PIERCE FOUNDATIONS, INC. v. JAROY CONSTRUCTION, INC.
No. 2015-C-0785
Supreme Court of Louisiana
May 3, 2016
190 So. 3d 298
FOR IMMEDIATE NEWS RELEASE NEWS RELEASE #025 FROM: CLERK OF SUPREME COURT OF LOUISIANA
The Opinions handed down on the 3rd day of May, 2016, are as follows:
BY CRICHTON, J.:
2015-C -0785 PIERCE FOUNDATIONS, INC. v. JAROY CONSTRUCTION, INC. (Parish of Jefferson)
Pursuant to the foregoing, we hold that Pierce’s lawsuit was timely filed against the general contractor and its surety, Ohio Casualty, and that the failure of the plaintiff to perfect its privilege against the public authority (as found by the trial court) does not defeat its right of action against the surety. The decision of the court of appeal is reversed and the decision of the trial court is reinstated. REVERSED.
KNOLL, J., dissents and assigns reasons.
GUIDRY, J., dissents and assigns reasons.
HUGHES, J., dissents for the reasons assigned by Guidry, J., and assigns additional reasons.
PIERCE FOUNDATIONS, INC. VERSUS JAROY CONSTRUCTION, INC.
NO. 2015-C-0785
SUPREME COURT OF LOUISIANA
05/03/16
CRICHTON, Justice.
This case involves the interpretation of two provisions of the Public Works Act (Act),
BACKGROUND
This matter arises out of a public works project for the construction of a gymnasium in Terrytown, Louisiana. Pursuant to a contract between JaRoy Construction Inc. (JaRoy or contractor) and Jefferson Parish Council (Jefferson Parish), JaRoy was to serve as the general contractor. In compliance with
In July 2009, Pierce filed a Petition for Damages in Contract against the contractor, and, in July 2010, amended the petition to add Ohio Casualty as a defendant. Pierce alleged that Ohio Casualty and the contractor were jointly and severally liable to Pierce for the failure of the contractor to perform under the contract. Ohio Casualty asserted several affirmative defenses to these allegations, one of which was that Pierce failed to comply with conditions precedent to filing a claim against the surety. When the contractor filed a petition for bankruptcy protection in December 2010, the lawsuit proceeded solely against Ohio Casualty.
On October 17, 2011, when the project was substantially completed, the Jefferson Parish government filed a notice of acceptance of work with the Jefferson Parish mortgage records office. This occurred over a year after Pierce amended its lawsuit to add Ohio Casualty as a defendant. It is undisputed that Pierce never filed a sworn statement of claim in the mortgage records.
Before trial, Ohio Casualty filed a motion for summary judgment, contending that Pierce was required to comply with the notice and recordation requirements of
The trial court granted Ohio Casualty’s motion in part, only to the extent that there is no privilege in favor of [Pierce], and otherwise permitted the suit to proceed. Ohio Casualty sought supervisory review, and the court of appeal denied relief, stating:
On the showing made, we decline to exercise our supervisory jurisdiction. K Construction, Inc. v. Burko Construction, Inc., 629 So. 2d 1370 (La. App. 4 Cir. 1993); Wilkin v. Dev Con Builders, Inc., 561 So. 2d 66 (La. 1990).
Pierce Founds., Inc. v. The Ohio Casualty Ins. Co., 12-0859 (La. App. 5 Cir. 11/09/12) (unpublished).
On December 13, 2012, after a bench trial, the trial court rendered judgment in
Ohio Casualty suspensively appealed the judgment, contending that the trial court erred in failing to dismiss it prior to trial, because Pierce’s failure to comply with the notice provisions of
We then granted Pierce’s application for a writ of certiorari. Pierce Founds., Inc. v. JaRoy Constr., Inc., 15-0785 (La. 6/5/15), 171 So. 3d 938.
RELEVANT LAW
In 1918, the legislature enacted Act 224, the precursor to the modern Public Works Act,
The effect of these provisions is to give certain classes of persons not enjoying privity of contract with the general contractor or with the governing authority a claim nevertheless against the general contractor and his surety and in some instances a claim against the governing authority itself.
