66 W. Va. 10 | W. Va. | 1909
Lead Opinion
Boman Pickens brought an action against the Coal Eiver Boom & Timber Company and the Coal Eiver Boom & Driving Company, both corporations, to recover damage for injury to his mill on Coal river, claiming that the works of the Boom Company on the stream below his mill stopped the outflow of sand and .other sediment and caused them to rest in large quantities in the stream, and lessened the fall of the water over his dam, and thus lessened the grinding capacity of his mill. He recovered verdict and judgment for seven thousand dollars, and the Driving Company appeals.
This is a second action for damage from the same cause. The character of the case is just the same as that of the former action, which twice came to> this Court. Eeports of decisions in that action will be found in Pickens v. Boom & Timber Co., 51 W. Va. 445, and 58 Id. 11, rendering it needless to repeat the facts, as they are the same involved in the present case.
Does this boom, if damaging the mill by operation upon the water power, give Pickens action? The boom right rests upon a state charter. Does that charter give immunity from action by Pickens? We think that former decisions of this Court upon the same and similar facts answer this question in the affirmative The two decisions just cited do so. In Rogers v. Coal River Boom Co., 39 W. Va. 272, it was held that where
The statute of limitation of live years is pleaded in this case. This suit was brought to recover damages from 21st December, 1899, to 21st December, 1904, five years immediately preceding the institution of the suit. The contention on the side of that plea is, that as the boom had been constructed long prior to 21st December, 1899, the statute began to run from the date of the construction of the boom and thus recovery is barred. Upon principles stated in Rogers v. Boom Co., 39 W. Va. 272, and Pickens v. Boom Co., 51 Id. 445, this plea is inadmissible. Its theory is that the boom is a structure of permanence and that any damage from it is permanent and the right of suit is for past and prospective damage, and but one suit can be maintained, and that th&re must be recovery once for all. Our holding in Pickens v. Boom Co. and Rogers v. Boom Co. that the damages are continuous and recurrent, and repeated suits may be maintained as damage goes on, is assailed and we are asked to overrule those former cases in this respect, because unsound. But we think that holding is supported by much authority in this and other states. Hargrave v. Kimberly, 26 W. Va. 787; Watts v. R. R. Co. 39 Id. 196; Henry v. Railroad, 40 Id. 234; Eels v. Railroad, 49 Id. 65; Rogers v. Boom Co., 39 Id. 272. We cite authority from other states. Prentiss v. Wood, 132 Mass. 486; Baldwin v. Caukins, 10 Wendell 165; Chicago &c. Co. v. Andreesen, 62 Neb. 456; Omaha &c. Co. v. Standen, 22 Id. 343; Miller v. Keokuck R. Co., 63 Iowa 680; St. L. R. Co. v. Biggs, (Ark.) 20 Am. St. R. 174; Hempsted v. Cargill, 46 Minn. 118; N. Y. &c R. Co. v. Hamlet Hay Co., 149 Ind. 344; Chicago &c. Co. v. Emmert, 73 N. W. 540. In Ridley v. Railroad, 118 N. C. p. 998, the rule is stated thus: “The right to recover prospective as well as existing damages in an action depends usually upon the answer to the test question, whether the whole injury results from the original tortious act or from the wrongful continuance of the state of facts produced by these acts," citing Troy v. Chesshire
For use I cite cases illustrating permanent damages. Virginia Hot Springs v. McCray, 6 S. E. 217; Gwin v. Railroad, 46 W. Va. 151; Smith v. Railroad, 23 Id. 451; Battrell v. Railroad, 34 Id. 237.
Former decisions above given rule this case and require us to affirm the judgment.
Affirmed.
Dissenting Opinion
(dissenting):
I cannot concur in the conclusion reached by my associates. The decision involves a principle of vital importance to every public service corporation in the state; and, I think, misapplies it. The opinion, in effect, holds that a boom company, without negligence in the construction, maintenance or operation of its boom, is nevertheless liable to repeated actions for damage on account of an unavoidable injury to a mill owner, which is the natural result of the lawful operation of its boom, notwithstanding the injury is continuous and permanent. It affects railroads, pipe lines and all improvement companies exercising the right of eminent domain, and may rise up some day, like the ghost of Banquo, to plague us. If this decision is right, boom companies will have a precarious .and fretful existence in this state. Because if they are liable in repeated actions for unavoidable injury resulting from a continuation of the same cause, as if for maintaining a private nuisance, they are liable to be compelled by suit to abate the nuisance, which may mean a removal of their booms.
