115 Ky. 176 | Ky. Ct. App. | 1903
Opinion op the court by
appirming in cross appeal AND REVERSING ON DEPENDANTS’ APPEAL.
The Louisville Bridge Company was incorporated by an act of the Legislature in 1856, with authority to build a railroad toll bridge across the Ohio river at Louisville. The bridge wa® not built and completed till about 1870. The charter of the bridge company authorized it “to contract, at an agreed sum or rate, with any railroad company chartered by the State of Kentucky, or any other State of the United States, for the annual use of said bridge by the cars or for the purposes of said railroad company.”
This bridge was built from stock subscriptions and the proceeds of an issue of mortgage bonds. The capital stock paid in was $1,500,000. The bond issue was $800,000. When
On June 5, 1872, the Louisville Bridge Company (hereinafter referred to as the “Bridge Company”), the Jefferson-ville, Madison & Indianapolis Railroad Company, the Ohio & Mississippi Railway Company, and the Louisville & Nashville Railroad Company entered into a contract — -perpetual, except as it might be terminated by the parties according to its terms — by which the railroad companies agreed to pass over the bridge their traffic destined to cross the Ohio river at or near Louisville, and to pay for this privilege such rates per engine, per car, per ton, and per passenger as the bridge company might from time to time fix, not exceeding in the aggregate a sum sufficient to pay a certain fixed income to its stockholders, and taxes, cost of operating expenses, and the maintenance of the bridge company’s organization. It was not agreed, and could not have been, by the bridge company, that the contracting railroads were to have the exclusive right of passage over the bridge. On the contrary, it was expressly stipulated that the bridge company might admit any -other railroad or railroads to the same privileges as by the contract were accorded to the then contracting roads, but upon terms no more favorable. As this contract is at the foundation of this litiga
“Agreement made this fifth day of June, 1872, between the Louisville Bridge Company, party of the first part, the Jeffersonville,' Madison & Indianapolis Railroad Company, party of the second part, the Ohio & Mississippi Railway Company, party of the third part, and the Louisville & Nashville Railroad Company, party of the fourth part, witnesseth:
“Whereas, the first party owns the bridge over the Ohio river at Louisville, between the Commonwealth of Kentucky and the State of Indiana, with the approach thereto on the south or Kentucky side thereof, its capital stock being fifteen hundred thousand dollars, .and its mortgage debt eight hundred thousand dollars, bonds for said debt being issued for one thousand dollárs each, dated the first day of December, 1868, and payable twenty years after said date with interest at seven per cent, per annum, payable semiannually in gold on ■ the first day of June and the first day of December, principal and interest payable at the Bank of America, New York City. And, whereas, the second party owns the approach to said bridge on the north or Indiana side thereof and the railroad connecting therewith; and, whereas, the third party owns a railroad connecting with the railroad of the party of the second part at or near the north end of said approach; and, whereas, the party of the fourth part owns a railroad terminating in the city of Louisville and connecting with the track over and across the said bridge.
“Now this agreement witnesseth: In consideration that the second, third and fourth parties agree respectively to use said bridge as is hereinafter covenanted, the first party hereby covenants and agrees jointly and severally with the*183 second,, third and fourth parties, their successors and assigns respectively, that the tolls and charges over and for the use of said bridge and its tracks, owned by the first party, in the transportation of freights, passengers, mails and other goods received from or 'delivered to the roads of said second, third and fourth parties, per ton, and per passenger or per car, engine or other means of transfer over said bridge, shall be fixed on signing this agreement, and shgll not be in excess of a toll or charge sufficient to produce in the aggregate a sum equal to the cost and expense of keeping in repair and taking care of said bridge and the said approach owned by the first party — paying a dividend semiannually of six per cent, on said capital stock of fifteen hundred thousand dollars, the interest upon the said fund sufficient to pay off said bonds of eight hundred thous- and dollars at maturity, the amount necessary to keep up the corporate organization of the party of the first part, with its proper officers and servants, and such taxes as may be chargeable against such bridge company on said bridge or other property pertaining thereto or otherwise; and it is understood and mutually agreed that said charges and tolls shall from year to year be reduced in proportion to the' reduction of interest on said bonds by the operation of said sinking fund; and that said tolls and charges shall always be the same to each of the second, third and fourth parties, and that the tolls and charges to other railroad companies for like use of said bridge and the approach owned by the first party shall not be less than those charged to or incurred by the parties hereto. And all such tolls and charges paid by other railroads or railroad companies shall be applied to and form a part of the fund hereinbefore provided for the payment of expenses, sinking fund, inter*184 est, dividends and faxes the same as if paid by the second, third and fourth parties.
