MEMORANDUM DECISION AND ORDER GRANTING IN PART AND DENYING IN PART TRAVELERS’ MOTION FOR SUMMARY JUDGMENT
Pheasantbrook Home Owners Association’s (“PHOA” or “Pheasantbrook”) filed a complaint for breach of a contract of insurance and. breach of the covenant of good faith and fair dealing by The Travelers Indemnity Company-.(“Travelers”) related to PHOA’s insurance claim involving wind damage to PHOA premises. Travelers moves for summary judgment (“Motion”).
TABLE OF CONTENTS
SUMMARY JUDGMENT STANDARD ... 1344
UNDISPUTED FACTS ... 1344
PHOA Is Insured by Travelers ... 1345
Travelers and PHOA Conduct Initial Inspections ,., 1347
PHOA Hires HWC, HWC Provides Estimates to Travelers ... 1348
February 27, 2012 Email from PHOA to Travelers ,.. 1348
March 1, 2012 PHOA Board Meeting and Statements Regarding Building Code ... 1349
HWC Submits Work Orders ... 1350
May 14, 2012 Email and Páymént from Travelers to PHOA ,.. 1350
PHOA/HWC Advises of Project Completion and Submits Supplement ... 1352
.Travelers Seeks More Information Regarding the Supplement ... 1353
Travelers Reviews Supplement and WA Report ... 1353
Travelers Denies Supplement ... 1354
DISPUTED FACTS ... 1355
DISCUSSION ... 1356
A. Travelers Is Not Entitled to Summary Judgment as to Breach of Contract Claims ... 1356
i. There'Is a Genuine Issue Regarding Whether PHOA Failed to Perform ... 1357
ii. There Is a Genuine Issue Whether Travelers Fulfilled All Its Obligations under the Policy ... 1358
B. Travelers Is Entitled to Summary Judgment as to Breach of Covenant of Good Faith and Fair Dealing Claims ... 1359 !
ORDER ... 1361
SUMMARY JUDGMENT STANDARD
Summary judgment is appropriate if “there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.”
The moving party “bears the initial burden of making a prima facie demonstration of the absence of a genuine issue of material fact and entitlement to. judgment as a matter of law.”
UNDISPUTED FACTS
Windstorm Causes Damage to PHOA Buildings
1. On December 1, 2011, PHOA suffered property damage as a result of a wind
2. Each of the buildings sustained wind damage.
3. A windstorm is a covered cause of loss under the Policy, and Travelers accepted coverage for the Claim, subject to the Policy’s terms, conditions, limitations, and exclusions.
4. The December 1, 2011 loss was categorized as a CAT claim, which means it was a catastrophe with widespread damage exceeding $7 million.
PHOA Is Insured by Travelers
5. PHOA is the named insured under Condominium PAC Policy No. 1-680-3048W969 (“Policy”) issued by Travelers with effective dates of December 4, 2010 to December 4, 2011.
6. The Policy insures property at PHOA against covered losses:
A. COVERAGE
We will pay for direct physical loss of or damage to Covered Property at the premises described in the Declarations caused by or resulting from a Covered Cause of Loss.14
7. The Policy explains that “Covered Causes of Loss” include
RISKS OF DIRECT PHYSICAL LOSS unless the loss is:
a. Limited in Paragraph A.5, Limitations; or
b. Excluded in Paragraph B., Exclusions.15
8. The Policy excludes from coverage damage caused by wear and tear and hidden or latent defects in the insured premises:
2. -We will not pay for loss or damage caused by or resulting from any -of the following:
d. (1) Wear and tear;
(2)rust, corrosion, fungus, decay, deterioration, wet or dry rot, mold, hidden or latent defect or any quality in property that causes it to damage or destroy itself;16
9. The Policy excludes from coverage continuous leaks, condensation, or vapor:
2. We will not pay for loss or damage caused by or resulting from any of the following:
f. Continuous or repeated seepage or leakage of water, or the presence or condensation of humidity,- moisture or vapor, that occurs, over a period of 14 days or more.17
10. The Policy excludes from coverage faulty or defective design, workmanship, repair, construction, materials, and maintenance:
3. We will not pay for loss or damage caused by or resulting from any of the following under Paragraphs a. through
c. ...
