Ecoplas, Inc. (“Ecoplas”) appeals from a judgment entered in the United- States District Court for the Western District of New York (Arcara, J.) granting a motion by Phoenix Aktiengesellschaft (“Phoenix”) to confirm an arbitration award. Because 9 U.S.C. § 207 preempts the consent-to-confirmation requirement of 9 U.S.C. § 9 in cases brought pursuant to the Convention on the Recognition and Enforcement of Foreign Arbitral Awards, June 10, 1958, 21 U.S.T. 2517, T.I.A.S. No. 6997 (the “Convention”), we reject Ecoplas’s conten *434 tion that the lack of consent to confirmation in the arbitration agreement provides a ground for reversal. We also reject Ecoplas’s claim under Article V(l)(b) of the Convention that it was unable to present its case in arbitration and that the award therefore should not be enforced. Accordingly, we affirm the judgment of the district court.
BACKGROUND
The parties entered into a licensing agreement in December 1993 under which Phoenix, a German corporation, granted Ecoplas, an American corporation, an exclusive license to produce and sell “Phoenix polyester-(UP)-moulding compounds.” Phoenix further agreed to provide Ecoplas with “secret technical knowledge as well as technical know-how relative to the manufacture” of those compounds. In exchange Ecoplas agreed to pay Phoenix royalties and an annual licensing fee.
The licensing agreement contained an arbitration clause, which provided in relevant part:
The parties shall make a diligent effort to settle amicably all disagreements in conjunction with this contract. If an amicable agreement is not reached then the arbitration court of the International Chamber of Commerce in Zurich shall have jurisdiction at the exclusion of regular courts. This agreement is subject to Swiss law.
In August 1997, Phoenix informed Eco-plas that it had sold a business portfolio to Bakelite AG, a German company, and requested that Ecoplas agree to a transfer of the licensing contract to Bakelite AG as well. Ecoplas, in response, informed Phoenix that it would “not be continuing the license agreement with Bakelite AG, and it is being considered terminated.” A dispute then arose over whether Ecoplas had terminated the agreement prematurely. Phoenix claimed that because Ecoplas refused to allow the license transfer, the original contract obligations between Phoenix and Ecoplas remained in place. Eco-plas maintained that the contract had been terminated in 1997 by mutual agreement. Ecoplas did not pay the license fees for 1997 and 1998.
On April 7, 1999, Phoenix filed a complaint with the International Court of Arbitration of the International Chamber of Commerce (“ICC”). Defending its failure to pay the fees, Ecoplas argued that Phoenix’s sale of its business portfolio to Bakelite AG had dissolved the licensing agreement between Phoenix and Ecoplas, and that, in any event, Phoenix had failed to provide usable technical advice as required by the agreement.
The arbitrator rejected Ecoplas’s contentions and rendered a decision in favor of Phoenix on December 15, 2000. He found that the sale of assets to Bakelite AG did not void the contractual relationship between Phoenix and Ecoplas, and that the licensing agreement did not require Phoenix to provide Ecoplas with more technical assistance than had already been provided. The arbitrator awarded Phoenix approximately $100,000, plus $5751 in arbitration costs and 40,000 Swiss Francs in legal fees.
Because Ecoplas failed to pay the arbitration award, Phoenix commenced an action seeking confirmation of the award in the Western District of New York pursuant to the Convention. In response, Eco-plas claimed that the federal district court lacked jurisdiction over Phoenix’s action because the arbitration agreement did not reflect the parties’ intent to consent to judicial confirmation of the arbitration award, as required by § 9 of the Federal Arbitration Act (“FAA”), 9 U.S.C. §§ 1-16, 201-08, 301-07 (2000). Citing Article *435 (V)(l)(b) of the Convention, Ecoplas further argued that the district court should not honor the arbitration award because the arbitrator had refused to hear certain evidence regarding the competency of the technical advice provided by Phoenix.
The district court adopted a recommendation from Magistrate Judge Hugh B. Scott that the court confirm the award.. In doing so, the court observed that it remained an open question whether the consent-to-confirmation provision of § 9 had been preempted by § 207 for cases arising under the Convention. The court held, however, that even if the requirements of § 9 did apply, the licensing agreement complied with those requirements. The agreement, Judge Arcara wrote, “sufficiently demonstrates the parties’ intent that the result of the ICC arbitration be final and binding, such that the claims would not be heard de novo in any court.” By adopting the reasoning of Magistrate Judge Scott, Judge Arcara also implicitly rejected Ecoplas’s Article V(l)(b) -claim. Ecoplas appeals.
DISCUSSION
This- case presents an unresolved question related to the FAA. This statute, enacted ’ originally in 1925,
1
aimed to “ ‘reverse the longstanding judicial hostility to arbitration agreements that had existed at English common law and had been adopted by American courts.’ ”
Ermene-gildo Zegna Corp. v. Zegna,
The FAA provisions at issue here are those that grant federal courts the authority to confirm an arbitration award. See 9 U.S.C. §§ 9, 207. ' Chapter 2 of the FAA provides that “[wjithin three years after an arbitral award falling under the Convention is made, any party to the arbitration may apply to any court having jurisdiction under this chapter for an order confirming *436 the award as against any other party to the arbitration.” 9 U.S.C. § 207. The award confirmation provision in Chapter 1 of the FAA is more restrictive in that it requires prior consent to confirmation by both parties. Specifically, it provides: -
If the parties in their agreement have agreed that a judgment of the court shall be entered upon the award made pursuant to the arbitration, and shall specify the court, then at any time within one year after the award is made any party to the arbitration may apply to the court so specified for an order confirming the award ....
