Lead Opinion
OPINION
On June 5, 2003, appellant, equitable owner of 18.67 acres in Upper Merion Township, Montgomery County, submitted an application to the township’s Board of Supervisors to subdivide the property into two parcels, and to further subdivide one of those parcels into 17 residential lots. The Board twice requested extensions of time to make a decision; § 508 of the Pennsylvania Municipalities Planning Code (MPC), Act of July 31, 1968, P.L. 805, as amended, 53 P.S. § 10508, provides a municipality must take action on an application within 90 days of the next meeting of its governing body or planning agency, or such application will be “deemed an approval.”
Prior to that date, appellant filed a distinct conditional use application for the property. This plan reflected suggestions from the Township Planning Commission, and would have allowed development of 28 townhouse units on a 4.89-acre parcel, with a 8.65-acre open space parcel and a 4.38-acre recreational use parcel. On June 23, 2004, the Board denied this conditional use application, a decision the trial court and Commonwealth Court affirmed on appeal.
Six days after denial of the conditional use application, appellant filed an action for mandamus and peremptory judgment, asserting the initial subdivision application should be deemed approved under § 508 because the Board did not act upon it by the December 24 deadline. Mandamus is the appropriate mechanism to obtain recognition of a deemed approval of a proposed land development plan, see Lehigh Asphalt Paving and Construction Company v. East Penn
The court determined the conditional use application did not supersede the subdivision application, which was therefore deemed approved under § 508. The court distinguished the two applications, explaining a conditional use “addresses the use of the land, while a subdivision plan addresses how the land is to be developed. A conditional use application seeks approval for new and potential uses for the land that, if granted, would then require a later submitted subdivision plan to be filed.” Trial Court Opinion, 3/18/05, at 5; see also 2 Robert M. Anderson, Law of Zoning in Pennsylvania § 22.20 (1982) (“While the governing body of a municipality has broad discretion in adopting standards for the approval of subdivision and land development plans, it cannot include provisions relating to the use of land. Regulation of use is a matter appropriate for control through a zoning ordinance.”).
Because of this distinction, the trial court found inapplicable cases holding that a revised subdivision application causes the time for decision to run from the filing of the revised plan. See Wiggs v. Northampton County Hanover Township Board of Supervisors,
The Commonwealth Court reversed, holding that by filing the conditional use application, appellant abandoned the subdivision plan application. See Philomeno & Salamone v. Board of Supervisors of Upper Merion Township,
We granted allowance of appeal to determine whether filing a subsequent conditional use application effectively withdraws a pending inconsistent subdivision application for the same tract of land, or whether § 508 of the MPC “deems approved” all applications not acted upon in a timely manner. See Philomeno & Salamone v. Board of Supervisors of Upper Merion Township,
Our courts have long permitted landowners to file inconsistent subdivision or land development applications, and they are entitled to action on all applications. See Fiori, at 1208; Bobiak v. Richland Township Planning Commission,
It is clear that revising a land use application extends § 508’s 90-day decision period, see Wiggs, at 1363; see also DePaul, at 835. However, it must be a voluntary revision, and contain substantial changes. Id., at 835 (“The obvious effect of filing the revised plans was to void the original plans and substitute therefor the revised plans.”). Appellant’s conditional use application was not intended to revise the land use application as it dealt with zoning issues as opposed to the original subdivision application, which addressed land use. See 53 P.S. § 10107(a) (“ ‘Conditional use,’ a use permitted in a particular zoning district.... ‘Subdivision,’ the division or redivision of a lot, tract or parcel of land by any means into two or more lots, tracts, parcels or other divisions of land....”).
In Capital Inv. Dev. Corp., two mutually-exclusive subdivision plans were submitted to the township, and when the
Here, the Commonwealth Court did not address Capital Inv. Dev. Corp., Bobiak, or Fiori, though it did acknowledge that § 508 does not prohibit submitting inconsistent land use applications for the same tract of land. Nevertheless, it found the second application “effectively abandoned the subdivision plan application”; later the court stated the second plan caused “confusion and protracted proceedings” which resulted in the failure to rule on the first plan. See Philomeno, at 1048-49. We find no evidence of record supporting either conclusion.
