181 Pa. Super. 625 | Pa. Super. Ct. | 1956
Opinion by
In March, 1955 the Philadelphia Electric Company applied to the Public Utility Commission for approval to acquire a right-of-way across appellants’ farm. To this application an answer was filed stating that the condemnation was contrary to public convenience and
Is the order for the proposed line supported by evidence of necessity? The record reveals that the purpose for the transmission right-of-way is to coordinate the company’s system through the Bradford substation to assure adequate service to the Cliester-Marcus Hook area. This proposed line will integrate the network to enable it to supplement power deficient areas from adjacent areas having available capacity. The whole enterprise, according to the testimony, will provide for the integration of the present Chester generating station and the proposed Eddystone station with other stations of the Philadelphia Electric Company and other Atlantic Seaboard utilities. This, it is asserted, is essential to national defense and industrial expansion. See Lower Chichester Twp. v. Pennsylvania Public Utility Commission, 180 Pa. Superior Ct. 503, 119 A. 2d 674.
The Act of May 21, 1921, P. L. 1057, 15 P.S. 11S2, provides for the exercise of eminent domain where the service is necessary for public convenience. Our Appellate Courts have held that not only existing needs are to be considered but also future necessities. Chew v. Philadelphia, 257 Pa. 589, 101 A. 915; Pittsburgh Junction R. R. Company’s Appeal, 122 Pa. 511, 6 A. 564; Pittsburgh, Fort Wayne and Chicago Railway Company v. Peet, 152 Pa. 488, 25 A. 612. In Byers v. Public Utility Commission, 176 Pa. Superior Ct. 620, 109 A. 2d 232, we ruled that the selection of a route for transmission lines is a matter for the utility in the first instance and, unless it is shown that it proposes to ex
This Court will not substitute its own judgment for that of the commission unless the order is clearly unreasonable and not in conformity with law, or where there is a flagrant abuse of discretion. It was shown that the proposed line is connected with improvement of service as an important factor. The route across the property was determined and fixed after careful investigation and consideration of all factors. It has not been shown by the property owners that the proposed route was selected wantonly or capriciously; on the contrary, the inability of appellants to point out another, more feasible route is in itself sufficient proof
The question, it seems to us, is an administrative one. It is not for this Court to interfere with the commission’s finding in questions which the law requires it to determine when there is sufficient evidence to sustain its conclusion.
The other question raised by appellant is whether the commission correctly refused to reverse the examiner on his ruling in the record, namely:
“I think you are entitled to know where the route is going from beginning to end. However, I don’t think you are entitled to the title holders of the properties.” Was the commission’s order, upholding the examiner, reversible error? Appellants demanded the names of all property owners on the route line. The examiner refused their demand but, at the same time, permitted full cross-examination to determine the route. We cannot agree with appellants’ contention that this action of the examiner, as upheld by the commission, was error. The records reveal that exhibit No. 3, a topographical map, shows, among other pertinent factors, the following evidence: (1) the entire route of the lines; (2) the names of the townships; (3) natural landmarks; and (4) communities, highways and railroads. This extensive information was available to the appellants and, we believe, was sufficient to enable them to determine the names of all property owners affected by the proposed line.
Approval of the application by the commission is amply supported by the evidence and is justified as an important factor in connection with the improvement of the service. In view of the reasons above stated