It is not shown in this case that the Boom Company was negligent in any particular, either in the construction, or operation of its boom. It, therefore, can not be held liable, on the ground of negligence. Then, if it is not negligent, how can it be said to be maintaining a private nuisance, when the injury to Pickens’ mill is unavoidable and the Boom Company is occupying the river by virtue of the right of eminent domain conferred by its charter? I confess my inability to see it in this light. It is true the books speak of a thing which causes injury to the property of another as a nuisance. But I am now discussing an abatable nuisance, one that gives the injured party a perpetual i*ight of action for a' continuation of one and the same cause.
I do not deny that Pickens at one time had a right of action for injury to his mill, or even to his natural water-fall if he had not had a mill. There is abundant authority for this. He owned the fee in the bed of • the river and was entitled to the- flow of the water as nature had provided. This was a property right guaranteed to him by the Constitution, which the legislature could, at no time, have taken from him without just compensation, and which, since the Constitution of 1872, it could not so much as injure without compensation. Still his property was liable to be taken absolutely, or to be injured by the Boom Company by its right of eminent domain conferred upon it by the law and its charter. In either event, however, Pickens was entitled to compensation; in the one case, by means of condemnation proceedings; in the other case by an action for damages. His right to sue for injury is. expressly saved to him by section 28 of the Boom Act; but he had the right under the Constitution, independent of this reservation. It has been expressly decided by this Court in cases involving injury to a land owner by the changing of the grade line of a street. In these cases there was no statute conferring, or even reserving, a right to sue for injury, and the Court held that the party injured could sue by virtue of the constitutional right. Johnson v. Parkersburg, 16 W. Va. 402; Hutchinson v. Parkersburg, 25 Id. 226; Blair v. Charleston, 43 Id. 62; Crenshaw v. The Slate River Co., 6 Rand. 245.
It is again stated in these eases to be law, viz: Taylor v. Railroad Co., (Point 2 of the Syllabus) 33 W. Va. 39; Watts v. Railroad Co., 39 W. Va. 197, and Henry v. Railroad Co., 40 W. Va. 234. This last was a case of injury from overflow of land resulting from- negligent construction of an embankment, (mark the word negligent), and the Court, in its opinion, prepared by BRANNON, Judge, on page 242 says: “Where the nuisance is permanent, so that it will continue unless labor be applied to change it, and it necessarily injures the plaintiff, there must be a recovery in one suit for all damage, and none other can be afterwards brought, and recovery of damages will give the defendant right to continue his nuisance without further claim from the individual; but, where it is otherwise, there can not be recovery for future damages, but only from time to time as they occur, and one recovery does not justify the perpetuation of the nuisance, but there may be recovery after recovery, as long as continued.”
No authority, other than the Pickens Case, 51 W. Va. and 58 W. Va., so far as I can find, holds that the injured party has a perpetual right of action for the same continuing cause of injury, unless the act causing it is done without lawful right, or unless the injury is the result of negligence. Negligence will make the act wrongful and constitute it a perpetual nuisance for which repeated actions will lie, as well as the right to have it abated. But if the act is lawful and the injury results from work skillfully done, the injured party has but one right of action, and he must bring his suit within five years from the time of injury, or be forever barred. If Pickens had sired within five years from the commencement of his injury, he could have recovered entire damages; but having failed to sue in time the statute cuts off his remedy, and the Boom Company is entitled to maintain the cause of injury unmolested.
A correct answer to the two following questions 'will determine whether the foregoing principle should be applied in this case, viz: (1) WThat is the cause of plaintiff’s injury? and
■ The boom was “substantially” built, with piers constructed of logs forming a rectangular pen, bolted together and filled with stone to give them weight and prevent their washing away. These rested on the bottom of the river, and furnished the moorings for the boom logs. This, from- its very nature, is a
From the uncontroverted facts in the case I deduce the following conclusions, viz: (1) that the injury is the natural and unavoidable result of the doing of a lawful thing in a slcillful manner; (2) that, from both the testimony of Mr. Pickens and from the very nature of the injury, it is coexistent with the thing that caused it; (3) that the injury is necessary to the enjoyment of the Boom Company’s franchise, and is therefore an injury lawfully inflicted and gives a right, or license, to the Boom Company to maintain the cause of injury. Now, apply the well settled law, and what is the result? It is that Pickens can sue but( once, and has a right to recover entire damages, past and prospective, but he must sue within five years from the commencement of his injury, to-wit, not later than 1898, or be barred of his right.