c. Faulty, inadequate or defective:
(1) Planning, zoning, development, surveying, siting;
(2) Design specifications, workmanship, repair, construction, renovation, remodeling, grading, compaction;
(3) Materials used in repair, construction, renovation or remodeling; or
(4) Maintenance; of part or all of any property on or off the described premises.18
11.The Policy also has provisions applicable to repairs required by ordinance or law, including a $25,000 limit for such repairs:
(1) In the event of damage by a Covered Cause of Loss to a building that is Covered Property, we will pay. for:
(c) The increased cost of construction, meaning the increased cost to repair, rebuild or construct the BUSINES-SOWNERS property as a consequence of enforcement of the minimum requirements of any .ordinance or law. This increased сost of construction coverage applies only if:
(i) .The building is insured-for replacement cost;
(ii) The building is repaired, rebuilt or reconstructed; and
(iii) The repaired, rebuilt or reconstructed building is intended' for similar occupancy as the current building, unless otherwise required by zoning or land use ordinance or law. • -' '
(6) The ■ most we will pay for loss under this Additional -Coverage for the total of all coverages described in Paragraph (1) above in any one occurrence is $25,000 at each described premises.19
12. The Policy also requires that PHOA cooperate with Travelers in the event of a' loss:
E. PROPERTY LOSS CONDITIONS
The following conditions apply in addition to the Common Policy Conditions:
3. Duties in the Event of Loss or Damage
a. You must see that the following are done in the event of loss or damage to Covered Property:, -
(6) As often as may be reasonably required, permit us to inspect the property proving the loss or damage and examine your books and records. Also permit us to take samples of . damaged and undamaged property for inspection,' testing and • analysis, • and permit us to make copies from your books and records. ’
(9) Cooperate with us in the investigation and settlement of the claim.20
‘ 13. The Policy was a “replacement cost policy.”
14. The Policy as issued had a blanket coverage limit in the amount of $18,215,653.00.
15...The Policy does,not prohibit or exclude the submission of a supplemental claim.
Travelers and PHOA Conduct Initial Inspections
16. Travelers’ adjuster, Mike Slosek, conducted an initial inspection on December 4,2011.
17. On December 6, 2011, the claim was reassigned to general adjuster Robert Lewis who retained Larry Tieman of Young & Associates, a construction consultant, to assist with the scope of repairs and estimate of damage.
18. Beginning on December 12, 2011, Mr. Lewis.- and Mr. Tiernan. met- with PHOA’s representative, Robin Wheelwright, and PHOA’s contractor at the time, Pride Restorations, LLC (“Pride”), to inspect the premises and discuss the loss.
20. On January 6, 2012, Mr. Tiernan met with Beth Schumaker from PHOA to perform a follow-up inspection on some PHOA buildings.
PHOA Hires HWC, HWC Provides Estimates to Travelers
21. Later in January 2012, PHOA fired Pride and hired Hoffman Weber Company (“HWC”) to act as its general contractor to effect the repairs.
22. HWC’s initial estimate, dated January 23,2012, was for $1,849,141.46.
23. The January 23, 2012 Estimate called for the complete replacement of all roofs at PHOA.
24. Prior to May 10, 2012, Travelers stated that it did not agree to replace the amount of roofing HWC said needed replacement.
25. Travelers further had concerns about the claim proceeding to appraisal in that it did not want to “end up replacing all of the siding on all the buildings to match” if the appraisal panel did not agree with Travelers’ proposed method of salvage repair.
26. HWC’s estimated increased to $2,411,858.77 on February 8, 2012, when PHOA and HWC discovered there was no available match for the existing aluminum siding and, again, called for the complete replacement of all roofs.
27. Many of the roofs at PHOA were comprised of organic shingles, which are discontinued and no longer made.
28. Under replacement cost coverage, if the shingles are damaged from a covered cause of loss (windstorm) and need to be rеplaced, they would be replaced with new shingles.
