*1 discussion or treat- tention does not merit light of relevant factors be determined supra held that have danger posed an ment here since we such as: The inherent theory on the aircraft; expertise possessed, repre- the trial court’s instructions or retrial, defendants; liability were error and possessed, by the of strict sented as contradictory possibility knowledge hopefully, intended use of the defendants’ special aircraft, contributory negli- will not verdicts exist. gence assumption the risk of or trial a new remanded for Reversed and plaintiffs, any, in of fac- if consideration ap- Costs consistent with this opinion. aircraft, age of the its tors such as the pellants. previous repair and status and record of previous accident. J., maintenance and McQUADE, DONALDSON C. BAKES, SCOGGIN, District JJ., Plaintiffs-respondents argue that Judge (Retired), concur. the recent case of S. H. Kress & v.Co. Godman, 561 (1973) do
militates our result here. We agree. personal services Kress
were and there here defendants involved repairs make and it was al
were called to leged negligently. that such were also, argued following There it was Heating, PIERSON, A. John d/b/a repairs inspection in immediate Plaintiff-Respondent, repair defects in area would have revealed parts an accident. which later caused Sewell, hus- SEWELL and Marian Max F. Kress was reversed on the sole basis Defendants-Appellants. wife, band duty repairman on the the existence of a No. 11431. questions and a breach thereof were jury. have been submitted to the should Supreme Court of Idaho. implicit There it is of action cause Aug. 8, 1975. brought negligence contributory negligence of the was a owner at bar we hold
defense. So the case assumption contributory negligence plaintiffs’ theo are defenses to risk implied warranty.
ry of
In summary plaintiffs-re- we hold that
spondents theo- entitled to have their were
ry implied warranty submitted to
jury. the case involved rendition Since service, of action does a cause implied warranty in
not exist for breach part of the ac- of fault on the absence jury
tor. The be instructed should contributory negli- defenses of
gence assumption avail- the risk are defendants-appellants.
toble special also assert jury
verdict returned forms another,
inherently contradictory to one fatally
therefore defective and should have rejected by That con- court. *2 appellants’ property. The trial court
found this work was done on a time and basis, computed by the lineal foot installed, heating ducts were being customary in trade.
During
dwelling,
the construction of the
Brothers,
contractor,
general
Butler
experienced financial difficulties. Subse-
quently, appellant Max
had further
payments
progress
general contrac-
to the
January
tor
Max Sew-
withheld.
requested
ell
from the various subcontrac-
respondent,
tors,
so
including
lien waivers
lending
release
that the
institution would
necessary
funds. Each subcontractor
Respondent gave
a lien
executed
waiver.
January
appellant on
his lien waiver to
then dis-
The
proceeds
of
bursed
working
the various subcontractors
loan to
of re-
exception
dwelling
on the
with
spondent.
the subcontractors
All
exception
respon-
of
paid in full with the
Kennedy,
Lloyd Walker,
&
Walker
funds
nothing
dent,
from
who received
J.
Falls,
defendants-appellants.
Twin
for
Re-
lending institution.
released
lien March
spondent
filed a notice
Jerome,
plaintiff-re-
for
Jones,
T.
James
spondent.
filing
notice
days after
his
Several
of ac-
this cause
respondent brought
claim,
McQUADE, Chief Justice.
trial court
The
lien.
tion to foreclose
This
an action to
a mechan-
foreclose
discovery of
upon appellants’
found
ic’s lien.
affirm
We
difficulties,
financial
prime
contractor’s
trial court insofar
it ordered
Butler
assumed
appellant Max Sewell
foreclosed.
find
the lien was
We
the con-
arising
obligations
from
Brothers’
timely
signed
filed and that the lien waiver
trial court
dwelling. The
struction
respondent
was of no force or effect.
requested a lien
found
However,
we reverse
award of
defi-
for
consideration
respondent,
from
ciency judgment against appellants in the
full. The
payment in
be
was to
event that the
foreclosure
notice of
found that
trial court also
claim,
satisfy respondent’s
sale fail to
stat-
with
in accord
lien was filed
claim
portion
reverse
decree
or
had
been cancelled
it
ute
granting respondent
personal judgment
$2,195.85
discharged and that
otherwise
against appellants
for
for the
due
amount
per-
the work
respondent
was due
supplied.
materials and labor
The
furnished.
materials
and the
formed
lien foreclosed
prop-
real
trial court ordered
are
owners of
claim,
attorney’s
his
respondent’s
Respondent,
satisfy
erty
County.
in Blaine
work-
plus
costs
in the sum
ing
subcontractor,
$750.00
as a
labor and
fees
furnished
appel-
court held
amount
beginning
$203.15.