“Sec. 2. The first party shall keep in repair, maintain and renew the said bridge and its appurtenances, and the tracks and approach thereto owned by the first party. If, however, said bridge or its' appurtenances shall be injured by floods, ice, or other casualty, or by crystallization of the iron, or other inherent decay, so as to render same useless or dangerous, and it shall become necessary to rebuild the whole,, or any material part thereof, involving an expenditure greater than could be realized from a judicious amount of current rates and charges, then, and in every such case, it is mutually agreed between the parties that the first party shall issue bonds, secured by mortgage on said bridge and its appurtenances and appendages, owned by the first party, at a rate of interest not exceeding seven per cent, per annum in gold, payable semi-annually, principal payable in forty years, and to an amount sufficient to yield a fund equal to the expenses of renewing and repairing said bridge, and the proceeds of said bonds shall be applied to that purpose, in which event the tolls and charges for the use of said bridge, as hereinbefore provided, shall be increased so as to cover and provide for the payment of the interest on said bonds, and a sinking fund to retire and take up said bonds at maturity.
“Sec. 3. In consideration of the premises, the second and third parties each severally covenant for itself, its successors and assigns with the first party, its successors and assigns, that it will pass over the said bridge all the freight, passengers, mails, express matter, and other goods carried on and over their roads to and from Louisville,, and to and from points which require their passage over the Ohio river at or near Louisville during the existence of this agree-*185 meat, and will pay punctually to the party of the first part the tolls and charges' hereinbefore provided for the use by them respectively of said ¡bridge and the tracks and approaches thereto, owned by the first party; and the party of the fourth part for itself, its successors and assigns, covenants with each of the parties of the first, second and third parts, their respective successors or assigns, that it will deliver to said party of the first part, to ha passed over said bridge, or to the parties of the second and third parts, or to such other railroad company or companies as may for the time being be transporting freight, passengers, mails, express matter and other goods over the said bridge, all the freight, passengers, mail, express matter, and other goods carried on and over its road or iany part thereof, destined for Jeffersonville, in the State of Indiana, or any other points which require their passage over the Ohio river at or near Louisville, during the existence of this agreement, and will charge on such traffic, in addition to its rates for transportation service, the then established rates of toll and charges hereinbefore provided for the use of said bridge and approaches, and punctually pay the said tolls and charges to the first party.
“Sec. 4. In consideration of the premises aforesaid, and in consideration of the ownership and investment made by the second party in, and its control of, said approach to said bridge at the north end thereof, the third party hereby'covenants and .agrees with the second party, to use said approach to said bridge, from the existing point of connection between their respective roads, or such other point as may hereafter be agreed on by the said two parties in going to and from said bridge with the cars, engines and trains, or other means of transporting freight, passengers, mails, express and other goods over its railroad, destined*186 to and from Louisville, and to or from points at or near Louisville during the existence of this agreement. It is, however, mutually understood and agreed that all of the said trains, cars and engines, passing over said approach and over said bridge, are and shall be, under the control and direction >of the second party, and that whatever rules are prescribed for the, government of the trains, cars and engines of the second party in the premises, shall toe equally applicable to the trains, cars and engines of .the third party, each being dealt with alike. It is, however, further mutually understood and agreed between the second and third parties, that so long as the passenger trains of the party of the second part are run to and from said city of Louisville with the proper train engines of the second party, the passenger trains of the third party may also be so run by its own proper train engines. But whenever, in the opinion of the second party, the trains of the parties can not be so run with safety, the second party shall set apart a sufficient number of engines for that service. The freight trains and freight cars of the parties shall be run over said approach and said bridge, to and from Louisville, with the engines of -the second party set apart for that service, and the second party hereby covenants to furnish all needful and sufficient engines for the service hereinabove mentioned, and at all times to transfer with the same promptness and care, over the said approach and bridge, the trains, cars, engines and traffic of the parties of the third and fourth parts, received from or to be delivered to the roads of the parties of the third and fourth parts that it does the trains, oars, engines .and traffic received from or to be delivered to its .own road; the intention being that each of the parties shall enjoy equal facilities over said approach and bridge.