February 27, 2012 Email from PHOA to Travelers
29. As of February 27, 2012, there was a disagreement between PHOA/HWC and Travelers and its consultant Young and Associates regarding the scope of repairs.
30. On February 27, 2012, the president of the PHOA board, Robin Wheelwright, sent an email to Mr. Lewis.
31. The email stated:
Bob,
The reason that Hoffman Weber did not provide an estimate with the same scope of repairs as yours is because Pheasant-brook HOA and H-W did not agree withthe findings. When it comes to roofing, there is far more damage on the roofs than what the initial inspection had shown. Many of the roofs we have at Pheasantbrook are a discontinued organic shingle, which'is no longer available and cannot be “patched” in with asphalt. A few repairs have bene [sic] done to the roofs out of sheer necessity, this does not mean that we want our roofs pieced together after a major catastrophic event like we had December 1st.
The reason that there [sic] siding estimate is a great deal higher is that the existing aluminum siding is no longer available to be matched. The profile of the siding and the color are both discontinued. I strongly believe that patching and salvaging will decrease valuation, certainly not “pre-storm condition”, [sic] Even if you replaced a few buildings it would be unacceptable, as we would have mismatched and pieced. together siding throughout our complex. Again, unacceptable. . ,
It is the firm belief of Pheasantbrook HOA that Hoffman Weber has done their diligence on this project and we completely support their position that this project needs “replacement” in lieu of “salvage, piece together and repair.”39
32.On or about February 29, 2012 through on or about March 2, 2012, Mr. Tiernan, another construction consultant, Dustin Smoot, of Pie Consulting, and Andy Oakes, .of HWC,.inspected twelve roofs at PHOA.
“March 1, 2012 PHOA Board Meeting and Statements Regarding Building Code
33. On March 1, 2012, the PHOA Board Members met-to discuss the “Traveler’s Claim/Wind Storm 12/1/2011.”
.Per Any Oakes, .there is a State building code that will 'mandate full replacement of a roof if it is deemed that >25% of the roof nеeds replacement. Andy is trying to ‘lock’ the damage scope into more than 25%-50% on every roof for approval. He .will use the legality of the code after the approval has been issued by Bob Lewis/Traveler’s for maximum roof replacement coverage. Andy believes that Traveler’s will be ‘forced’ into full roof replacement on all but 3 of the roofs.42
The “State building code” referred to in the above statement is the 2006 . International Residential Code (“IRC”).
34. During a deposition, Mr. Oakes stated: -■ ;i •
We were trying to get the city [of Cen-terville] to put the 2006 building code that if 25% or more of a roof is being done at any time given, the entire roof needs to be brought up to current building code, which means they would needto add ice' and water on these, which means that roofs would need to be replaced. We were trying to get the city to put that on letterhead for us and they did not want to get'involved in-the battle between Pheasantbrook and the insurance company. 44
35. It is now undisputed that the 2006 IRC does not apply to the work done by HWC at PHOA. Rather, the 2009 Internatiоnal Building Code (“IBC”) was adopted by Centerville City on June 15, 2010.
'36. Even if the 2009 IBC had hot been adopted by Centerville, the 2006 IRC would not have applied because the 2006 IRC only applied to detached, one- and two-family dwellings, and the buildings at PHOA are four-family dwellings.
38. On August 18, 2015, PHOA’s expert, Mr. Hoffman, advised in his- deposition that the 2006 IRC did not apply, but the 2009 IBC was applicable to the PHOA repairs.
HWC Submits Work Orders
39. PHOA was presented with several work orders by HWC oh May 6, 2012, which were signed by some board members that day and-ultimately formally approved by the PHOA board óh Juné 5, 2012.
The first work order addressed the siding repairs, while the second called for the complete replacement of all the roofs at PHOA (except the maintenance shed), ■and repair and- replacement of various bridges on the Premises (which were required because they were in general disrepair, not because they were damaged in the Windstorm). The total contracted amount for all of these repairs was $2,010,916.00, which is $653,380.08 more than $1,357,535.92.
