requirement as to the kind of labor performed and the amount thereof cannot be omitted (Toop v. Smith, 181 N. Y. 283, 73 N. E. 1113), and that defects in the notice cannot be supplied by extrinsic evidence. Armstrong v. Chisholm, 100 App. Div. 440, 91 N. Y. Supp. 693. In short, the rule seems to be general that in all matters of substance the notice must conform to the statutory requirements. Norton & Gorman Cont. Co. v. Unique Const. Co., 121 App. Div. 586, 106 N. Y. Supp. 372; Bossert v. Fox, 89 App. Div. 7, 85 N. Y. Supp. 308; In re Fmslie (D. C.) 98 Fed. 716.

[7] This company pleads further that this lien was bonded without *614objection, and thereby all objections as to form were waived. The case of Kerrigan v. Fielding, 47 App. Div. 246, 62 N. Y. Supp. 115, is cited. This is a contest between colienors litigating for priority, and I think that the bond as among them serves no purpose except to transfer to itself the liens that rested upon the building.

[8] This company also urges that all objection to the notice of lien disappeared when it was received in evidence without protest. I do not so understand the rule. This is an equity action, and the mere fact that a paper is put in evidence is not conclusive upon its effect. With some reluctance I reach the conclusion that the lien of the Hasbrouclc Flooring Company must be disallowed. The lien of D. B. Pershall & Son was filed for an excessive amount.

[9] But I am satisfied from the evidence that, although the accounts were kept very carelessly, there was no intention to obtain any unfair advantage.

[10] The lien was filed for material only. The omission in one instance to erase the words “labor and” before “material” does not characterize the notice as one for labor and material. The main objection made is that nearly all the material was delivered more than 90 days before.the notice was filed. The statute provides that:

“The notice of lien may be filed * * * within ninety days after * * * the final furnishing of the materials, dating from the last item of * * * materials furnished.’’

These lienors appear to be entitled to a decree for $236.09; that being the sum to which the lien was reduced. The lien of John J. Wallace for labor and material must be allowed. Plaintiff, Pittsburgh Plate Glass Company filed a lien for both labor and material. While the notice makes no claim for material alone, it repeatedly claims for labor and material. In one place this occurs:

“That the nature and amount of the labor and services performed and the material furnished, and the agreed price and value thereof, are as follows: Materials, consisting of plate glass and sheet glass, and the labor in cutting and preparing same for shipment, delivered and set, of the price and value of $1,824.”

If plaintiff had filed a notice, as permitted by the statute, for materials and for labor, separating the amount of each, the court might feel authorized to reject the item of labor on plaintiff’s motion and allow the lien to stand for material only. But I must accept the notice as it appears on file, and plaintiff’s lien for labor and material will stand for the amount claimed.

A decision and decree in accordance with this memorandum should be settled on notice not later than June 27, 1911.

© 2024 Midpage AI does not provide legal advice. By using midpage, you consent to our Terms and Conditions.