48 Mo. App. 455 | Mo. Ct. App. | 1892
The plaintiff and defendant entered into a certain written contract which provided amongst other things “that in consideration of .the services of said Phister in obtaining for said Gove $19,000 on the property, describing it, said Gove agrees to pay said Phister $475,” etc. On this contract the plaintiff sued defendant. In the petition it was alleged that in pursuance of the contract plaintiff procured for and proffered defendant a loan of $19,000 on defendant’s said property, and performed the contract in every particular on his part, and that the defendant refused
I. The appealing defendant contends that there was a lack of correspondence between the allegations in the petition and the proof adduced in support thereof. It would subserve no useful purpose to set forth the evidence in full. It is sufficient to say that the plaintiff in his capacity of broker procured a party, the New England Trust Company, who was ready and willing to make the loan to the defendant on the terms he required. The managing officer of this company had examined the defendant’s property, and was satisfied with it as a security of the loan defendant had applied to it for. The plaintiff brought the defendant and the trust company together, and the latter accepted the loan. The defendant in his application obligated himself if the loan was accepted to furnish an abstract of the title to the property. This he subsequently declined to do, so that the negotiation fell through at that point. The plaintiff did all that was required of him by his contract. He procured the loan which defendant neglected to take. He could have done nothing more if the defendant had taken the loan. It was no fault of the plaintiff that the defendant declined to take it. Under such circumstances the defendant cannot under the terms of the contract escape liability to plaintiff. The case is that of a contract wholly performed on the side of the plaintiff. The cause of action was properly stated and proven. These views find support in the following cases: Budd v. Zoller, 52 Mo. 238; Carpenter v. Rynders, 52 Mo. 278; Bailey v. Chapman, 41 Mo. 536; Love v. Owens, 31 Mo. App. 501; Harwood v. Diemer, 41 Mo. App. 48 ; Gaty v, Foster, 18 Mo. App. 639 ; Barnard v. Monnot, 33 How. Pr. 440; Glenworth v. Luther, 21 Barb. 145; Keys v. Johnson, 68 Pa. St. 42.
III. The defendant’s further contention is that the second instruction given for the plaintiff and for the defendant are inconsistent and contradictory. The plaintiff’s instruction told the jury that if the loan company accepted the loan and so informed defendant Gove, and was waiting upon said Gove to furnish an abstract, and that said Gove knew that said money on the loan could not be turned over to him until said abstract was delivered and title approved, and said Gove failed to deliver any abstract or present any acceptable
These two instructions are glaringly and irreconcilably repugnant. But since that given for the plaintiff is confessedly a correct exposition of the law based on the evidence defendant can have no advantage in this court on account of the conflict. The defendant’s instructions gave him a chance to escape a liability to which he was not in law entitled. The jury evidently disregarded defendant’s instruction, and adopted the theory of the plaintiff’s. We cannot see that the defendant has any just grounds of complaint in this regard. Blackwell v. Bailey, 1 Mo. App. 328; Loshe & Miller v. Railroad, 44 Mo. App. 645.
IV. The defendant’s final contention is that the court erred in excluding the evidence offered by him to the effect that if the Patterson loan was made to him that the one in question was not to be made. This evidence was inadmissible under the answer. If the
For the latter purpose it would have been admissible had the pleadings been of a frame to have authorized it. To have admitted it would have been violative of the well-settled rule that parol evidence is inadmissible to vary, alter or change the terms of a written instrument. It was wholly inadmissible for any purpose in the case. The terms of the contract were plain and unambiguous. There could be no doubt as to what was meant. It was not a case where such extraneous aid was needful in construing it.
The judgment must be affirmed.