Wiggs and DePaul hold revisions of previously submitted subdivision plans restart the 90-day approval period, but as noted, we are not dealing with revision of an existing subdivision application. Neither case addresses a conditional use application filed in addition to a subdivision plan. Alternate plans are different from revisions of existing plans, especially when, as here, they are filed under different ordinances and involve different requests. The original plan here was not withdrawn, and the record shows no acts consistent with abandonment save the conditional use application. Offering an alternative plan does not make the original submission disappear.
Because the Board did not act on the initial subdivision plan within the mandatory time period under § 508, the learned trial court correctly deemed it approved. A clear reading of § 508 requires the township to act on land use applications within 90 days, and the Commonwealth Court’s order is reversed. Additionally, appellant’s Application for Substitution of Legal Owner of the Property Pursuant to Pa.R.A.P. 502(b) is granted.
Order reversed. Jurisdiction relinquished.
Notes
. If the next meeting is over 30 days after filing, the 90-day period begins to run 30 days after filing, giving the body up to 120 days to render a decision. See 53 P.S. § 10508.
. As legal owner of the property, and assignee of the subdivision plan at issue in this appeal, Sabertooth, LLC has been adversely affected in a substantial, immediate, and direct manner. See Hydropress Environmental Services, Inc. v. Township of Upper Mount Bethel, County of Northampton,
Concurrence Opinion
concurring.
Although I support the result obtaining under the majority opinion, I differ with its analysis.
As I understand the majority opinion, it applies a general rule that the filing of alternate and/or inconsistent land devel
One difficulty with this analysis, it seems to me, is that the words “alternate,” “inconsistent” and “revised” are not closely defined, and in the context of land development plans, these terms are not necessarily mutually exclusive.
Here, however, it is undisputed that the alternative or revised plan was offered at the suggestion of the Township.
Finally, I note that the application of deemed approval statutes may raise due process concerns, at least with respect to neighboring landowners who may have a direct interest in the outcome of a land use proceeding, but who have no control over the issuance of the decision necessary to prevent an automatic approval. No such interests, however, are raised in this appeal.
. I realize that the majority opinion does not treat Appellant’s conditional use application as in the nature of a land development plan and, for the same reason, does not consider such application as a revision to the original subdivision plan. See, e.g., Majority Opinion at 412,
. Morris seems to me to be irreconcilable with the Commonwealth Court's later decision in Appeal of Fiori Realtor, Inc. from Decision of Lower Southampton Twp. Bd. of Supervisors,
. We would not be free to consider such an inquiry, absent a constitutional violation, but for the fact that Section 508 is silent as to the effect of serial applications upon the 90-day approval period. See 1 Pa.C.S. § 1921(b) ("When the words of a statute are clear and free from all ambiguity, the letter of it is not to be disregarded under the pretext of pursuing its spirit.”). Under Section 508, a key event in calculating the ninety-day period is the filing of "the application,” 53 P.S. § 10508, and I believe that the filing of serial applications may render the statute ambiguous in terms of which filing or filings represents “the application” pending for consideration before the governing body. In this regard, I would conclude that the Legislature could not have intended to impose upon municipalities the obligation of having to consider numerous, inconsistent land development applications and render a decision on each individual application within 90 days of filing. See generally 1 Pa.C.S. § 1922(1) (setting forth the presumption that the Legislature "does not intend a result that is absurd, impossible of execution or unreasonable”).
. Other state courts have determined that their legislatures did not intend harsh results in providing for deemed approval where there is legitimate confusion or inadvertence. See, e.g., Manalapan Holding Co. v. Planning Bd. of Hamilton Twp., 92 N.J. 466,
. In the case of minor revisions, I do not believe that a new ninety-day period should begin. However, again, the party seeking the revisions should make clear its perspective concerning the substantiality of revisions so that at least all parties are aware of a potential difference and can seek legal advice and apply precautionary measures where appropriate.
. The Township’s brief does not provide further detail; according to the landowner's submission, the governing body sought to address open space concerns by requesting the cluster development overlay.