October
pro-
if the
any deficiency
liable for
lants
connection
of a heat-
installation
insuffi-
sale were
system
of the foreclosure
ing
ceeds
dwelling being
in a
constructed
perform labor
due, plus
attor-
furnish material to
cover
cient
construction,
in the
be used
court also
alteration
ney’s fees and costs.
repair
personal judgment
building
of a
recovery
or structure. Boise
allowed
Payette Lumber
appellants for the total amount
Weaver.5
awarded.
respondent
The evidence shows that
sub-
contractor
the prime
contracted with
con-
assign
urges
Appellant
eleven
tractor,
Brothers,
Butler
heat-
install a
ments of error which can be summarized
system in
ing
appel-
the construction of
three
into
main issues:
dwelling.
such,
lants’
supplied
As
file
respondent
Did
a valid
(1)
through
materials and
employees
prereq-
timely notice
of lien as a
of claim
therefore,
and,
right
has
I.C. 45-501 a
action;
instituting
uisite
dwelling.
to a lien on
perfect
To
right to a
Did
waive his
*4
lien,
subcontractor,
respondent,
such as
lien
of
lien waiv-
by
claim of
must file
of
notice of claim lien within
January 13, 1972;
er on
sixty days following the subcontractor’s
subject
appellants
Are
(3)
to
cessation of
materi-
furnishing
labor or
of
judgment for the amount awarded?
als. I.C. 45-507.
appellants’
Many
assignments of error
of
argue
first
that the trial
findings
by the
deal with
factual
respondent
in finding
court erred
that
fur
many
trial
re-affirm the rule
court. We
14,
nished labor
on January
and materials
stated,
of,
credibility
times
that
1972,
complete
in order
his
to
subcontract
weight given to,
at
presented
the evidence
ap
in connection with the construction of
exclusively
province
is
of the trial
They
respon
pellants’ dwelling.
claim
of
judge when
acts as finder
the court
employees completed
dent’s
their
on
work
v.
fact.
Ivie
Peck.1 It
that find
follows
1971,
dwelling in
there
December
ings
substantial,
fact supported by
of
com
Upon
fore,
timely
lien
was not
filed.
petent, although conflicting,
will
evidence
ample,
record we find
examination
appeal.
not be disturbed on
Id.2
conflicting
to
competent, although
evidence
Mechanic’s and
related
other
re
finding
support
trial court’s
statute,
statutory
liens are creatures of
ma
performed
supplied
spondent
labor
requirements
substantially
must be
com
January 14, 1972.
terials on
plied
perfect
with in order to
a valid lien.
respondent’s
Assuming
Boone v. P.
Logging Company.3
arguendo
& B.
Yet,
these
labor and
liberally
employees
lien statutes are
did
to be
furnish
14,
1972,
argue
provisions
appellants
construed:
January
“The
me
our
extending
not
law,
chanics’ and
lien
as
a trivial nature
laborers’
was of
well
work
They
running of
lien.
statutes,
liberally
all other lien
must be
time for the
in-
dwelling,
argue
construed with
their ob
that construction
a view to effect
substan-
promote
system, was
jects
justice.”
heating
cluding the
Seafoam
December,
six-
completed
with
Corp.
Mines
Vaughn,4
purpose
tially
v.
claim
filing a notice
compensate persons
period
these
statutes is to
who
ty-day
1166,
352,
1170
625,
342,
(1972).
P.2d
53
See
1. 94 Idaho
495 P.2d
Idaho
1119
4. 56
supra
Parker,
Accord,
Parker,
v.
v.
118,
(1936).