Id. at 70. The laws also protect a public authority complying with the requirements of the statute from expenses caused by the failure of the contractor to perform the contract. 561 So. 2d at 71.
The statutory framework set forth in the Act accomplishes this purpose, first, by mandating that, when a public entity enters into a contract in excess of $25,000.00 for the construction, alteration, or repair of any public works, the contractor is required to post a bond in a sum of not less than fifty percent of the contract price for the payment by the contractor or subcontractor to claimants as defined in R.S. 38:2242.
Any claimant2 may after the maturity of his claim and within forty-five days after the recordation of acceptance of the work by the
The Act also addresses a claimant’s direct right of action on the bond against the general contractor and/or surety, making clear that the subcontractor maintains a separate right of action outside of the parameters of the Act. To that end,
Nothing in this Part shall be construed to deprive any claimant, as defined in this Part and who has complied with the notice and recordation requirements of R.S. 38:2242(B), of his right of action on the bond furnished pursuant to this Part, provided that said action must be brought against the surety or the contractor or both within one year from the registry of acceptance of the work or of notice of default of the contractor except that before any claimant having a direct contractual relationship with a subcontractor but no contractual relationship with the contractor shall have a right of action against the contractor or the surety on the bond furnished by the contractor, he shall in addition to the notice and recordation required in R.S. 38:2242(B) give written notice to said contractor within forty-five days from the recordation of the notice of acceptance by the owner of the work or notice by the owner of default, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor or service was done or performed.
The court of appeal, construing
Ohio Casualty urges this Court to affirm the court of appeal, arguing that Pierce’s failure to file the sworn statement of claim is fatal to its cause of action against Ohio Casualty. Ohio Casualty argues that exclusive rights of action against the surety are set forth in
Pierce argues that the court of appeal decision frustrates the purpose of the Act – specifically, that the Act was adopted to protect those performing labor and furnishing materials for public works, as set forth in Wilkin, not to immunize sureties from lawsuits brought in contract related to unpaid funds. Pierce contends, inter alia, that the court of appeal erred by converting the permissive may of
ANALYSIS
Legislation is the solemn expression of the legislative will; thus, the interpretation of legislation is primarily the search for the legislative intent. Cat‘s Meow, Inc. v. City of New Orleans, 98-0601, p.15 (La. 10/20/98), 720 So. 2d 1186, 1198; La. Safety Ass‘n of Timbermen Self-Insurers Fund v. La. Ins. Guar. Ass‘n, 09-0023, p.8 (La. 6/26/09), 17 So. 3d 350, 355-56. See also
Because this matter involves the interpretation of statutory provisions and only questions of law are presented, review by this court is de novo. See, e.g., Red Stick Studio, 56 So. 3d at 187. Additionally, because the case involves the Public Works Act, it must be strictly construed. Wilkin, 561 So. 2d at 75.
The court of appeal found that Ohio Casualty was entitled to summary judgment before trial, because Pierce did not comply with the notice and recordation requirements of
We disagree with this holding, and find that where the subcontractor fails to comply with the notice and recordation requirements of
The fundamental error in the court of appeal’s analysis is that it renders the permissive may in
Instead of employing this interpretive principle, the court of appeal references the legislative history of
However, an examination of 1985 La. Acts 244, § 1 does not support the court of appeal’s assumption that the legislature intended to modify or otherwise limit
Further, the court of appeal’s interpretation of
We acknowledge that
A court of appeal case, “K” Construction, Inc. v. Burko Construction, Inc., 93-1338 (La. App. 4 Cir. 12/16/93), 629 So. 2d 1370, authored by former Chief Justice John Dixon sitting pro tempore, is instructive in its analysis of the relationship between
[The sureties] claim that although R.S. 38:2242 B says may instead of shall, R.S. 38:2247‘s reference to the formalities of notice/filing and recordation as requirements causes the formalities to become mandatory. The sureties contend that the formalities are discretionary in R.S. 38:2242 B because that provision deals with perfecting a statutory claim against the prime contract funds in the hands of the public owner. R.S. 38:2247, they believe, is a separate provision for filing suit against the sureties in which the permissive provisions of R.S. 38:2242 B become mandatory.