*187 “For the services aforesaid of the said engines of the second parity, and the conducting and management of the same, and of the cars, trains and business over said approach and bridge., the second party shall be allowed a rea-. sonable compensation, to be fixed on signing this agreement, to be apportioned between the parties hereto in proportion to the service to 'each, per ton and per passenger, or per car, engine or other means of transfer, as the parties may hereafter agree.
“In respect to the usa by the third party of. the approach to said bridge, owned by the second party, on the north side of said bridge from the point of connection made therewith by the third party the party of the third part hereby covenants and agree to pay the second party five per cent, per annum on the actual cost of it-he right of way, the construction of the same and the value of tba superstructure thereon, which cost and value are together assumed at-. dollars, and also pay in proportion to use the expenses of keeping up and maintaining and renewing the same. If any of the parties hereto, and in interest, cannot .agree as to the compensation or rule of . apportionment for said engine service and management of trains, or upon the expense or rule of apportionment of the expenses relating to said approach, or the cost and value of said roadway and track as above provided then each of the two parties in interest may select one referee to determine the difference, and if said referees can not agree, an umpire may be chosen by them, and their decision, or a majority, shall conclude the matter. If either party fail to appoint u referee as aforesaid within thirty days .after written notice to miake such appointment, the referee appointed by the party motín default shall appoint ithe referee for the defaulting party, and the two shall proceed to determine the matter or ap*188 point an umpire. No person shall be qualified to act as umpire or referee except disinterested persons of experience and skill in railroad management. The parties mutually covenant to perform the awards.
Any of said parties in interest, after the expiration of six months from the time such agreement for said compensation for said services and expenses is made, or six months after such award, may then and semi-annually thereafter, upon thirty days’ previous notice in writing to the other party in interest, require said compensation to be readjusted, and if they can not agree upon the terms of such readjustment, the same may be referred to and determined by arbitrators as hereinbefore provided; but no readjustment shall be made of the rate of interest to be paid for the cost of such approach to said bridge.
“Sec. 5. Accounts of all expenditures, tolls and charges and payments required by the terms of this agreement shall be kept by the party authorized by this agreement to charge the same against either of the parties hereto. The account of tolls, however, to be- kept by the respective parties chargeable therewith, and all such accounts -shall be rendered’ to the proper parties during the month next succeeding the accruing of the items ihereof, and the same shall be settled and paid within thirty days after the rendition of each monthly account.
“Sec. 6. If it is found during the month of May or November in any year that the tolls and charges herein provided are not sufficient to meat the said interest and dividend due the first day of the next succeeding month, the parties of the second and third parts each covenant and agree separately with the first party, -and mutually covenant 'each with .the other to advance and pay the deficit immediately, and prorate according to the aggregate amount*189 of tolls and charges for .the use otf said bridge against each for the then current six months. The said advance, with interest thereon iat the rate of seven per cent, per annum, shall be refunded by the first party out of the tolls first thereafter accruing.
“Sec. 7. This agreement shall take effect on the first day of July, A. D. 1872, and the first semi-annual interest on said mortgage bonds of the first party and the first semiannual dividend on the oapital stock of the first party, provided for by this agreement, shall be payable on the first day of December, A. B. 1872, and the first of January, A. B. 1873, respectively, and semi-annually thereafter. If any difference shall arise between the parties or any of them as to the construction oí any of the provisions of this contract of the mode of performance, the same shall be submitted to arbitrators the qualification of arbitrators and an umpire, and the obligation to perform the award by them made, to be the same as hereinbefore provided in section four.
“This contract shall continue iu force and in operation until it shall be terminated by some one of the parties thereto giving notice in writing to the other parties of its election to terminate the same at the expiration of tw'o years from the giving of such notice, at the expiration of which two years the same shall terminate as to all the parties thereto included in’ such notice.
“In witness wheieof, each of the parties has hereto set its corporate seal, and has caused these presents to be duly signed by its president, the day and year first before mentioned. [signed.]”