Máy 14, 2012 Email and Payment from Travelers to PHOA
41. On May 14, 2012, Robert -Lewis wrote an email to PHOA President Robin Wheelwright.
42. Mr. Lewis also explained that Travelers would issue payment to PHOA in the amount of $776,170.07, and the remaining amount would be issued once construction was completed.
44. On July 5, 2013, Travelers issued a payment to PHOA in the amount of $380,517.71.
45. PHOA' did not agree to the $1,357,535.92 estimate.
46. PHOA decided to proceed with the roof repairs, despite being dissatisfied with what Travelers was offering to pay for.
47.. Mr. Lewis’s email also explained that:
It has been our experience that there is always the possibility of missed or hidden damage to be found once demolition is complete, and restoration is started. However, any supplemental costs, or missed damages, must be submitted to Travelers Casualty Insurance Compаny of America (hereafter Travelers) for our review and approval prior to any additional costs being incurred. We reserve the right to decline consideration for any supplemental costs that we have not remewed and approved prior to their obligation and/or submission. When, or if, a supplement item or cost is identified, travelers requests that we be given immediate notice of the supplement (within 3 business days), so that we may visit the site, if necessary, and/or communicate with the contractor,58
48. Mr. Lewis’s email also stated that:
1.It is Travelers’ position that we agree to reimburse you for any repair/replacement costs that are necessary to affect repairs as owed according to the policy of insurance. Once you choose a contractor to affect the reconstruction, we will be happy to work with you and the contractor to verify that no necessary repair/reconstruction costs have been overlooked in relation to the scope of repair. This will ensure a fair and equitable claim settlement.
2. Any supplemental costs, or missed damages, must be submitted to Travelers for our review prior to any costs being incurred. We reserve the right to decline consideration for any supplemental costs that we have not reviewed and approved prior to their obligation .and/or submission.
3. When, or if, & supplement item or cost is identified, Travelers requests that we be given immediate notice of the supplement (within 3 business days), so that we may visit the site if necessary, and/or communicate with the contractor. Travelers will agree to retain a cost consultant to monitor the repair, costs, if necessary. This will be done at or [sic] cost and discretion.
4. If any additional/supplemental costs are required by the building department, and/or local laws or ordinances, Travelers does request that any additional code related costs be subhiitted to us for our review and approval prior to any agreements/contracts to incur the costs. We will require verifiable documentation and/or proof to verify that these “code” type supplements are required due to a specific building code, law, and/or ordinance.59
50. Travelers stipulations for the submission of supplements are not contained within the Policy.
51. Mr. Lewis’s May 14, 2012 email did not quote the “cooperation” clause of the Policy.
' 52. As of May 14, 2012, Travelers was of the opinion that PHOA had cooperated.
PHOA/HWC Advises of Project Completion and Submits Supplement
53.On October 2, 2012, Robin Wheelwright advised Travelers they were nearing completion of the project and asked Travelers to consider an inspection of the removal and replacement work.
54.On October 3, 2012, Robin Wheelwright wrote an email to Mr. Lewis stating: “It appears that the Pheasantbrook Community is nearing the conclusion of many major construction projects.' It is finally all coming together and for the most part, we are very pleased with the choices the HOA has made in rebuilding, replacing and repairing.”
55. On May 7, 2013, Mr. Lewis received a call from HWC, advising that they would be submitting a supplemental estimate. Mr. Lewis did not discuss the supplemental estimate at that time.
56. A supplemental estimate includes additional damage outside of the initial scope, or include items that were missed within the original scope that should have been included.
57. On June 1, 2013, PHOA advised Travelers that construction, including the punch list items, had been completed.
58. On June 6, 2013, HWC submitted the supplemental estimate in the amount of $540,897.70 (“Supplement”) to Travelers stating it was seeking payment for “complete roof replacement, additional under-layment for low slope areas, decking for unnailable [sic] surfaces, and sill flashing around windows.” With the Supplement, HWC provided a cost breakdown for the supplemental work and building permits pulled during the construction.
