PI-CON, INC v A J ANDERSON CONSTRUCTION COMPANY
Docket No. 83682
Supreme Court of Michigan
Decided July 30, 1990
Argued October 4, 1989 (Calendar No. 3).
435 MICH 375
In an opinion by Justice ARCHER, joined by Justices LEVIN, CAVANAGH, and GRIFFIN, the Supreme Court held:
A claimant on a public works bond may maintain an action on the bond upon establishing that the principal contractor actually received timely written notice of materials furnished, the labor performed, the party contracting for the labor or materials, and the site for performance or delivery. A failure to send notice by certified mail as prescribed by
1. Notice under
2. In this case, summary disposition for either party under MCR 2.116(C)(10) is inappropriate because of the existence of a dispute regarding whether notice actually was received, a material fact. The plaintiff is entitled to a trial to resolve the dispute.
Justice LEVIN, writing separately, stated that on remand the scope of inquiry should be broadened to include consideration of whether the general contractor paid the subcontractor for labor and material supplied by the plaintiff before the plaintiff served the general contractor with notice that it intended to rely on its rights under the public works bond act.
Pi-Con claims that the thirty-day notice was actually received. Pi-Con may prevail on that basis on remand. If, however, it is decided on remand that the notice was not actually received, that should not be determinative if notice of the claim reached Anderson before it paid Brian & Gregory for labor and materials supplied by Pi-Con.
Reversed and remanded.
Chief Justice RILEY, joined by Justices BRICKLEY and BOYLE, dissenting, stated that pursuant to
Fleisher Engineering & Construction Co v United States, 311 US 15 (1940), interpreting the Miller Act,
Timely written notice is a condition precedent under
169 Mich App 389; 425 NW2d 563 (1988) reversed.
BONDS — PUBLIC WORKS — SUBCONTRACTORS — NOTICE.
A claimant on a public works bond may maintain an action on the bond upon establishing that the principal contractor actually received timely written notice of materials furnished, the labor performed, the party contracting for the labor or materials, and the site for performance or delivery; a failure to send notice by certified mail as prescribed by the public works bond act will not preclude recovery, and the claimant may prove the principal contractor‘s actual receipt of timely notice by a preponderance of the evidence (
Goldstein, Serlin, Reizen, Rosenbaum & Baker, P.C. (by Barry M. Rosenbaum and Richard E. Baker), for the plaintiff.
Mager, Monahan, Donaldson & Alber (by Lita Masini Popke) for the defendants.
We hold that, so long as Pi-Con timely sent notice which otherwise complies with the notice requirements of the public works bond act,
I
Pi-Con entered into a contract with Brian & Gregory Contracting Company, a subcontractor of Anderson, to furnish materials and services for a construction project at Cass Technical High School in Detroit for which Anderson was the general contractor. The contract between Pi-Con and Brian & Gregory is dated November 4, 1982. Pi-Con asserts that it began furnishing materials and services pursuant to the contract on November 22, 1982.
The statute provides that a claimant not having a direct contractual relationship with a general contractor shall not have a right of action upon a public works payment bond unless two written notices are served, the first within thirty days after the first furnishing of materials or labor, and
The statute further provides that the notices “shall be served by mailing the same by certified mail.”2
Pi-Con claimed in its affidavit in support of its motion for summary disposition that it mailed notice to Anderson and the Detroit Board of Education, with a copy to Brian & Gregory, on Decem-
Pi-Con, on September 6, 1984, within ninety days of the last furnishing of materials or labor, notified Anderson and the school board by certified mail that Brian & Gregory owed Pi-Con $25,140.
Brian & Gregory had by then filed for bankruptcy. This action was commenced to recover on the payment bond. The circuit court granted Pi-Con‘s motion for summary judgment on the basis that Anderson had actual notice of Pi-Con‘s work on the Cass Technical project.3
The Court of Appeals reversed, holding, in reliance on decisions of that Court,4 “that mailing notice by regular mail, despite evidence of actual notice, does not satisfy the statute and that strict compliance with the statute‘s notice requirements is required.”5 We reverse.
II
We are guided by the decision of the United States Supreme Court in Fleisher Engineering & Construction Co v United States ex rel Hallenbeck,
Fleisher construed the Miller Act,
The Supreme Court held that substantial compliance with the notice requirements was sufficient to perfect an action on the bond:
We think that the purpose of this provision [notice by certified mail requirement] as to manner of service was to assure receipt of the notice, not to make the described method mandatory so as to deny right of suit when the required written notice within the specified time had actually been
given and received. In the face of such receipt, the reason for a particular mode of service fails. It is not reasonable to suppose that Congress intended to insist upon an idle form. Rather, we think that Congress intended to provide a method which would afford sufficient proof of service when receipt of the required written notice was not shown. [Fleisher, supra at 19. Emphasis added.]