The sureties also claim that the may in R.S. 38:2242 simply means that a claimant has the option to: 1) file and record a sworn statement to perfect his statutory claim, or 2) not file and record a sworn statement and not have a perfected statutory claim. R.S. 38:2247, the sureties assert, is what creates a cause of action against the bond and it requires a perfected claim to proceed against the bond.
The statutes do not, however, operate together as the sureties suggest. R.S. 38:2242 gives no consequence of not filing and/or recording the sworn statement. And, styled as a prescription article, R.S. 38:2247 does not actually create a cause of action on the bond. The assumption that the legislature intended to explain or limit R.S. 38:2242 in R.S. 38:2247 is not warranted.
We agree with the Burko court that any other interpretation of
Because the statutory language at issue is ambiguous, and because the purpose of the Act is to assist laborers in recovery – not to immunize sureties where parties may proceed in contract – the purpose of the Act is effectuated by this decision.
DECREE
Pursuant to the foregoing, we hold that Pierce’s lawsuit was timely filed against the general contractor and its surety, Ohio Casualty, and that the failure of the plaintiff to perfect its privilege against the public authority (as found by the trial court) does not defeat its right of action against the surety. The decision of the court of appeal is reversed and the decision of the trial court is reinstated.
REVERSED.
PIERCE FOUNDATIONS, INC. VERSUS JAROY CONSTRUCTION, INC.
NO. 2015-C-0785
SUPREME COURT OF LOUISIANA
05/03/16
KNOLL, Justice, dissenting.
I disagree with the majority’s finding failure to comply with the notice and recordation requirements of
As the majority correctly notes, the issue in this case concerns a subcontractor’s direct right of action on the bond against the surety to which
Nothing in this Part shall be construed to deprive any claimant, as defined in this Part and who has complied with the notice and recordation requirements of R.S. 38:2242(B), of his right of action on the bond furnished pursuant to this Part, provided that said action must be brought against the surety or the contractor or both within one year from the registry of acceptance of the work or of notice of default of the contractor; except that before any claimant having a direct contractual relationship with a subcontractor but no contractual relationship with the contractor shall have a right of action against the contractor or the surety on the bond furnished by the contractor, he shall in addition to the notice and recordation required in R.S. 38:2242(B) give written notice to said contractor within forty-five days from the recordation of the notice of acceptance by the owner of the work or notice by the owner of default, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor or service was done or performed. Such notice shall be served by mailing the same by registered or certified mail, postage prepaid, in an envelope addressed to the contractor at any place he maintains an office in the state of Louisiana. (Emphasis added).
Clearly,
The recognition of this direct action has been in the PWA since its inception, providing in Section 3 of Act 224 of 1918: nothing in this act shall be so construed as to deprive any person or claimant within the terms of this act of his right of action on the [bond], which right shall accrue any time after the maturity of his claim.2 Notably in Act 16 of 1962, the Legislature amended
Nothing in this Part shall be construed to deprive any person or claimant within the terms of this Part of his right of action on the contractor’s bond which shall accrue at any time after maturity of his claim, which said action must be brought against the surety and/or the contractor within one year from the registry of acceptance of the work or of notice of default of the contractor.
The Legislature stated its purpose in enacting Act 16 was [t]o amend and re-enact Section 2247 … to define the rights of persons or claimants to have or bring a right of action against a contractor or the surety. By expressly defining and limiting the right of action, the Legislature brought the claimant’s direct action on the bond against the surety squarely within the protection of the PWA.
The LOUISIANA PRACTICE SERIES: LOUISIANA CONSTRUCTION LAW § 13:14 provides:
The Louisiana Public Works Act contemplates that if there are unpaid claims at the expiration of forty-five days after recordation of acceptance or default, the public body can file a concursus proceeding, citing all claimants, the contractor and the surety on the bond, and requiring them to assert whatever claims they have against one another. If the public body does not file such a proceeding, any of the unpaid claimants may do so. In these proceedings, all claimants can assert their claims against the surety and the contractor, and those claims are paid in preference to any claims of the governing authority.