59. Travelers did not speak with HWC regarding the Supplement.
60. HWC’s Supplement did not include costs to redo work, or the cost to correct poor workmanship.
61. The Supplement includes a full summary of the dаmages caused by the wind loss event and accurately reflects the work
62. Travelers’ consultant, Young & Associates, never performed an inspection at the property relative to the Supplement submitted.
Travelers Seeks More Information Regarding the Supplement
63. On June 14, 2013, Mr. Lewis sent PHOA a letter concerning the Supplement, raising concerns that PHOA was notifying Travelers of a significant deviation after the construction had been completed and reserving rights under the Policy. Mr. Lewis requested that PHOA provide:
... all documentation in your/their [HWC’s] possession that would support the line items in the supplemental damage claim. This may include photographs, invoices, sub-contract agreements, material invoices, project accounting summaries/records, proofs of payment, and other items that support the additional amounts being claimed.75
64. On June 24, 2013, in response to Travelers’ request, HWC submitted a report from Western Architecture (“WA Report”) to support the Supplement with the explanation that the WA Report “brought about the supplements. The work complete [sic] was done to compile [sic] with building standards.”
65. Upon being advised that PHOA had retained an architectural firm, Travelers did not discuss the same with PHOA.
66. The WA Report was prepared after WA’s retention by PHOA “to complete an assessment of the building envelope components on the structures located' at Pheasantbrook ... in conjunction with the recent roofing and siding replacement in the community” by HWC.
67. One of WA’s three primary objectives was to “[a]ddress defective construction that is not in compliance with prevailing building code, manufacturers [sic] requirements and industry standard practices at the time of construction.”
68. Travelers did not have any discussions with Western Architecture regarding the WA Report.
Travelers Reviews Supplement and WA Report
69. On June 24, 2013, Mr. Lewis requested that Travelers’ construction consultant, Mr. Tiernan of Young and Associates review the Supplement and the WA Report to determine “if the additional charges represent reasonable and necessary costs of repairs related to the windstorm.”
70. On July 29, 2013, Mr. Tiernan sent his report (“YA Report”) concerning the Supplement to Mr. Lewis.
72. Mr. Tiernan observed that:
[t]here is no documentation or comments, etc. within the supplement which would support the addition of any of the included items in the approved scope of work for Pheasantbrook. Accordingly, YA has no basis on which to support or not support the respective work scope additions for a particular building.84
73. Mr. Tiernan further observed that:
YA and HWC had previously agreed on the buildings and quantities associated with roofing repairs for the claim; there had been no information presented to YA that those previously approved quantities needed to be revised.85
74. Mr. Tiernan explained that:
a. The sill flashing that PHOA requested payment for would not be required as a result of the windstorm;
b. YA had not observed in all .of its inspections, and PHOA did not present any evidence of a signifiсant amount of wall sheathing that required replacement; and
, c. While there may have been a need for roof sheathing not called for in the original scope of work, PHOA did not pres'ent 'any evidence to demonstrate that these areas were indeed discovered during construction.86
751 Mr. Tiernan explained that:
In any event, it is YA’s opinión that the observed construction and maintenance deficiencies included in the Western report do not have ány bearing on the wind event of December 2011, which was the basis for the carrier’s (and YA’s) involvement-in the claim. Construction deficiencies associated with HWC’s work need to 'be addressed directly with HWC, while any observed maintenance deficiencies need to be addressed by the Pheasantbrook HOA relative to the property’s long term maintenance plan.87
Travelers Denies Supplement
76. On August 5, 2013, Travelers denied PHOA’s claim for payment of the Supplement.
77. Travelers explained it and its building consultants.had reviewed the Supplement and the WA Report and that the Supplement was not covered because:
1) Travelers was given no notice of the .alleged additional damages prior to their repair and had no opportunity to inspect/document or validate the nature of the damages, and 2) the additional costsappear to pertain to repairs that were associated with correcting construction defects as .identified in the report from WA. 89
78. Travelers, nevertheless, requested that PHOA provide any “new, or previously undisclosed, information that [PHOA] may feel might impact Travelers’ position ... within the next thirty (30) days and we will review it promptly.”