We agree. Applying Fleisher‘s reasoning to Michigan‘s public works bond statute as illuminated by prior case law, we hold that a claimant on a bond may maintain an action on the bond upon establishing compliance with four substantive elements of the notice provisions of
This Court established the fourth element in People ex rel Wheeling Corrugating Co v WL Thon Co, 307 Mich 273; 11 NW2d 886 (1943). In that case we denied recovery to a claimant who was sixty days tardy in giving notice of the completion of its work, holding that the time limits contained within the public works bond act were mandatory. Cf. People ex rel Chasteen v Michigan Surety Co, 360 Mich 546; 104 NW2d 213 (1960).
As to the third element, this Court established
The second element, regarding the detail required in the notice, was clarified in Wheeling, where this Court stated that conversations between the general contractor and the surety regarding the several parties furnishing materials on the project could not fulfill the notice requirement. The conversations did not comply with the notice requirement because they were “of a very general nature . . . with nothing specific being said as to the amount or character of any of these claims.” Wheeling at 277.
We look to Fleisher in establishing the first element, that the principal contractor must actually receive notice in order for a claimant to perfect its right on the bond. Fleisher determined that the purpose behind the Miller Act‘s provisions regarding the method of mailing notice “was to assure receipt of the notice . . . .” Id. at 19.
The purpose behind the thirty-day notice required by
III
We further hold that Pi-Con is allowed to prove Anderson‘s actual receipt of timely written notice by a preponderance of the evidence.
It is possible to limit the rule of Fleisher to its facts and hold that the certified mailing requirement is not strictly required only when the principal contractor does not dispute receiving the notice. We decline to read Fleisher that narrowly and note that federal courts interpreting the Miller Act‘s notice requirements after Fleisher have similarly rejected such a reading.
In United States ex rel Birmingham Slag Co v Perry, 115 F2d 724 (CA 5, 1940), the court held that the claim of a supplier of materials was not barred where the trial court found as fact that the principal contractor received notice of the supplier‘s claim in a letter the contractor received, through ordinary mail, from the government agency paying for the construction project. In National State Bank of Newark v Terminal Construction Corp, 217 F Supp 341, 355 (D NJ, 1963), the defendant principal contractor denied receiving notice as required by a bond, but the court held, citing Fleisher, “[a]lthough the bonds require
The dissent argues that, in order for the plaintiff to maintain an action on the bond, it must either comply with the certified mailing requirement or present some other proof that would foreclose the existence of a genuine factual dispute regarding receipt of the notice. The dissent claims such an interpretation is necessary to prevent rendering the certified mailing requirement “nugatory.” Post, p 406.
However, the dissent‘s interpretation itself would render the certified mailing requirement nugatory, because it would impose a hypertechnical requirement elevating form over substance. The dissent‘s reasoning appears to be grounded in the belief that the certified mailing requirement is entirely procedural, designed to control the nature and quality of proofs in any action on the bond. Instead of finding any substantive purpose in the certified mail requirement, the dissent concludes that it is intended to require uncontrovertible proof of the general contractor‘s receipt.8
The dissent, in our view, is wrong in this regard.
We view the certified mail requirement as substantive. The Legislature, recognizing the vagaries of ordinary first-class mail, required certified mailing as a way to better ensure actual receipt of the notice. The Legislature intended to protect public works bonds from claims by materialmen and subcontractors of whose participation on the project the general contractor was not notified; it mandated a more certain form of postage to specify that first-class mailing was inadequate, not to control the form of proof of receipt in any subsequent actions on the bond. As the Court stated in Fleisher: “We think that the purpose of this provi-
Because we agree with the Supreme Court that the certified mail requirement is intended to ensure actual receipt and not to qualify the right to sue on a manner of delivery or proof of delivery, we hold that the plaintiff has a right to prove actual receipt of notice by a preponderance of the evidence. Such a rule furthers the substantive purpose of the notice requirement and prevents a danger which the dissent‘s rule would allow. Under the rule advocated by the dissent, general contractors could defeat legitimate claims on public works bonds where the claimants fail to send otherwise sufficient notice by certified mail by simply raising a factual dispute regarding receipt of the notice. Allowing contractors such a trump card would run contrary to the ultimate purpose of the public works bond act, the protection of subcontractors and suppliers of materials.