As a practical matter, the concursus proceeding is very seldom used because claimants have a direct right of action against the contractor and the surety on the bond. This action can be filed any time after maturity of the claim, rather than requiring that the claimants wait for forty-five days after acceptance of the entire project, which in many cases could occur long after the claim matures.
It further provides:
The Public Works Act also provides a separate remedy for claimants against the contractor and its surety who have complied with notice and recordation requirements of
La. R.S. 38:2242(B) . If the claimant is a materialman or laborer, this separate suit must be filed by the claimant against the contractor or the surety within one year after recordation of acceptance or notice of default. The Louisiana Supreme Court has held that a subcontractor’s suit is also governed by the one year prescription periodLa. R.S. 38:2247 .
Id. at § 13.11.
As authority, the authors cite to
Nothing in this Part shall be construed to deprive any person or claimant within the terms of this Part of his right of action on the contractor’s bond which shall accrue at any time after maturity of his claim, which said action must be brought against the surety or the contractor or both within one year from the registry of acceptance of the work or of notice of default of the contractor; except that before any person having a direct contractual relationship with a subcontractor but no contractual relationship with the contractor shall have a right of action against the contractor or the surety on the bond furnished by the contractor, he shall record his claim as provided in R.S. 38:2242 or give written notice to said contractor within forty-five days from the recordation of the notice of acceptance by the owner of the work....
The Court concluded:
… an unpaid subcontractor having a direct contractual relationship with the contractor may sue on the contractor’s bond without filing and recording a sworn claim or giving written notice to the contractor. Although the action against the contractor is subject to the ten-year prescriptive period ordinarily applied to actions in contract,
La. Civ. Code art. 3499 , the action against the surety on the bond must be brought within one year from the registry of acceptance of the work by the governing authority….
In what can only be logically explained as action taken in response to the Honeywell holding, the Legislature immediately enacted Act 244 of 1985, amending
Read this way, the specific language of
The Legislature went one step further in Act 244 by adding a provision to
Nowhere does the majority opinion address this key provision in the PWA—the immunity granted the surety under
The majority randomly dismisses the mandatory requirements of notice and recordation and states: We disagree with this holding, and find that where the subcontractor fails to comply with the notice and recordation requirements of
The majority opinion further fails to address the strong policy consideration of ensuring proportional payment of all claimants, which is the primary purpose of
the PWA, by requiring the queuing of claimants through recordation and preventing depletion of the bond until all claimants have an opportunity to notify and record their claims.
In its analysis, the majority summarily dismisses the appellate court‘s examination of legislative history in its search for legislative intent. However, by not addressing the steady and consistent changes made by the Legislature in direct correlation to misinterpretations rendered by this Court, I find the majority mistakenly focuses on its interpretation of the specific words used by the Legislature without examining why the Legislature employed those very words— its purposeful intent to rectify this Court‘s repeated attempts to expand the PWA beyond its terms. This jurisprudential history and later legislative amendments “overruling” this Court‘s opinions are very telling and important to a correct statutory interpretation of the PWA.
Concededly, the direct right of action of a subcontractor in direct contractual
privity with the general contractor and his surety most likely first arose from our
suretyship provisions.
Legislature in direct response to interpretations of this Court—clearly reveals this transformation. The Legislature said as much in Act 16 of 1962.
Likewise, this Court has over time revised its interpretation of the limits of a
surety‘s liability on the bond, starting from
Early on this Court held the bond was statutory and therefore limited by the statute:
But the claimant contends that the bond executed by the appellant surety company is broader in its terms than those required by the statute. The bond provides, among other things, that the surety company will pay, if the contractor does not, “all bills for materials and labor entered into in the construction of said work or used in the course of the performance of the work.” The engagement of the contractor‘s surety to pay for material and labor “used in the course of the performance of the work” is, admittedly, more comprehensive than the requirement of the statute.