In 1882 two other roads were admitted by the* bridge company upon terms substantially identical, save as to amount of dividends to be provided for stockholders (the
In 1896, because of lack of funds, the bridge company reduced its dividends from 4 per cent., due for the first half of that year, to 2 y2 per cent., and for the year 1897 they were reduced to 3 per cent, semi-annually, and a similar reduction for the year 1898. No dividend was declared for the first half of 1899.
This suit is by appellee John L. Dodd .and others, representing about 700 shares of the capital stock in the bridge company, out of an issue of 15,000 shares, against the bridge company, the Louisville & Nashville Railroad Company, and the Jeffersonvill'a, Madison & Indianapolis Rail.
1.For deficit in 6 per cent, dividends, semiannual, and interest.................. $2,239,875 00
2.Capital appropriated, with interest....... 443,842 36
3.To have reconveyed to the bridge company a lot of 10% acres of land, on which is built the northern approach to the bridge.
4.Taxes due by the bridge company....... 200,002 23
Total (not valuing -the 10% acres of land) .............................. $2,882,720 02
The record made up, ■ comprising several thousand pages, is unnecessarily large, for there is little or no dispute concerning the facts. The principal controversies over the
This suit is brought by the minority stockholders of the bridge company because they aver that the directors of the company refuse to sue to redress the grievances to the company 'complained of, and will not and ought not to take charge of this litigation, because of a conflict of interest and of duties, owing to their being also directors and interested in the Pittsburg, Cincinnati, Chicago1 & St. Louis Railroad Company and the Jeffersonville, Madison & Indianapolis Railroad Company. The circuit court granted plaintiffs relief in part only. The Pittsburg, Cincinnati, Chicago & St. Louis Railroad Company and the Louisville & Nashville Railroad Company have appealed, and the minority stockholders, represented by the plaintiffs below, have prosecuted a cross-appeal.
The Right of Minority Stockholders to Maintain a Suit for the Corporation.
The first question naturally presented is the right of minority stockholders of a corporation to maintain suit on
In the case at bar the holders of the majority of the stock of the bridge company are also owners of a majority of the stock of the Pan Handle Railroad. The same votes elect the board of directors or managers of each corporation. They select the same persons to fill these places in each board. If there is a misunderstanding between the two cor
Under this application of the rule discussed, it does not follow that every contract entered info between two corporations having directors in common is void, or even that it may be set aside upon the complaint of a single stockholder for that fact alone. Roberts v. Washington Nat. Bank, 11 Wash., 550, 40 Pac., 225, and notes, 2 Am. & Eng Dec. Equity, 272-284. We go no further than to say that upon an allegation of fraud on the pant of his directors, or upon an allegation of facts showing that the directors (who are also directors of another contracting corporation), because of conflict of interest and duty, could not or ought not to act in the matter, coupled with the further allegation showing material damage to the complaining stockholder by reason of the transaction between the two corporations, a court of equity will hear a single stockholder’s complaint, and, if the charges be sustained by the proof, will grant appropriate relief. In this case the complaint shows a contract between two corporations having directors in common, both
The case of allowing the suit by minority stockholders of'the bridge company against the Louisville & Nashville Railroad Company is not so free from difficulty. It is not claimed that the Louisville & Nashville Railroad Company had any part in the selection of the bridge company’s di
The court is of opinion that the cause of action set out may be maintained by the minority stockholders of the bridge company suing on its behalf, and joining it as a defendant, against all the defendants. Whether the grounds of laction are sustained is another question.
Is the Bridge Company Entitled to Collect from the Contracting Railroads Tolls to Produce 6 per cent. Semiannual Dividends on its Stock, in Addition to the Other Charges Provided in Contract of June 5, 1872?
The circuit court adjudged that in 1877 the contract of June 5, 1S72, had been modified by all the parties to it, so that 8 per cent. (4 per cent, semi-annually) only has since been paid by the contracting railroads for dividends upon the capital stock of the bridge company. The minority stockholders, haying sued for 6 per cent, semi-annual dividends for this period, prosecute a cross-appeal from the judgment.