Whether, or not, Pickens in some former suit may have been denied a recovery for entire damages, by a mistake of the court in failing to apply the correct principle, is not a justifiable argument to support a repetition of the error. The court is not in conscience bound by its own mistakes as if its decisions were in the nature of contracts to which it is a party. The ablest jurists are not infallible, and past experience and observation teach us that all courts sometimes make mistakes. But as soon as a mistake is discovered by a court it should not hesitate to correct it upon first opportunity, and in a manner to work as little hardship as possible. A court’s decision is not law; it is only evidence of the law. And if a decision is erroneous it is
The doctrine of stare decisis should not be invoked to sustain erroneous decisions, especially where rights of’ property will not be affected by overruling them. It is not a sacred and unassailable doctrine. It is only an argument, and it is the least forceful of all arguments. It has been disregarded by this Court, as well as by all others, in numerous instances; by this Court in Town of Weston v. Ralston, 48 W. Va. 158; State v. McEldowney, 55 W. Va. 1; Pennington v. Gillaspie, 63 W. Va. 541; Catzen v. Belcher; 64 W. Va., 314 (61 S. E. 930); and in many other cases to which I need not refer.
As a question of abstract justice, which would result in the greater injury, to deny Pickens recovery in this action because he was not allowed to recover entire damages in a former suit; or to permit a recovery in this action, and thereby approve the case of Pickens v. Boom Company, 51 W. Va. 445, and confer on Pickens the right either to sue the Boom Company every month in the year for damages, or compel it to remove its boom in order to abate the so-called nuisance? The question answers itself, and serves to show the utter futility of trying to administer justice without a strict adherence to correct legal principles. The law is the embodiment of man’s accumulated wisdom during the ages, which has been preserved and transmitted to us through the centuries of the past. It is founded upon the experience of mankind throughout the historical past; yea, it is even supposed to have its beginning in a time wherein man made no record of passing events, a time whereto his memory runneth not; and the rules and principles, thus established
I do not think the authorities cited in the majority opinion sustain the conclusion. Watts v. Railroad Co., 39 W. Va. 196, certainly does not. That was injury from negligence. Point 7 of the syllabus states in terms, better than I can employ, the very rule for which I contend. State v. Elk Island Boom Co., 41 W. Va. 796, was an indictment for obstructing the passage of fish, and the injury there complained of could have been avoided.
I think the law quoted from Wood on Nuisance is good. But it does not apply to the present case, because the legislature has authorized the act complained of to be done by the Boom Company, and, unless the act is done negligently, it can no more be a private than a public nuisance.
The New Jersey case, Trenton Water Power Co. v. Raff, 36 N. J. L. 335, on which so much reliance is placed does not decide the point for which I contend. It is true that was a second suit for the same cause of injury, the maintenance of a dam causing overflow of plaintiff’s land. But it does not appear that defendant pleaded a former recovery, o-r the statute of limitations, in bar of plaintiff’s action, and this question is not discussed in the opinion. The question there decided is, that, although an act be done under authority of legislative enactment, if injury result there is liability. This I do not deny. But, if the act be skillfully done, must the defendant be liable, as was held in Pickens v. Boom Company, 51 W. Va., perpetually, and for punitive damages, as if it were maintaining an abatable private nuisance? I cannot think so. There were only two ways in which to abate the injury, (1) remove the boom and piers, or (2) remove the sand as it accumulated, and toi require the latter would be to make the Boom Company a trespasser.
Taylor v. Railroad Co., 33 W. Va. 39, allowed a recovery for injury occasioned by the building of a bridge across a stream in such a way as to obstruct the natural flow of water in case of a freshet. That was for negligence. See point 2 of syllabus, and also opinion by Brannon, Judge, on page 47.
Eels v. Railway Co., 49 W. Va. 65, is in perfect harmony
Of course, no action will lié in any case until injury happens. But in the present case the sand in Coal Biver never ceased to interfere with Pickens’ water power. The sand, first deposited, remained, and more sand accumulated. There was not a moment of time after the injury first began when it could be said that Pickens was not sustaining injury from the same continuing cause.