The claimant argues that, whatever may be the inhibition imposed by the legislative act on the public body executing the contract and bond, there is no inhibition against the incurring by the contractor‘s surety of a liability beyond that fixed by the statute. In support of his argument, claimant cites certain decisions from other jurisdictions.
But we see no reason for departing from the well-established rule of our own jurisprudence that in a statutory bond the statute must be read into the instrument; superadded stipulations must be disregarded and necessary obligations which have been omitted must be supplied. John H. Murphy Iron Works v. United States F. & G. Co., 169 La. 163, 124 So. 768; Minden Presbyterian Church v. Lambert, 167 La. 719, 120 So. 61; Miller v. Bonner, 163 La. 342, 111 So. 776; Davis v. West Louisiana Bank, 155 La. 245, 99 So. 207; Id., 155 La. 252, 99 So. 210.
Long Bell Lumber Co. v. S.D. Carr Const. Co., 172 La. 182, 187-88, 133 So. 438, 439-40 (1931). Then in Construction Materials, Inc. v. American Fidelity Fire Ins. Co., 388 So.2d 365, 366-67 (La. 1980), with Justice Dennis as organ, this Court contrarily held a surety could contractually extend his liability:
The statute‘s aim is to define the types of claims to be given protection and to make the governing authority responsible for their deduction and payment out of the contractor‘s receipts. The legislation clearly does not forbid a contractor and his surety from providing security for the payment of claims falling outside the ambit of statutory protection. In fact, the Public Works Act makes clear that it shall not be construed to deprive any person of his right of action on the contractor‘s bond.
La.R.S. 38:2247 , in pertinent part, provides:“Nothing in this Part shall be construed to deprive any person or claimant within the terms of this Part of his right of action on the contractor‘s bond which shall accrue at any time after maturity of his claim . . . .”
Defendant surety argues that this provision was intended to provide protection only for “a claimant within the terms” of the statute. We think it clear, however, that the section was designed to protect “any person” with a “right of action on the contractor‘s bond.” Claimants whose claims fall within the ambit of the statutory protection have no need of the savings clause. It was specifically for the benefit of those persons and claimants whose rights depend solely on
the contractor‘s bond that the section preserving their actions was added. The surety also contends that extending coverage of Public Works bonds will conceivably allow extra-statutory claims to dilute the protection afforded traditional claimants and public bodies. These are legitimate concerns addressing themselves to the legislative process, which thus far has given more weight to other considerations. One such consideration might be found in the words of the court of appeal, which aptly suggested that there is “little merit in a rule of law which permits a surety to evade the conditions of its own bond, which it has written, and for which it has charged a premium . . . .” 383 So.2d at 1294.
Construction Materials, Inc., 388 So.2d at 367. Through its enactment of the 1985 amendments, discussed supra, the Legislature codified this Court‘s earlier position on the bond‘s statutory nature. Then in State v. McInnis Brothers Const., 97-0742 (La. 12/12/97), 701 So.2d 937, this Court once again adopted the interpretation of the bond as statutory:
As explained in Wilkin, supra,
La. R.S. 38:2241 et seq. require of the general contractor a statutory bond (the labor and materials payment bond) and give to the qualifying claimant a “privilege against the unexpended fund in the possession of the authorities.” Wilkin, 561 So.2d at 70.... Because it is required by the statute and the parties are not free to enter into the contract without it, the bond is in the nature of a statutory bond which exists for the benefit of the public authority and in essence creates a “privilege” or a source of funds available to the State should it be successful in a suit against the general contractor and the surety .... “The Act is to be strictly construed and the liability of the surety should not be expanded beyond the statute.” Metro Builders Hardware, Inc. v. Burko Construction, Inc., et al., 93-1970 (La.App. 4th Cir. 2/25/94), 633 So.2d 838, writ denied, 94-0727 (La.5/6/94), 637 So.2d 1049. “[T]he obligations of a statutory bond are limited to the exact provisions of the statute.” Martinolich v. Albert, 143 So.2d 745, 747 (La.App. 1st Cir.1962).
McInnis Brothers Const., 97-742 at pp. 9-10, 701 So.2d at 944.