It would be now impossible to equitably adjust the accounts of all interested parties upon the 12 per cent, basis. This is owing not only to the fact that a number of railroads have since been admitted to the use of the bridge on the 8 per cent, basis, and have settled theiir accounts and been discharged, and some have since gone out of existence, but it would priobablyi be impossible, owing to the great lapse of time, of death and removal of witnesses, and loss of proper records, to reach a just settlement. The stockholders of necessity knew all these years of this state of affairs. They should have taken action sooner, if determined not to abide the reduction. In all probability, if the point had not been yielded at the demand of the Ohio & Mississippi Company, other contracting _ railroads might soon thereafter have come to the same conclusion, and availed themselves of the privilege, under the contract, of withdrawing from the bridge. The parties have so long rested upon the present status, have treated it as satisfactory and valid till such material changes in conditions and circumstances have occurred as to constitute a.n estoppel against them. Furthermore, in view of the changed and changing conditions, the action of the bridge company
Misappropriation of Capital Stock.
Appellees assert that appellants and the other railroad companies using the bridge under the contract referred to herein have appropriated to their own use and distributed among themselves about $108,000 of the capital stock of the bridge company. Appellants deny the charge. In addition they plead the statute of limitation (the 10-years statute), section 2519, Ky. St.
Before considering the plea of limitation, we have deemed it best to determine whether the charge' was true in fact. Of the authorized capital of $1,500,000, $1,208,926 had been paid in when the railroads' entered upon their contract of 1872, and took charge of the bridge. In addition, the bridge company awed a floating debt of $131,619.35 shortly before or about the time of the contract of June, 1872. This was paid off partly with the proceeds of the remainder of the capital stock, leaving a balance of $87,513.05, which was paid in some time after the railroad companies took charge of the bridge traffic. This sum seems to have been placed in the bridge company’s sinking fund. In addition to that, the bridge company sold a right of way under its northern abutment in 1886 for $10,000, which wtas placed in the sinking fund. In 1885 the bridge company conveyed m the Jeffersonville, Madison & Indianapolis Railroad Company 10% acres of land in Indiana (forming the subject of a distinct branch of this litigation, and treated of further along) for $10,286.91. This sum also seems to have gone into the sinking fund. These three items, making a total of $107,799.96, are the only ones that “we are able
To understand how it may be worked out whether these sums have been .appropriated, it is necessary to state the purpose and uses of this' sinking fund, how created and supplied by the contracting railroads, and how disposed of. The contract of- June 5, 1872, required the contracting railroads (including, of course, all others who subsequently came to use the bridge Upon the same terms) to' provide, from tolls on their traffic passing over the bridge, for discharging the interest «annually of 7 per cent, per annum, and the principal of the mortgage debt of $800,000 against, the bridge, due in 1888. The main thing of this matter, so far as the bridge company was concerned, was to have its property -freed of the mortgage debt by the time it was due. So far as the railroads were concerned, it was to discharge this debt in the easiest way, and by the one least burdensome to their traffic. A number of experiments seem to have been tried before one was finally adopted as -the permanent sinking fund Scheme. In the first place, a rate, or schedule of nates, was adopted by the bridge company with the concurrence, and presumably upon an agreement with, the railroads, by Which it was thought and estimated that the fixed and current charges under the contract would be met. It is. plain that the railroad companies were interested in keeping the bridge tariffs down to a minimum figure, because they Were a charge upon their business, and necessarily affected the ability of the roads to get the traffic. The problem was to arrange a schedule of bridge .tolls in advance, so that surely enough, hut no more than enough, would be raised to satisfy the contract with the bridge company. As the volume of business fluctuated — a matter that it Was utterly impossible to foretell — there would be either
Subsequently a controversy arose between the bridge company, the Pan Handle Company, and 'the Monon Company over the surplus remaining after the discharge of the bonded indebtedness. This came up in an effort to settle an account of the bridge company against the Monon Company for tolls, in which numerous matters were in dispute. A suit was instituted by the bridge company against the Mo-non Company in the Jefferson circuit court. Availing themselves of the contract, the parties submitted its final decision to the Honorable H. W. Blodgett, of Chicago. He adjudged that the surplus arising from excessive rates of bridge tolls belonged exclusively to the railroad companies contributing thereto in the proportion of their traffic, respectively, passing over the bridge, and creating the surplus. Later the Louisville & Nashville Railroad Company, conceiving that the continuance of this excessive rate was an unnecessary burden, and a source of annoyance and trouble to the roads
If the $107,799.96 was in the -sinking fund all this time, its accretions in the way of interest or otherwise, under the pooling arrangement of 1881, acquiesced in and continued all this while, was properly used in discharging the bonds and interest. Whatever may have been the technical rights of the parties on this subject under the original contract, they seem to h'ave treated the matter in this manner as one satisfactory to themselves. Perhaps a reason was that, as the railroad companies were paying 8 per cent, annually net to stockholders on the total capital of $1,500,000, it was thought to be but right that they should have the use of the earning capacity of that total capital.