Prentiss v. Wood, 132 Mass. 486, was a case between private persons. In this case B’s dam injured A’s mill. The court held it was done “without right” and that it was a private nuisance. But the defendant’s boom is in Coal Biver by right. It had a right to injure, but was liable to malee compensation. This takes from it the character of a nuisance, and it is liable to respond only once, and within five years from the beginning of the. injury.
Chicago &c. R. R. Co. Andreesen, 63 Neb. 456, was a case of injury on account of an “insufficient culvert,” which of course involved negligence.
Omaha &c. R. R. Co. v. Standers, 33 Neb., was a case of negligent construction of a bridge causing injury to land by overflow. The court held, that damages were recoverable only for past injxiry, and that one recovery did not bar another. But the opinion is based expressly on the ground of negligent construction, thereby constituting a perpetual nuisance.
Miller v. R. R. Co., 63 Iowa 680, was also a case of negligence. The ditch causing the injury was “wrongfully dug,” says the court. This, of course, constituted it an abatable nuisance.
St. L. &c. R. R. Co. v. Biggs (Ark.), 30 Am. St. Rep. 174, is directly in favor of my contention. Point 1 of syllabus reads as follows: “When a nuisance is of a permanent character, and its construction and continuance are necessarily an injury, the damage is original, and may be at once-compensated. In such case, the statute of limitations begins to run upon the construction of the nuisance.”
This is the principle which should be applied in the present case. Pickens knew that as long as the water continued to flow in Coal river, and as long as defendant’s boom remained in the stream, his injury would “necessarily continue.” He could not help knowing this from the beginning. He also knew
I have examined the other cases cited in the majority opinion, and, in my view, they do not sustain the conclusion. Where they hold that the statute of limitations does not apply, it is so held either on the ground of negligent construction, or on the ground that the injury did not occur at the time the act complained of was done; some of them so hold on both grounds combined.
The case of Virginia Hot Springs Co. v. McCray, 56 S. E. 216, I think is direct authority in support of my view. The first point of the syllabus reads: “An injury resulting from a permanent nuisance must be sued for in one action, and limitations begin to run from the time of the erection o’f the nuisance.” This is what I insist on as the law applicable to the present case. So also does the second point of syllabus in case of Guinn v. R. R. Co., 46 W. Va. 151, state the principle of law, giving the proper test in determining whether, or not, the statute of limitations has application in the present case.
The rule by which it must be determined whether, or not, permanent damages should be recovered in a given case is again stated in the opinion of the Court in Battrell v. Railroad Co., 34 W. Va. 237.
In Street Ry. Co. v. Payne, 192 Ill. 239 (Syl. pt. 4) it is held: “The construction and operation of a power house by a street railway company upon its own property, if done in a reasonably skillful manner, do not constitute a nuisance which maj'' be abated; but the company is liable to the owner of adjoining property in an action on the case for damages resulting from the establishment and operation of the power house, without any charge of negligence.”
In the case of Call v. Middlesex Co., 68 Mass. 232, which was a case very similar to the case under review, the court held that the statute of limitations applied, “even though such damages did not occur, and could not be foreseen, before the expiration of said three years;” three years being the statutory period allowed for the bringing of the action.
“In an action for injury to real estate by erecting and main-
“Whenever a nuisance is of such a character that its continuance is necessarily an injury, and when it is of a permanent character that will continue without change from any cause but human labor, then the damage is an original damage and may be at once duly compensated. Successive actions are not allowed for damages resulting from negligence combining with a natural cause, however gradual the operation of the cause, and they will only lie where the defendant is continually in fault.” Powers v. The City of Council Bluffs, 45 Iowa 652. See also Eastman v. St. Anthony’s Falls Water Power Co., 12 Minn. 137; Baldwin v. Calkins, 10 Wend. (N Y.) 167; Guinn v. R. R. Co., 46 W. Va. 151; Henry v. R. R. Co., 40 W. Va. 242.
Farnham in his work on Waters and Water Eights, Vol. 2, sec. 586, in discussing the application of the statute of limitations to actions for various kinds of nuisances, says: “The rule that- every continuance of a nuisance is a fresh nuisance should have no application in case of permanent nuisances of this class any more than it should be contended that a trespass upon the land and erection of the structure there should constitute a fresh trespass every moment it was continued for the purpose of extending the time within which the action could be brought. And there are cases which have applied the true rule that, in case the dam is a permanent one, the limitation period will begin to run against the right of action to recover damages for the injury, from the time the dam is built.” And he cites the case of Missouri &c R. R. Co. v. Graham, 12 Tex. Civ. App. 54 (33 S. W. 576).