Our role as civilian jurists is to interpret the laws in search of the
Legislature‘s intent. In this matter, the Legislature has made clear its intent to limit
the liability of the surety on the bond to only those claims provided for in the
PWA. Under the facts herein, the only right of action on the bond the PWA
recognizes and provides for is that of a claimant “who has complied with the notice
and recordation requirements of
Much is also made by the majority herein of “K” Construction, Inc. v. Burko Construction, Inc., 629 So.2d 1370 (La. App. 4th Cir. 1993), authored by former Chief Justice Dixon, then sitting pro tempore, in which the court held:
styled as a prescription article,
R.S. 38:2247 does not actually create a cause of action on the bond....
While it is arguable that the reason for the notice provision of
R.S. 38:2242 is to ensure that the governing authority and its surety are not subject to claims long after a project is completed, it is not reasonable to penalize a sub-contractor who has given timely notice sufficient to apprise the governing authority of its claim, merely omitting to provide the governing authority with a sworn statement....
Simply put, the Public Works Act does not appear to envision a situation where suit is filed before the notice of default is recorded. Consequently, our task is to determine if what the claimants did in this case was sufficient to notify HANO and, in Laurent‘s case, Burko of the claims.
“K” Construction, Inc., 629 So.2d at 1372-74 (emphasis added). This
interpretation is flawed, however, in its complete failure to recognize as well as
preserve the notice to other claimants, which the recordation requirement of
Guided by the Legislature‘s intent expressed in its 1962 and 1985
amendments to the PWA, I find a claimant, in order to maintain its direct action
against the surety on the bond under
Finally because its holding is contrary to this interpretation, I would overrule “K” Construction. And I would strongly discourage reliance on any statement in the LOUISIANA PRACTICE SERIES, which likewise does not conform to the Legislature‘s clear intent recited above.
PIERCE FOUNDATIONS, INC. VERSUS JAROY CONSTRUCTION, INC.
NO. 2015-C-0785
SUPREME COURT OF LOUISIANA
05/03/16
GUIDRY, Justice, dissents and assigns reasons.
I disagree with the majority‘s holding that failure to comply with the notice
and recordation requirements of
I agree with the majority that the Act is intended to protect those
contributing to the construction, alteration, or repair of public works, rather than to
foreclose preexisting contractual rights between parties. In enacting the subject
version of
However, I do not believe that is the only purpose. The notice to the governing
authority, together with recordation in the public records as required in
To that end, I believe
such a situation, as he may still proceed against the contractor, in any case, but he
may also proceed against the surety without waiting until after the recordation of
acceptance of the work by the governing authority. The only condition for
proceeding against the surety on the statutory bond is compliance with the notice
and recordation requirements of
PIERCE FOUNDATIONS, INC. VERSUS JAROY CONSTRUCTION, INC.
NO. 2015-C-0785
SUPREME COURT OF LOUISIANA
05/03/16
HUGHES, J., dissents for the reasons assigned by Guidry, J., and assigns additional reasons.
The courts are supposed to follow the law, not make it.
It is a long standing principle of statutory interpretation that “[a]s a general rule, lien statutes are stricti juris and should thus be strictly construed.” Guichard Drilling Co. v. Alpine Energy Services, Inc., 94-1275 p. 7 (La. 7/3/95), 657 So.2d 1307, 1313, rehearing denied (La. 1995). “[P]ublic contract laws are to be strictly construed such that the privileges granted are not extended beyond the statutes.” Wilkin, supra, 561 So.2d at 71. See also American Creosote Works, Inc. v. City of Natchitoches, 182 La. 641, 162 So. 206 (1935); and Rester v. Moody & Stewart, 172 La. 510, 134 So. 690 (1931). “The Public Works Act is sui generis and provides exclusive remedies to parties in public construction work.” U.S. Pollution Control, Inc. v. National American Ins. Co., 95-153 p. 4 (La. App. 3d Cir. 8/30/95) 663 So.2d 119, 122.1
In the present case the claimant intentionally chose not to comply with the Public Works Act and did not comply with the notice and recordation requirements of this Part. The statutory surety is therefore immune.