This brings us to consider whether this $107,799.96 is yet
In the record are annual statements, made up from the bridge company’s books. It is in evidence that the assets of the company shown in these statements, excepting the items of accounts against the Monon and Air Line Oom panies for tolls, are absolutely good, and convertible into cash at at least the figures used. By deducting from these assets all the liabilities of the bridge company that it will be compelled to pay, it is shown that there would be left, on a liquidation of the company as of the date of the last statement in evidence (issued a short while before the judgment in this case), a sum that would pay to all stockholders about $1.56 to the -dollar of the company’s capital. The assets so treated as good are the bridge structure (including fender piers) at the original cost of $2,134,261.50: the new draw span, $36,540.67; real estate, $68,011.50; securities (Pennsylvania Company 4y2 guaranteed bonds), $62,-412.75; cash and cash accounts, $117,310.20.
The item on the liability side of the statement “surplus of sinking fund divisible among the railroads contributing
It is true that there is owing a greater sum for taxes than is shown on this statement. At that time, however, the matter was in litigation. The railroad companies admit their liability for the difference, and say they are preparing to pay it, and the circuit court reserved control of the case to enforce their payment, if necessary. Therefore, if the $800,000 of bonds paid off for the bridge company be treated as capitalized, it is clear that no part of the capital, either of the $1,500,000 or of the $800,000, has been withdrawn by either of the railroad companies, or anybody else, for the very sufficient reason that it appears to be yet there in the property, in the bridge company’s custody and control.
The last item on the “statement,” viz., “Balance to credit of income account, $799,619.95,” is vigorously attacked as being false in fact and in toto. To our mind it is but a bookkeeper’s fancy. It is an .arbitrary entry to produce a balance between the two sides of the general statement-It might as appropriately have been entered in one of several other ways. But the name given to it is not material.
There were two other pieces of real estate sold by the bridge company, one sold ,in 1871 for $5,715.77, ;and the other for $730, sold in 1885. It is not shown that either of these pieces of property ever represented a part of the capital stock of the company, nor is it clearly shown what became of the proceeds. There was also a balance of undivided earnings claimed to be on hand in 1872, when the railroad companies took charge of the bridge. We assume the theory
The Draw Span and Render Piers.
Included among the .assets of the bridge company, representing ,an expenditure to that extent of its capital, is the cost of the two fender piers and a draw span built since the contract of June 5,1872, and within the last few years. The fender piers cost $20,000, and the draw span $86,510.67. It is the contention of appellees that by the terms of the contract of June 5, 1872, the contracting railroads ware to build such improvements, or, what is the same, furnish enough additional tolls to enable the bridge company to make them without using its other assets. Of course, if the duty was upon appellants to provide for such improvements at their own expense, it must be because of the terms of the contract alone. The draw span and fender piers are entirely new, and have been made necessary because of conditions not existing, and evidently not contemplated by the parties, when the contract of June 5, 1872, was entered into. In recent years the canal at Louisville has been completed and materially altered, so that, during most of the year, nearly all of the boating traffic on the Ohio river at that point passes through the canal, instead of using the river channel, as was formerly more generally done. The bridge crosses the canal. The great increase of boating traffic at that point, and the widening of the canal, made it a source of constant danger to the bridge structure, because of the liability of passing boats coming in contact
Both of these improvements were substantial and permanent betterments of the bridge company’s property, which must be left in good condition when the contract ends. They are not repairs, and are not charges, by the terms of the contralct, to be provided for by the railroads. It was proper that their cost should have been paid by the bridge company out of its unexpended capital.
The 10% Acres Conveyed to J. M. & I. R. R. Co.