The theory of the plaintiff, however, is that the injury is intermittent and recurring, and that every injury resulting from natural causes, coupled with the existence of the boom, even though the boom remains unchanged, constitutes a fresh nuisance, and entitles him to a new action. This theory is wholly untenable, and is in conflict with all the authorities. There seems, however, to be much confusion in the decisions, growing out of a failure by some of the courts of the states to distinguish between those cases arising out of the conflicting rights of pri
It would certainly entail a very great hardship on the Boom Company to hold it liable to respond in damages, in successive, and unlimited number of, actions. If such were the law it would have tire effect to deprive it entirely of the enjoyment of its franchise; because, if plaintiff has a right to' sue it more than once, he has a right to sue it as often as he pleases. If he chose to do so, he could bring an action every month and thus bankrupt the defendant in paying costs. This appears to me to be not only unreasonable and unjust,^but a very cruel doctrine;.because, from the very nature of the injury, it is seen that the defendant is unable to abate the injury without pulling up its boom and piers from the river, or trespassing on .'plaintiff’s
This was an action against the railroad company for injury done to plaintiff's property by the running of its engines and cars. The defendant pleaded the general issue and the statute of limitations. The railroad had been built and operated for a longer time than the statutory period within which an action for trespass to real estate could be brought, and the plaintiff was held tó be barred. The court in its opinion says, page 215: “The allowance of successive actions for damage, as it should occur from day to day, as new-damage, would seem to serve but the purpose of harassing, and the wasting of means in expenses of litigation. The law does not favor the multiplying of actions.” Citing in support of this principle, a number of its own decisions, and Kutz v. McCune, 22 Wis. 628; Mills on Em. Dom., sec. 66; Memmert v. McKeen, 112 Pa. St. 315.
The principle was again announced in the later case of The Hyde Park &c. Light Co. v. Porter, 167 Ill. 276, which was an action by a property owner against an electric light company. One point of the syllabus reads: “A property owner has but one action for damages for permanent injury to his property from the operation of an electric light plant near to it, but in such action all damages, present and future, are recoverable.” The court in its opinion cited the case of Chicago &c. R. R. Co. v. McAuley, 121 Ill. 160, wherein it was held that when the injury is “of a permanent character, so that the damages inflicted are permanent, a recovery not only may, but must, be had for entire damages in one action; and such damages accrue from the time the nuisance is created, and from that time the statute of limitations begins to run.” See also, The Chicago &c. R. R. Co. v. Maher, 91 Ill. 312. The City of Centralia v. Wright, 156 Ill. 651, contains the following point in the syllabus, viz: “The erection of a dam by a city for water-works, whereby a riparian owner suffered damage through overflow and the de-stuetion of a private ford, is a permanent injury, for which all damages, past, present and prospective, are recoverable in one
“All special damages, present and prospective to the owner of lands resulting or to result from the proper construction, maintenance and operating of a railroad, under the laws of this State, constitute, as to such land owner, one single, common, indivisible cause of action, which may be enforced under the Eminent Domain act, or any other appropriate form of action.” Ohio &c. R. R. Co. v. Watcher, 123 Ill. 440.
The case of Bizer v. The Ottumwa Hydraulic Power Co., 70 Iowa 145, was an action brought by a land owner for damages for the overflowing of his land by the damming of the Des Moines river. The defendant was the grantee and' successor of the company that had originally built the dam, and was simply maintaining it in its original condition. The court held that the injury was permanent and original; that it was not a nuisance which could or should be abated; that the plaintiff was entitled to but one action for past and future damages, which action accrued to him at the beginning of the injury, and held that the defendant was not liable. On page 147, the court says: “Where the injury is permanent, but one action can be maintained, and the recovery allowed is for all damages, past and prospective. The right of action in such case accrues wholly against the party doing the injury.” See, also, Powers v. The City of Council Bluffs, 45 Iowa 652; Finley v. Hershey, 41 Iowa 389; The Town of Troy v. The Cheshire R. R. Co., 23 N. H. 83; E. L. & B. S. R. R. Co. v. Combs, 10 Bush. (Ky.) 382; Ridley v. Seaboard &c. R. R. Co., 118 N. C. 996; Aldworth v. City of Lynn, 153 Mass. 53; Fowle v. New Haven & Northampton Co., 112 Mass. 334.