IV
Given the procedural posture of this case, we remand to allow the plaintiff a chance to prove by a preponderance of the evidence that Anderson received timely, written, and sufficient notice of Pi-Con‘s participation in the Cass Tech project.
The trial court granted the plaintiff‘s motion for summary disposition under MCR 2.116(C)(10), finding that there was no genuine issue with regard to any material fact and that plaintiff was entitled to judgment as a matter of law. The trial court never made a finding regarding whether the defendant ever actually received the notice which the plaintiff claims to have sent. In fact, counsel for the plaintiff conceded at the hearing on the summary disposition motion that “maybe there is an issue of
The Court of Appeals reversed the decision of the trial court, and took the extra step of ordering summary judgment for the defendant under MCR 2.116(C)(10). The Court concluded that the statute required strict compliance and that the plaintiff‘s claim was unperfected as a matter of law because of the failure to send the notice via certified mail.
Granting summary disposition for either party under MCR 2.116(C)(10) is inappropriate because of the existence of a dispute regarding the material fact whether notice was actually received. Pi-Con, therefore, is entitled to a trial to resolve this issue. We reverse the judgment of the Court of Appeals and remand the case to the trial court for proceedings consistent with this opinion.
LEVIN, CAVANAGH, and GRIFFIN, JJ., concurred with ARCHER, J.
LEVIN, J. (separate statement). The statute provides in effect that an unpaid subcontractor, laborer, or supplier of materials shall have a direct right of action against the general contractor and its surety for the amount owing for labor and materials supplied for the undertaking of the general contractor although the unpaid subcontractor, laborer, or supplier does not have a direct contractual relationship with the general contractor.1
I have signed the opinion of the Court because I agree that summary disposition was inappropriate in the circumstance that there was a dispute regarding the material fact whether the notice required to be given within thirty days was actually received.3
I write separately because I would broaden the scope of the inquiry on remand to include consideration of whether Anderson paid Brian & Gregory for labor and materials supplied by Pi-Con before Pi-Con served notice on Anderson that it intended to rely on its rights under the statute.
Pi-Con claims that the thirty-day notice was actually received. Pi-Con may prevail on that basis on remand. If, however, it is decided on remand that the notice was not actually received, that should not be determinative if notice of the claim reached Anderson before it paid Brian & Gregory for labor and materials supplied by Pi-Con.4
I
I agree with my colleagues that notice must be served before an unpaid claimant may maintain an action.5 Unless the requisite notices shall have been served within the thirty- or ninety-day periods, the general contractor (Anderson) is at liberty
Requiring Anderson to pay Pi-Con may very well mean that Anderson would be required to pay more in respect to its contract with Brian & Gregory than it contracted to pay. That might result, however, because Brian & Gregory was unable to obtain the supply of labor and materials within the amount it bid for the job either because it bid too low, misadventure on the job, unanticipated contingencies, or other circumstances.
The statute provides a right of direct recovery by the unpaid claimant against the general contractor and its surety without regard to whether there is sufficient money owing by the general contractor to the subcontractor to pay the unpaid claimant in full.7
The statute thus imposes, for the benefit of the unpaid claimant, on the general contractor the risks or loss resulting from the vicissitudes of the job and of general contractor/subcontractor contractual relationships. Loss so resulting cannot, consistent with the policy of the statute, be shifted to the unpaid claimant because of inconsequential delay in serving notice of claim.
It might be argued that the statute allocates such risks to the general contractor only for the benefit of an unpaid claimant who serves timely notice. Such literalism ignores the apparent policy of allocating the risks of loss resulting from vicissi-
Providing timely notice can protect only against the possibility that Anderson will have paid Brian & Gregory for labor and materials supplied by Pi-Con and then be called upon to pay again for the same labor or materials. A general contractor should not be permitted to escape from the responsibility imposed on it by statute because of a failure to serve timely notice that had no bearing on and did not cause the events that give rise to the money shortfall.
Where the loss of the general contractor cannot be attributed to delay in complying with notice requirements, where the loss is attributable to failure of performance by the subcontractor of its contractual obligations owing the general contractor, not attributable to a failure in performance of the unpaid claimant, the statutory purpose of providing a means of direct recovery without regard to the status of the general contractor/subcontractor relationship should not be defeated on the basis of inconsequential delay in serving notice of claim.
