55 N.J.L. 192 | N.J. | 1893
The opinion of the court was delivered by
The defendants in error sued below to enforce a lien for materials furnished to Sylvester towards the construction of a house for the plaintiff in error. The sole question now pending arises upon an exception to the ruling of the trial court, that the filing of the contract between Sylvester and the plaintiff in error, without the accompanying-specifications, did not bar the lien.
The contract required Sylvester “ well and sufficiently to-erect and finish the mason work of the new building * * * agreeably to the drawings and specifications * * * signed' by the parties, * * * ” and to “ find and provide such good, proper and sufficient materials of all kinds whatsoever,, as shall be proper and sufficient for the completing and finishing of all the mason work of the said building mentioned in-the said specifications.”
In the present case the contract appears to require a resort to the specifications in order to ascertain its scope. The contractor was not to provide all the materials needed for the erection of the building, but only such as were necessary to complete the mason work mentioned in the specifications. What this mason work was could be determined only by reference to those specifications. It might be all the mason work of the building; it might be only part of it.
Under the decisions in the cases cited, which have stood for a generation as correct interpreters of the statute, we think the filing of the contract alone was insufficient.
The judgment below should be affirmed.