79. PHOA did not provide any additional information, and instead filed this lawsuit.
80. PHOA is seeking complete replacement of all the roofs due to wind damage.
DISPUTED FACTS
1. After all of these inspections and additional discussion following the February 20 to March 2, 2012 inspections, in April 2012, HWC/PHOA came to an agreement with Travelers concerning the scope of work required to repair damage caused by the windstorm.
2. The agreed replacement cost to effect the repairs caused by the Windstorm was $1,357,535.92.
3. As refleсted by the PHOA-HWC work orders, PHOA and HWC always planned to replace every roof at PHOA, without telling Travelers, and then seek to have Travelers pay for the replacements, despite the mutually agreed upon scope of repairs.
4. Mr. Lewis explained that Travelers had come to an agreement with PHOA regarding the scope of necessary repairs, which was reflected in the estimate prepared by HWC and attached to Mr. Lewis’ May 14,2012 email.
5. Despite their explicit agreement with Travelers on the scope and cost of repairs, and in furtherance of-their scheme to force Travelers to pay for the additional work, PHOA and HWC commenced to replace every roof at PHOA without notice to Travelers even though “everybody” at PHOA and HWC knew of Travelers’ standing request that PHOA advise Travelers of any need to deviate from the Agreed Scope.
6. The WA Report does not explain' why every roof at PHOA had to be replaced, likely because every roof had been cоmpletely re-roofed.by the time WA even began its inspections.
8. Likewise, the WA Report does not suggest that the sheathing’s unnailable condition was caused by the windstorm.
9. Eric Hoff, one of the contributors to the WA Report, has since testified that the sheathing identified in the Supplement appeared to be damaged by years of water intrusion and not as a direct result of the Windstorm.
10. And, the WA Report does not explain how the sill flashing was required as a result of the Windstorm.
11. Travelers understood that HWC wrote an estimate and was of the belief that all the roofing and siding on the buildings needed to be replaced.
12. Travelers’. consultant did not have any conversations with WA regarding the report.
DISCUSSION
PHOA asserts two causes of action in its First Amended Complaint. The first cause of action relates to breach of contract, and the second relates to breach of the implied covenant of good faith and fair dealing.
A. Travelers Is Not Entitled to Summary Judgment as to Breach of Contract Claims
“The elements of a prima facie case for breach of contract are (1) a contract, (2) performance by the party seeking recovery, (8) breach of the contract by the other party, and (4) damages.”
Travelers advances two arguments with respect to breach of contract. First, Travelers argues summary judgment should be
Travelers also argues that summary judgment should be granted in its favor because it has fulfilled all of its obligations under the Policy. Travelers believes it has “paid for the repairs caused by the Windstorm,”
i. There Is a Genuine Issue Regarding Whether PHOA Failed to Perform
Travelers argues that the' “undisputed evidence” shows that “PHOA failed to cooperate with Travelers in ‘the investigation and settlement of the claim.’ ”
Travelers cites Cardella
The undisputed facts show that PHOA, through. HWC, advised Travelers before work began, .that repairs and replacements would total about $2 million. Travelers then sent an email on May 14, 2012 stating that the «work would be completed for $1.8 million, and gave instructions to PHOA about how to submit supplemental claims. While the May Í4 email purports to include certain requirements for the submission of supplemental claims, such as “within ’ three days”' and “before work is completed,” there is no requirement contained in the Policy that supplements be submitted within a' certain'time frame.
Furthermore, to the extent Travelers argues there was an “Agreed Scope” of the work to be performed, this fact is disputed,
ii. There Is á Genuine Issue Whether Travelers Fulfilled All Its Obligations under the Policy
Next, Travelers argues that summary judgment should be granted because Travelers fulfilled all its obligations under the Policy.. Travelers asserts that. the parties “came to an Agreed Scope in May .2012,” which “identified the repairs as a.result of the Windstorm,” and then “Travelers paid the amount it and PHOA agreed was due for the covered damages resulting from the Windstorm.”