II
The present public contractor bonding act was enacted in 1963.9 This Court has not construed that statute as providing that the thirty- or ninety-day notice provisions are so far mandatory that,
The purpose of the notice provisions is to protect a general contractor, who makes disbursements to a subcontractor who fails to pay those with whom it deals, from being called upon to pay again for the same labor and materials. The thirty- and ninety-day notice provisions are mandatory in the sense that delay in giving notice defeats the claim of an unpaid claimant if the general contractor would, unless the time limits are enforced, in effect be required to pay again for the same labor and materials.
The thirty- and ninety-day periods are notice provisions, not statutes of limitations. Notice provisions, in contrast with statutes of limitations, are not designed to bar stale claims, but to give early notice of a potential claim so that the person entitled to notice can protect itself by taking appropriate action. If the failure to give timely notice did not result in the prejudice that the giving of notice seeks to forestall, the claim should not be barred as if it were stale, the purpose of requiring notice not having been thwarted.10
III
Subsequent to the enactment of the 1963 public contractor bonding act, the Legislature repealed the mechanics lien law11 and enacted the construc-
I would regard the construction lien act as a current statement of public policy and a guide to the construction of the earlier 1963 act even though the 1963 act has not been amended to so state. There is no reason to suppose that the Legislature might enact one policy in this regard for unpaid claimants in respect to private construction contracts and another for unpaid claimants in respect to public works construction contracts under the circumstance that, under the public contractor bonding act, the risk of loss is imposed on the general contractor, not the government.
RILEY, C.J. I respectfully dissent because, while I agree with the majority that this Court should look to the United States Supreme Court decision in Fleisher Engineering & Construction Co v
I
The United States Supreme Court decision in Fleisher involved the interpretation of the Miller Act,
We think that the purpose of this provision [notice by certified mail requirement] as to manner of service was to assure receipt of the notice, not to make the described method mandatory so as to deny right of suit when the required written notice within the specified time had actually been given and received. In the face of such receipt, the reason for a particular mode of service fails. It is not reasonable to suppose that Congress intended
to insist upon an idle form. Rather, we think that Congress intended to provide a method which would afford sufficient proof of service when receipt of the required written notice was not shown. [Fleisher, supra at 19. Emphasis added.]
I agree and believe that Fleisher requires the subcontractor to prove that the principal contractor received written notice within the time prescribed by the statute and not merely that the principal contractor had notice. In my opinion, Fleisher only excuses compliance with the certified mail requirement when a genuine issue of material fact does not exist regarding whether the principal contractor received written notice within the time prescribed by the payment bond statute.
II
Initially, I agree with the majority that United States Supreme Court, federal court, and Michigan Supreme Court decisions decided after Fleisher have interpreted either the notice provision of the Miller Act or
The purpose for the statutory requirement that the notice be in writing is to prevent misunderstanding between the parties and to afford certain minimal evidence of communication between the parties. Coffee v United States [ex rel Gordon], 157 F2d 968, 969 (CA 5, 1946) and Apache Powder Co v Ashton Co, 264 F2d 417, 421 (CA 9, 1959). Hence, the elimination of a requirement of any written
form of notice in a case where the receipt and content of notice is disputed would tend to emasculate the clear intent of the statute to avoid such disputes. See United States [ex rel Charles R Joyce & Sons, Inc] v FA Baehner, Inc, 326 F2d 556, 558 (CA 2, 1964).
Excavation argues that Mallory‘s testimony provides undisputed evidence that sufficient timely notice was given and that a written notice supplementing Mallory‘s testimony became unnecessary. Even if the Court were able to disregard the persuasive list of cases cited above which hold that written notice is a strict condition precedent to bringing suit under the Act, the Court would nevertheless reject Excavation‘s argument. In this case written notice would confirm or deny Mallory‘s supposition that she was told the amount of the Feinman bill. Written notice would evidence the nature of the communication and shed light on the context in which any information about the claim was given. It would indicate whether or not Mallory was justified in her conclusion that the telephonic conversation was intended merely as an effort by Garner to solicit Glenn-Stewart‘s aid in Excavation‘s attempts to contact Feinman and could in no possible way be interpreted as notice to Glenn-Stewart of a materialman‘s and supplier‘s claim. Thus, even without meeting Excavation‘s argument that the notice need not indicate an intent by the use plaintiff to look to the defendant for payment, written notice serves a useful purpose. Of course, if articulation of such intent were found to be required, written notice would serve the additional purpose of supplying notice or lack of notice of such intent.