The City of North Vernon v. Voegler, 103 Ind. 314, was a suit for injury to property resulting from negligently grading a street, and the court thus states the law: “In an action for injury to real estate caused by the negligence of corporate officers in constructing a public work of a permanent character, as the grading of a street, all damages, past and prospective, can be recovered in one action.” “In such a case, all the damages must be recovered in one suit, and for, fresh damages resulting from the original wrong, a second action can not be maintained.”
Mr. Sutherland in his work on Damages, Yol. IY, sec. 10-1-5, referring to the decision by one of the appellate courts of Illinois gives the following as the proper test in determining whether or not an injury amounts to a permanent one and therefore giving but one right of action, or whether it is a continuing nuisance for which the wrongdoer may be subjected to repeated actions, viz: “Where a permanent structure is lawfully erected and thereby an injury is occasioned to adjoining property, if the structure is properly built with reference to its use and so as to produce no unnecessary damage, the cause of action arising from an injury caused by it is an entirety; but if the injury complained of results from an improper construction it is otherwise.”
Applying the foregoing principles to the present case there is no doubt in my mind that the injury, in a legal sense, is a permanent one, and is not a continuing and, therefore, abatable nuisance. If this is so, it then necessarily follows that the cause of action accrued to plaintiff at the time the injury began, and that the statute of limitations would begin to run from that time. To my mind this conclusion is irresistible.
If it is to become the law of this State, that a boom skill fully constructed in a permanent manner, and lawfully operated, is a continuing nuisance, because the property of a riparian owner is injured by it; and boom companies are to be subjected to repeated actions, unlimited in number, involving penal dam
I think the statute of limitations bars plaintiff’s action, and am in favor of reversing the judgment and dismissing the ae-. tion.
Rehearing
PETITION EOR REHEARING.
A petition for rehearing says that the Court did not consider a point of chief reliance of the defendant. This Court in this case has decided that Pickens was not barred from successive actions by one suit and recovery therein, but that he might maintain successive actions for different periods of time. The petition for rehearing does not claim to the contrary, does not claim that the damage was original and permanent in nature, but admits that there may be successive actions for continuing damage. But the point which it is said the court has not considered is thus stated in the petition for rehearing: “We do not claim that the statute runs from the construction of the boom. We freely admit that the statute does not begin to run until injury occurs. But we do insist that the statute begins to run when injury once occurs, and that the statute applies as well when there is a right to successive actions, as when all damages present and prospective must be recovered in one suit. We say that for all damages occasioned by the deposit of sand in any year a suit must be brought within five years thereafter; and that when this suit was brought on December 21, 1904, damages could only be recovered for injuries caused by sand deposited within five years prior thereto, and not for injuries caused by sand deposited at any time since the construction of the boom, as ruled by the trial court. As directly sustaining our contention we gave the Court the high authority of the Supreme Court of Pennsylvania in Lentz v. Carnegie, 145 Pa. St. 627, a decision which has never been answered or attempted to be answered by counsel for Pickens.”
It is said that instructions allowed the jury to consider dam
Remember that this is a suit for damage in lessening the power of the mill of Pickens. It is for the effect of the sand upon the mill, not like permanent injury to land from deposit upon it. Pickens had right to operate his mill in its original condition not only during the five years involved in the first suit, but also during the five years involved in the second suit. He had right to run that mill every minute, every hour, every dajr, week, month and year, free of damage from deposit of that sand, and it is utterly immaterial when that sand was deposited, so it continued to operate in diminishing the working capacity of the mill
It is but repetition of old principle and of what has been several times said in the litigation over this matter, to say that it is only the case of a private non-abatable nuisance because working injury to private property, every day’s -continuance of the old cause being a fresh injury giving cause for successive actions. 3 Blackstone 220; 23 Cyc. 1187. That the boom was built under law does not give immunity from damage, because the Legislature could not exempt from damage under the Constitution, and also because the boom act says that a boom company shall be liable.
As the Driving Company operated the boom and worked damage, it would be liable, not only for deposit in its own time, but also that deposited by the lessor, on principles stated in Pickens v. Boom Co., 58 W. Va. 11.
Rehearing Refused.