Idaho
P.2d
Durfee
90
410
Durfee
Etc. Mines
Idaho
v.
(1965).
Etc. Co.
1;
Mine
962
n.
(1911).
300,
P. 301
118
Idaho
20
Accord,
Plumbing
Schuler,
Perry
96
Accord,
(1925).
516,
150
P.
234
Idaho
5. 40
494,
;
v.
Mitchell
P.2d 584
Idaho
581
McAdoo,
1057
P.
206
Idaho
v.
35
McGill
Flandro,
95
506 P.2d
Idaho
455
Lewiston,
City
(1922) ; Chamberlain
See
P. 1069
129
See
Idaho
Idaho
Packing Corporation,
Layrite
Company
Eastern
Lux,
Products
Weber
appellant
found
running
Thus,
per-
the March
court
Max Sewell
from that time.
sonally
9, 1972,
asked
untimely.
be
for a lien
filing would
understanding
principle
fol
We re-affirm
money
necessary
waiver was
so that the
six
lowed in Mitchell v. Flandro that the
from the
loan
re-
construction
would be
ty-day period
filing
liens cannot
for the
by
lending
leased
institution in order
furnishing
be extended
revived
or
pay respondent.
or
the con
trivial labor materials once
prior
Pierson
completed.
testified that
tract has
Sewell,
execution of the
Max
di
per
or
“Ordinarily,
an article
furnishing
inference,
rectly
guaranteed
if
is
forming a service trivial in character
completed
his
subcontract he
not
the time
to extend
sufficient
compensated.
be
would
Max Sewell denied
expired
or to
claiming
revive
this. He
he
testified that
realized that the
lien,
article
or the
where the
is furnished
funds from the
loan
not
would
service
com
rendered
a substantial
after
subcontractors;
be sufficient
all
pletion
contract,
article
and the
upon
but
understanding
that Butler
required
the terms
expressly
arrange
compensate Pierson, he
would
thereof.”"7
secured
from all of the sub
waivers
material
When additional
contractors so that the
relied
for fil-
to extend the time
*5
would disburse the
from the con
claim,
ing of the
lien
must
the
claimant
loan
all the subcontractors
struction
show that the materials or
were ac-
exception
with
of Pierson. Whatever
tually
in constructing
repairing
used
may have been Pierson’s motivation for
structure,
they
reasonably
waiver,
e.,
executing
receipt
i.
the lien
complete
necessary to
accord-
construction
payment
disbursement of the loan
ing to the terms of the contract.8
by
lending institution,
monies
evidence
presented
Evidence was
effect
lacking
parties
to indicate that the
ex
that
respondent’s
spent
one of
employees
pressly agreed
payment
that
would be
“good
day”
half
installing registers, chang-
forthcoming to Pierson from Sewell based
ing two air ducts and replacing the ther-
upon his
execution of
waiver. Taken
Respondent
mostat.
testified
that
so-
value,
at
testimony
parties
face
of both
called “finishing” work was considered the
they
indicates that
different
had
intentions
final work
under
contract and is cus-
at
time of
execution of
lien
tomarily
in
done
The trial
trade.
expressed,
pur
intentions never
as to the
finding
court’s
that
work
Janu-
pose and
Clearly,
effect
waiver.
ary 14, 1972,
part
was done
con-
was no
meeting
there
minds. The
tract and therefore that the lien of March
parties
minds of the
must meet on all
timely
was
9, 1972j
supported
filed is
terms before a
is formed.9
contract
the record.
argue
general
next
the trial
The
rule is that
an ex
press
court erred
failing
in
find
waiver
lien
of mechanic’s
must be
13, 1972,
supported by
January
executed on
in
consideration
order to be
respondent’s
waived
rights.
The
effective and
McCorkle
binding.
trial
v. Law-
Supra
Accord,
Mendenhall,
Gem
Lumber
9.Turner
State
n. 2.
Witty,
Co. v.
37 &
Lumber
P.
See Pacific
Dailey,
Timber Co. v.