[7] Finally, a number of courts have expressly rejected Excavation‘s argument that all the statute requires with respect to notice is that the general contractor have knowledge of the claim regardless of how that knowledge is acquired. In Bowden [v United States ex rel Malloy], 239 F2d [572,] 577 [(CA 9, 1956)], the use plaintiff argued that since a letter from a subcontractor to a gen-
“no rule of liberality in construction can justify reading out of the statute the very condition which Congress laid down as prerequisite to the cause of action” at 577.
I agree. The claimant must send notice in writing.
I also concur with the majority‘s recitation of the fourth element, specifically, that the claimant must send timely written notice. In People ex rel Wheeling Corrugating Co v WL Thon Co, 307 Mich 273; 11 NW2d 886 (1943), this Court denied recovery to a claimant who conceded that it sent written notice after expiration of statutorily proscribed time limits of the notice provision. I agree. Timely written notice is a condition precedent under
However, the issue in the instant case focuses upon this Court‘s interpretation and application of the first element. The majority concludes the first element requires that “a claimant must prove that the principal contractor actually received notice.” Ante, p 382. According to the majority, even though the statute specifically requires a claimant to send “[e]ach notice . . . by certified mail,” a claimant must only prove timely receipt of written notice. The majority contends that the Legislature
First, while I agree that this Court should look to Fleisher for guidance in the instant case, I disagree with the extent to which the majority relies upon and expands Fleisher. In Fleisher, the United States Supreme Court excused the claimant‘s compliance with the certified mail requirement because the principal contractor conceded that it had received timely written notice by regular mail. However, the Court never intimated that it intended to excise the certified mail requirement from the statute. I agree and decline to join the majority‘s erasure of the certified mail requirement from
Second, the majority justifies overlooking the certified mail requirement on the grounds that “[h]ad the Legislature desired a procedure whereby it could conclusively be established that defendant received plaintiff‘s notice, it would have required notice be sent certified mail with return receipt requested.” Ante, p 386. I do not agree. This Court should not ignore a statutory requirement upon the basis of our belief that the Legislature could have placed more exacting language within a given statute.6
Fourth, the justification advocated by the majority for ignoring the certified mail requirement also supports an interpretation of the payment bond statute which the majority specifically rejected, namely, the statute only requires that “the principal contractor [had] notice.”7 The majority contends that, “the ultimate purpose of the public works bond act [is] the protection of subcontractors and suppliers of materials,” and therefore, this Court should ignore the “technical” certified mail requirement. However, if the majority correctly argues that this Court should overlook one statutory requirement in the interest of protecting subcontractors and materialmen, then it would
Moreover, this Court‘s primary goal in interpreting
The words of a statute, however, should not be construed in the void but must be read together to effectuate the intention of the legislature. . . . The general rule of statutory construction was stated by this Court in Grand Rapids v Crocker (1922), 219 Mich 178 [182-183; 189 NW 221]:
“There seems to be no lack of harmony in the rules governing the interpretation of statutes. All are agreed that the primary one is to ascertain and give effect to the intention of the legislature. All others serve but as guides to assist the courts in determining such intent with a greater degree of certainty. If the language employed in a statute is plain, certain and unambiguous, a bare reading suffices and no interpretation is necessary. The rule is no less elementary that effect must be given, if possible, to every word, sentence and section. To that end, the entire act must be read, and the interpretation to be given to a particular
word in one section arrived at after due consideration of every other section so as to produce, if possible, a harmonious and consistent enactment as a whole.” [See also In re Forfeiture of $5,264, 432 Mich 242, 248; 439 NW2d 246 (1989).]
The legislative history of
Lastly, a comparison between notice provision of the Miller Act and
Thus, while I agree with Fleisher that it makes little sense to adhere to the certified mail requirement when the contractor concedes it received written notice, it does not also follow that we should ignore completely the terms of the statute and require a trial on the merits every time a subcontractor contends that it sent timely written notice by means other than certified mail. I decline to adopt an interpretation of
III
Each of the cases interpreting the Miller Act or
As applied in the instant case, although Pi-Con claims that it sent written notice by regular mail within thirty days, Anderson has continuously argued that it never received timely written notice. Moreover, Pi-Con has not submitted any other proof that Anderson received notice as required by
IV
Accordingly, I would hold that pursuant to
BRICKLEY and BOYLE, JJ., concurred with RILEY, C.J.