9 U.S.C. § 9 (emphasis added). By including a consent-to-confirmation requirement, Congress aimed “to ensure that the parties have affirmatively agreed to the application of the federal substantive law contemplated by the [Federal Arbitration] Act to the interpretation of the arbitration agreement into which they have entered.”
I/S Stavborg v. Nat’l Metal Converters, Inc.,
We review
de novo
legal issues in a district court’s confirmation of an arbitral award.
See Pike v. Freeman,
Section 207 does not in any way condition confirmation on express or implicit consent. Because the plain language of § 207 authorizes confirmation of arbitration awards in cases where § 9’s consent requirement expressly forbids such confirmation, we hold that the two provisions conflict. Accordingly, we hold that § 207 preempts § 9’s consent-to-confirmation requirement in cases under the Convention.
2
*437
See
9 U.S.C. § 208. The only other circuit court to rule on this issue has reached the same conclusion.
See McDermott Int’l, Inc. v. Lloyds Underwriters of London,
Ecoplas argues that Chapters 1 and 2 have been found not to be in conflict where, as here, “the first results in limits being placed on the latter.” The two cases upon which Ecoplas relies for this proposition, however, do not support Ecoplas’s claim. In
Hartford Accident & Indemnity Co. v. Equitas Reins. Ltd.,
Ecoplas’s reliance on
Atlas Chartering Services., Inc. v. World Trade Group, Inc.,
Ecoplas cites only one case directly supporting its claim that § 9 and § 207 are consistent. In
Daihatsu Motor Co., Inc. v. Terrain Vehicles, Inc.,
the district court for the Northern District of Illinois held that § 9’s consent-to-confirmation requirement did not conflict with 9 U.S.C. § 207, even though the court also recognized that § 9’s consent requirement constituted “an additional limitation not otherwise included in Chapter 2.” No. 92-C-1589,
Ecoplas further argues that we should refuse enforcement of Phoenix’s awards on the grounds that Ecoplas was denied an opportunity to present its defense during the arbitration proceeding. Under Article V(l)(b) of the Convention, an exception to enforcement arises where “[t]he party against whom the award is invoked was not given proper notice of the appointment of the arbitrator or the arbitration proceedings or was otherwise unable to present his case.” See also 9 U.S.C. § 207 (“The court shall confirm the award unless it finds one of the grounds for refusal or deferral of recognition or enforcement of the award specified in the said Convention.”). Ecoplas contends that the arbitral panel refused to permit it to substantiate its main defense by denying the admission of testimony from Ecoplas’s technical staff regarding the defectiveness of the “transferred know-how.”
We find the Article V(l)(b) claim merit-less. The record reveals that Ecoplas received an opportunity to raise the defense in question and that the arbitrator rejected it on the merits. Because the contract between Ecoplas and Phoenix required only transfer of sufficient know-how to manufacture Phoenix’s compounds, and not to develop them for new applications, the arbitrator found that the testimony concerning the transfer of additional development know-how was irrelevant to whether the contract had been breached. Given the arbitrator’s careful consideration of the issue, Ecoplas’s claim that it was “unable to present [its] case” is groundless. 4
*439 CONCLUSION
For the foregoing reasons, the judgment of the district court is AFFIRMED.
Notes
. See Act of Feb. 12, 1925, ch. 213 § 1 et seq., 43 Stat. 883.
. The district court ruled for Phoenix on the alternative ground that even if § 9’s consent requirement applied, the arbitration clause satisfied the requirement. Though we need not discuss the issue in depth, we note that the language used in the Agreement, taken together with the parties’ actions, provides some support for the district court’s conclusion. Although the agreement contains no express consent provision, our cases have not required that consent be explicit in order to satisfy § 9.
See Kallen
v.
District 1199, Nat’l Union of Hosp. and Health Care Employees,
. The consent provision is only one of several differences between § 9 and § 207. Section 9, for example, requires applications for confirmation to be filed within one year of the arbitration, while § 207 provides the parties with three years to seek confirmation. Section 9, moreover, provides that the application for confirmation should be made "to the United States court in and for the district within which such award was made,” unless the parties have specified a different court. Section 207, in contrast, allows parties to the arbitration to apply to any court having jurisdiction under Chapter 2. Though these additional differences between the sections are not at issue here, they bolster our finding of preemption by demonstrating that the Convention contemplates a significantly less restrictive approach to confirmation than the original FAA. See also 9 U.S.C. § 204 (providing that an action pursuant to the Convention "may be brought in any such court in which save for the arbitration agreement an action or proceeding with respect to the controversy between the parties could be brought, or in such court for the district and division which embraces the place designated in the agreement as the place of arbitration if such place is within the United States”).
. In its reply brief, Ecoplas raises an additional defense to enforcement under Article V(l)(e) of the Convention, which provides that recognition and enforcement may be refused if "the award has not yet become binding on the parties.” Convention- Art. V(l)(e). Because this argument was not raised in Eco-plas’s opening brief, we decline to address it. See
Mitchell v. Fishbein,
