60 Pa. Super. 293 | Pa. Super. Ct. | 1915
Opinion by
This appeal is from an order of the court below refusing to strike off the mechanic’s lien and the judgment entered for want of an affidavit of defense. It is urged:
First: That the claimant was not a “contractor” within the mechanic’s lien law of 1911. The defendant made a contract with one Powell for the plumbing and heating of a number of houses. Powell asked the plaintiff for a proposal for furnishing certain material necessary in this contract. The proposal while accepted by Powell was subject to the condition that the defendant, the owner, would personally pay for the material. The defendant agreed in writing to pay for all of said material in specified amounts. The contract, so far as it affected this plaintiff and defendant, was made up from the contract between Powell and Rogers, the defendant, the conditional proposal by the plaintiff to Powell and the defendant, and accepted by them. It was a tripartite agreement among them. Powell, the general contractor as to this work, was to do the buying. The plaintiff, pursuant to this buying, was to furnish the material, and the defendant, for whose property the material was bought, was to pay for it. This, after a careful study of the writings, was the reasonable interpretation of the contracts between the parties and places the claimant in the position of a contractor. It was an original undertaking on the part of the defendant to pay for the material delivered. It was not an agreement to pay in
Second: The objection that the claim is not self-sustaining because it does not appear that the plaintiff had completed its contract with the defendant cannot be sustained. The contract included many houses in addition to those against which this lien is filed. It appears frpm the lien that the defendant was insolvent and later bankruptcy proceedings had been instituted against him, A large part of the material shipped by the claimant had been returned because of defendant’s insolvency. The claimant, thus had a good excuse for not completing the balance of the contract.
Section 20 of the Act of June 4, 1901, provides that where proceedings in bankruptcy or insolvency are instituted by or against any contractor or owner, the contract shall be suspended but the right to file a lien shall remain and may be exercised with the same effect as if further, proceedings under such contract had been determined by consent of the parties. The lien does not set up a credit for a note alleged to be given in payment of the claim. If it was accepted in payment of the account, this could only be used as a matter of defense.
Third: The Supreme Court, in Murphy v. Bear, 240 Pa. 448, approved the method adopted in that case in ascertaining the value of the materials furnished, where the contractor had been prevented .by the owner for
Admitting the contract originally was entire, the insolvency of the owner prevented the claimant from completing his contract and permits the lien to be filed and a recovery for the materials furnished. “There can be no question that, in nearly all of such cases the contract is entire, yet nearly all provide for advances or payments at stipulated stages of the work, the avowed object being to enable the contractor to complete the whole. While plaintiff’s failure in ability or intention to complete the work will be a good defense, even to an action for a payment stipulated to become due on a state of progress shown to be reached, yet a refusal to pay such an installment without. that or. other legal excuse is such a breach of the contract as will justify a rescission, and entitle the plaintiff to recover pro tanto for the work done”: Easton v. Jones, 193 Pa. 147.
Fourth: It is urged that the claim .is not a proper one for apportionment. The contract, as applied to this block, was for nineteen houses and .the lien was filed against fifteen houses. The Act of March 30, 1831, P. L. 243, permits, where two or more houses are to be erected, one lien to be filed covering all the houses,
Fifth: We said, in the appeal of Crane & Co. v. Rogers, et al., No. 1, in an opinion handed down this day, that somewhere in the lien or bill of particulars there should appear the dates on which the materials were furnished. An examination of this lien shows that
The assignments of error are overruled and the judgment is affirmed at the cost of the appellant.