Notes
A claimant who has furnished labor or material in the prosecution of the work provided for in such contract in respect of which payment bond is furnished under the provisions of section 3, and who has not been paid in full therefor before the expiration of a period of 90 days after the day on which the last of the labor was done or performed by him or material was furnished or supplied by him for which claim is made, may sue on the payment bond for the amount, or the balance thereof, unpaid at the time of institution of the civil action, prosecute such action to final judgment for the sum justly due him and have execution thereon. A claimant not having a direct contractual relationship with the principal contractor shall not have a right of action upon the payment bond unless (a) he has within thirty days after furnishing the first of such material or performing the first of such labor, served on the principal contractor a written notice, which shall inform the principal of the nature of the materials being furnished or to be furnished, or labor being performed or to be performed and identifying the party contracting for such labor or materials and the site for the performance of such labor or the delivery of such materials, and (b) he has given written notice to the principal contractor and the governmental unit involved within ninety days from the date on which the claimant performed the last of the labor or furnished or supplied the last of the material for which the claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor was done or performed. Each notice shall be served by mailing the same by certified mail, postage prepaid, in an envelope addressed to the principal contractor, the governmental unit involved, at any place at which said parties maintain a business or residence. The principal contractor shall not be required to make payment to a subcontractor of sums due from the subcontractor to parties performing labor or furnishing materials or supplies, except upon the receipt of the written orders of such parties to pay to the subcontractor the sums due such parties. [
That any person having direct contractual relationship with a subcontractor but no contractual relationship express or implied with the contractor furnishing said payment bond shall have a right of action upon the said payment bond upon giving written notice to said contractor within ninety days from the date on which such person did or performed the last of the labor or furnished or supplied the last of the material for which such claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor was done or performed. Such notice shall be served by mailing the same by registered mail, ... or in any manner ....
If Anderson paid Brian & Gregory for labor or materials supplied by Pi-Con, it may have violated a procedure established by court order.
The payment bond between Anderson as principal and Federal Insurance Company as surety is for $2,705,000 in respect to general building work for an addition to Cass Technical High School, Detroit. The contract between Brian & Gregory and Anderson was entered into on June 16, 1982, and stated a contract price of $990,000.
Brian & Gregory filed a chapter 11 petition with the United States District Court on October 4, 1982. On October 22, 1982, a bankruptcy judge entered an order providing that Brian & Gregory was author-
ized to complete work on the Cass Technical High School project, and to enter into an amendment of the contract between Anderson and Brian & Gregory, and that the contract as amended was affirmed.
The amendment provided that Brian & Gregory would furnish Anderson with a list of the names, addresses, and telephone numbers of all subcontractors and suppliers who were or may become claimants pursuant to § 7 of the public contractor bonding act (see n 1 for reference to the act), and that Brian & Gregory should furnish with each request for payment to Anderson a list of subcontractors, suppliers, and others who are entitled to receive payment for work reflected in the request for payment, and that Anderson “shall remit the net sum as determined by the parties, by check or other negotiable instrument made payable jointly to Brian & Gregory and the supplier.” In the Matter of: Brian & Gregory Contracting Co., Inc., No. 82-05593-B, document 12. (Emphasis added.) See n 6.
Thereafter, on November 4, 1982, Pi-Con entered into a contract with Brian & Gregory to provide labor and materials for the Cass Technical High School project. Pi-Con‘s claim filed with the trustee in bankruptcy in the amount of $26,845.10 was allowed, and Pi-Con received a “dividend” from the trustee for $7,266.30.
The appeal in the instant case does not involve the second element. However, the parties should be allowed to address this issue at the trial on remand.[A]ny person having direct contractual relationship with a subcontractor but no contractual relationship express or implied with the contractor furnishing said payment bond shall have a right of action upon the said payment bond upon giving written notice to said contractor within ninety days from the date on which such person did or performed the last of the labor or furnished or supplied the last of the material for which such claim is made, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor was done or performed. Such notice shall be served by mailing the same by registered mail, . . . or in any manner in which the United States marshall . . . is authorized by law to serve summons. [
(6) The failure of a lien claimant, to provide a notice of furnishing within the time specified in this section shall not defeat the lien claimant‘s right to a construction lien for work performed or materials furnished by the lien claimant before the service of the notice of furnishing except to the extent that payments were made by or on behalf of the owner or lessee to the contractor pursuant to either a contractor‘s sworn statement or a waiver of lien in accordance with this act for work performed or material delivered by the lien claimant. This subsection does not apply to a laborer.
(7) The failure of a laborer to provide a notice of furnishing to the designee as required by subsection (2) shall defeat the laborer‘s lien for those wages for which the notice of furnishing is required. [