111 P.
60 Wash.
7.
son &
party.13
contracting
consid-
third
characterization, the instant
court’s
in
promise
payment
eration would be
support the trial
The evidence does not
fails, the
such consideration
full. Where
appellants initially
finding
court’s
con
Thompson
no
lien waiver is of
effect.
directly
tracted
for the
“The
Property
states:
Real
furnishing
heating system
of a
and labor
agree-
right to a lien is not waived
installing
system;
in
fact,
and in
ment of waiver executed
consideration
pre-trial
contrary.
order is
The
promise
performed.”
of a
which was
finding that a direct contractual relation
reasons,
purported
For the above
waiv-
ship
appellants
respon
existed between
er failed and was of no effect.
work,
dent from the commencement of
out
implied
side
45-
I.C. §
Appellants’ final contention is that
et seq.,
must be set
aside. Wood
erroneously
the trial court
held them Sadler.14
liable for the
due
on the labor
ap
trial court also found that
provided
respondent.
We
pellant Max Sewell assumed the contract
find that the trial
in granting
court erred
and obligations
general contractor,
respondent personal
ap
judgment against
Butler Brothers
Company,
Construction
pellants for
the total amount due on
when that firm encountered financial diffi
respondent’s
claim and also find that
during
culties
dwelling.
awarding respondent
trial court erred in
The record indicates that Max
deficiency judgment
appellants
instrumental
securing
lien releases from
any portion
may
of the claim
remain
the various subcontractors, including re
unsatisfied after the foreclosure sale.
spondent. The record does not demon
strate that Max
respon
court found
took the
further
step
provided
dent
request
building
at
assumed the
services
contract and
appellants
the obligations
general
and that this
contractual rela
contractor.
*6
tionship
respondent
note that
between
We
appellants
and
testified that sev
homeowners,
was on a time
eral
including appellants,
and materials basis.
took
While
provides
I.C.
45-501
“money payout”
over the
that the contractor
when Butler
§
experienced
“shall be
Brothers
agent
held to be the
financial difficulties.
owner
But,
. .” this
applies only
Mr. Butler testified that bills for la
purposes
supplies
for
directly
of mechanics’ and
bor and
to
material-
submitted
foreclosure,12
men’s
the lending
liens
their
were disbursed
does
encompass
directly by
not
agency
usual
rela
institution. Butler also
tionship, whereby, a
testified that
contract
Sewell did not take
an
over
Dailey,
(Ky.Ct.App.1953);
10.
Costs to ; Rig gen Perkins, v. (1907). Accord, P. 24 13 Idaho P. 962 City Lewiston, Chamberlain v. 23 Idaho Lumber P. 1069 Weeter Fales, 75 Idaho P. 289 20 Idaho Flandro, See Mitchell v. benefits, having from for real these receive funds commissions received the fact subsequently that Pierson estate filed his lien not- sales. withstanding any the waiver did not in determined that there it was When way prior personal obligation affect remaining with the lend- insufficient funds Sewell assumed to obtain the lien order and pay all claims Butler ing institution to waiver. between Sewell discussed Sewell, that But- It is to be it Butler and Pierson to the effect noted that was Butler, together negotiations who ler and Pierson had worked conducted contracts, Pierson, many obtain lien waiver from previous necessary had on Sewell was real estate salesman when Pierson assumed- ly experienced in agreeable giving Butler real estate transactions. occasions obligation. my opinion these facts it is time Under additional to meet obligated personally became Following this it determined Sewell discussion was Pierson, all the trial get lien waivers from Sewell would except court be affirmed. and that all should claimants pro- claims, paid would be their without lend-
rating money available from the
ing institution. approached Pierson to ob-
When waiver, expectation
tain his lien Pierson’s
was that he would execute the lien
paid
See, Perillo, Contracts, Calamari & 73§ Supreme of Idaho. Court Aug. 8, 1975. ' At the time that Sewell obtained the lien Pierson, obligated waiver from he himself money
to see that Pierson obtained —i. e., he thus assumed this as a obli-
gation. then used this lien waiver having
as the basis for institu- payment
tion release funds for to all claimants, and
other thus Sewell obtained agreement benefits of this ex- See, Perillo, supra,
tent. Calamari & my It that Sewell
286(b). conclusion