In the contract of 1872 reference is made to the fact that the Jeffersonville, Madison & Indianapolis Railroad Company then owned, and. was by that contract 'conceded to own, the “northern approach” to the bridge. Exactly what is meant by that expression is uncertain. The Jefferson-ville, Madison & Indianapolis Railroad Company owned an
The railroad company pleads and relies on the statute of limitation to defeat the recovery for the bridge company. It is charged in the petition seeking to have this convey
We do not think it necessary to elaborate the idea that if, in fact, this approach belonged to the bridge company, its attempted conveyance by the directors, even by the stockholders’ concurrence, for that matter, would have been ultra vires. The approach of a bridge is as essentially a part of the bridge as any span or other part. To dispose of the approach is to dismember the bridge, and render it impossible for the bridge company to serve the public as required by its charter. Thompson, Corp., section 5373; Thomas v. R. R. Co., 101 U. S., 83, 25 L. Ed., 950; Whitcher v. Somerville, 138 Mass., 455.
Section 2519, Kentucky Statutes, is invoked by the railroad company. It is:
“In actions for relief from fraud or mistake, the cause of action shall not he deemed ¡to have accrued until the discovery of the fraud or mistake; hut no such action shall he brought ten years after the time of making the contract or the perpetration of the fraud.”
We are of opinion that that section of the statute can not he applied t'o this part of appellees’ suit. Although, strictly speaking, the Jeffersonville, Madison & Indianapolis Railroad Company may not have been a tenant of the bridge company, its relation was ¡so closely akin to that of tenant to landlord that the principles applicable to that relation ought to be applied. The principles governing the rights of .a tenant under .such state of case are fairly stated thus in Trabue v. Ramage, 80 Ky., 325, 4 R., 7: “We understand the law to be that a tenant can, under no> circumstances, after the lease and entry under his landlord, attorn to ¡another without his consent, or deny the title or claim under which he entered, whether the title or claim be good
The Reduced and Omitted Dividends for Years July, 1896, to July, 1899.
Having found that the contract of June 5, 1872, has been modified by the parties so that 4 per cent, ¡semi-annual dividends are provided for in lieu of the 6 per cent, named in the contract, we come to determine whether the contracting railroads' are to pay that rate at all events. It is the contention of the railroads that they did not contract to pay any fixed dividend or any sum; but that they agreed, each for itself, to pay the tolls charged against them for their use of the bridge, at a rate or rates to be fixed by the bridge company, but that such tolls “shall not be in excess of a toll or charge sufficient to produce in the aggregate a sum equal to the cost and expense of keeping in repair and taking care of said bridge and its approach, paying a dividend semi-annually of 6 (4) per cent, on said capital stock of $1,500,000,” the interest upon the bonds, provide a sinking fund to discharge its mortgage debt, the expense to maintain the bridge company’s corporate existence, and to pay the taxes assessed against it.
Whatever may have been the correct construction of this undertaking, the parties have from the first given to it the
As contracts are a meeting of the minds, or the agreement of the understandings, of those engaging in them, it is generally held to be not so material what words were used, as what was meant and understood by the parties. In disputes over the construction of written contracts, the words employed are first considered. But Where the terms are not entirely clear, and the parties' have themselves, through a long term of years, by a consistent course of dealing under the contract, with full knowledge of all the facts affecting their rights, construed its meaning and accordingly applied it, the usual labor of the courts is done. We have but to accept and enforce their own construction.
Here the parties have construed that each of the contracting railroads using the bridge was bound to pay to the bridge company, in proportion as the roads’ traffic over the bridge bore to the whole volume of traffic by all the contracting roads over the bridge, its proportion of a sum which would discharge the items named. This construction has been from 1872 till this suit was brought. In July, 1896, for the first time under the contract, the bridge company failed to pay its stockholders' a semi-annual dividend of at least 4 per cent. It then paid them 2% per cent. only. For each of the half years following, until 1899, only 3 per cent, was paid. : The dividend of July 1, 1899, was passed entirely. These reductions and omissions, on the basis of 4 percent., amounted to $142,500.
W>e are of the opinion that the contracting roads undertook, and that all parties then understood it so, that the tonnage of freight would produce, in the aggregate, a sum sufficient to pay all the fixed changes named in the contract, dividends included. Each for itself agreed to pay its own share, but all undertook, in the proportion that their traffic respectively bore to the total traffic of the bridge, to pay the whole of the sum needed to be raised for the bridge company under the contract. The railroad companies must have so understood it, for they have, in every instance till 1896, acted upon that theory, and lived up to it. The failure of the Monon and of the Air Line to pay their proportions began long before 1896, yet the other roads, parties to the contract, continued to pay enough of tolls, without question or complaint, to provide for the payment of the regular semi-annual payments of 4 per cent, dividends. When the Monon finally became insolvent, for the first time
We are of opinion that, for their failure to provide an income from tolls sufficient to pay the full dividend of i per cent, semi-annually for the years in litigation, appellants are liable, and that the circuit court has properly fixed and .apportioned the liability between them.
L. & N. R. R. Co. v. Bridge Co. Judgment.
Instead of reporting its tonnage of freight direct to the bridge company, the Louisville & Nashville Railroad Company delivered its freight destined for the North by way of Louisville to, and received its northern freight crossing this bridge from, the northern roads using the bridge. These roads made up their accounts and reports of freight so as to include the Louisville & Nashville Railroad Company’s. The latter settled and paid upon the basis of the reports made out by these roads, and they in turn paid the tolls to thehridge company. By the system of rebating above alluded to, this matter resulted in the rebates being made to the Northern roads alone. As these rebates were not in fact money paid out by the bridge company, but were credits entered on the current accounts against the respective railroads receiving them, the result was that, to the extent of these rebates, the Louisville &' Nashville Railroad Company was being required to pay a higher rate of tolls to the bridge company under the contract than other contracting xuads were paying. The Louisville & Nashville Railroad Com
Assuming that the Air Line land Monon accounts are insolvent (as they appear in fact to be), so far .as they embrace .paints of the liability for the Louisville & Nashville Railroad Company judgment paid off by the bridge company (estimated at from $34,000 to about $37,158.80, plus their proportion of interest; costs and damages upon that judgment), these liabilities, when ascertained, are to be treated as if they had been collected by the bridge company and then lost. In other words, this sum has been once collected by the bridge company from appellants and other roads as tolls on traffic. Instead of applying it to paying dividends, it was used to pay a judgment against the bridge company for which the Air Line and the Monon Companies were to that extent alone liable as among the railroads. Therefore, when .ascertained, the amount of unsatisfied liabil
In providing for the $142,500 of deficit in dividends, regard should be bad alsio to the sums that may be collected from the roads north of the river under this item for reimbursing the bridge company for its payment of the Louisville & Nashville judgment. For whatever sum. is collected will represent that much of tolls collected from the traffic by the bridge company, and which was available for dividends, but had been wrongfully diverted. So that, when collected again, it should be applied to its original purpose.
The Termination of the 1872 Contract.
The circuit court adjudged that the contract of 1872, as modified and heretofore explained, was still in full force and effect, and binding upon both appellants. The last clause of the contract provides for its termination as to all parties embraced in a two years’ notice given by one of the parties to terminate it. On the 25th of September, 1897, the Pitts-burg, Cincinnati, Chicago & St. Louis Railway Company and the Jeffersonville, Madison & Indianapolis Ráilroad Company gave notice to the bridge company of the former’s intention to terminate the contract on September 25, 1899. On the latter date the parties acted upon that notice, but the railroad company has since continued to send its freight to and from Louisville over that bridge upon the terms fixed by the bridge company as to all other freight. We are of opinion that by the notice and action under it the contract was terminated on September 25, 1899, as to the parties included in the notice.
Wherefore, the judgment upon the cross-appeal is affirmed. Upon the original appeal the judgment is reversed, and the cause is remanded for proceedings .and the entering of a judgment consistent with this opinion.
The whole court sitting.
Extension of opinion in response to petition for modification by plaintiffs:
What was meant by the expression in the opinion regarding taxes is, appellants will be required to pay the taxes alluded to in the litigation. But, in so far as they have paid them, they will not be required to again pay that amount. Appellants will be credited by the amounts they have paid to the bridge company on the taxes in litigation; in other words, they will have to pay to the bridge company the balance of the sum necessary for appellants to have paid to enable the bridge company to pay its taxes in question. The court adheres to the opinion that the contract of 1872 was terminated by the notice of 1897, and came to an end in 1899 as to .all parties to that notice. But we do not, of course, undertake to pass upon the rights and liabilities of the parties since the termination of the old contract. And in all other respects the petition for an extension and modification of the opinion is overruled.
The whole court sitting.