As explained above, whether’there was an “Agreed Scope” is disputed.
Travelers is also incorrect in its argument that it is undisputed that “each and every item identified in the 'Supplement is excluded from coverage by the unambiguous terms of the Policy.” This is disputed by PHOA.
Finally, Travelers’ argument that “nothing in the Supplement was required by code”
B. Travelers Is Entitled to Summary Judgment on PHOA’s Breach of Covenant of Good Faith and Fair Dealing Claims
The Utah Supreme Court has held that the implied covenant of good faith and fair dealing “contemplates, at the very least, that the insurer will diligently investigate the facts to enable it to determine whether a claim is valid,, will fairly evaluate the claim, and will thereafter act promptly and reasonably in rejecting or settling the claim.”
It is not certain that Travelers has fulfilled all of its obligations under the Policy. Therefore, Travelers is incorrect that summary judgment should be awarded because it has not breached any express provisions of the Policy.
If there is a “legitimate factual issue as to the validity of [the insured’s contractual] claim,” summary judgment may be granted on a bad faith claim because a genuine factual dispute about the validity of a claim makes that claim' “fairly debatable.”
If the insurer consults with an outside expert and relies on that expert to make its decision, that expert’s involvement “generally provides a good faith basis for an insurer’s defense of a bad faith claim.”
Under the given set of undisputed facts above, PHOA’s claim is “fairly debatable.” That is, Travelers was “entitled to debate it and cannot be held to have breached the implied covenant [because Travelers chose] to do so.”
Moreover, Travelers consulted with an outside expert and relied on that expert to make its decision, which “generally provides a good faith basis for an insurer’s defense of a bad faith claim.”
Accordingly, under the set of undisputed facts outlined above, Travelers did not breach the implied covenant of good faith and fair dealing when it denied the Supplement. That decision may ultimately be determined to be incorrect, or it could be upheld. But it is clear that Travelers is protected under the “fairly debatable” defense in this instance.
ORDER
IT IS HEREBY ORDERED that Travelers Motion
Notes
. Motion for Summary Judgment (“Motion”), docket no. 30, filed October 13, 2015.
. Plaintiffs Response in Opposition to Defendant’s Motion for Summaiy Judgment (“Opposition”), docket no. 37, filed November '20, 2015.
. Fed. R. Civ. P. 56(a).
. Adler v. Wal-Mart Stores, Inc,,
. Id.
. Id. at 670-71.
. Id. at 671.
. The stated facts included in this section ■ have been altered to include only undisputed portions. Therefore, when a footnote states that a fact is "undisputed,” it means that the portion included in this Undisputed Facts section is undisputed, not that the party has admitted the version of the facts written by opposing counsel. Facts are deemed admitted if there is no specific denial or dispute stated in a response to that fact. DUCivR 56-l(c) (requiring party to "specifically controvert” stated facts if in dispute).
PHOA and Travelers each attempt to set forth additional facts in their responses to opposing counsel’s stated facts. See, e.g., Opposition at
. Motion at 12, ¶ 9. Undisputed by PHOA. Opposition at 8, ¶ 9.
. Opposition at 24, ¶ 71. Undisputed by Travelers. Reply Memorandum in Support of Motion for Summary Judgment ("Reply”) at 36, ¶71, docket no. 41, filed December 11, 2015.
. Motion at 12, ¶ 10. Undisputed by PHOA. Opposition at 8, ¶ 10.
. Opposition at 24, ¶ 69. Undisputed by Travelers. Reply at 36, ¶ 69.
. Motion at 8, ¶ 1; Certified Coрy of Policy ("Policy”), Exhibit 2 to Motion, docket no. 30-3, filed October 13, 2015. Undisputed by PHOA, Opposition at 5, ¶ 1.
. Motion at 8, ¶ 2; Policy at ¶ A. Undisputed by PHOA. Opposition at 5, ¶ 2.
. Motion at 9, ¶ 3; Policy at ÍA(4). Undisputed by PHOA "subject to all the terms and conditions of the Policy.” Opposition at 5, ¶ 3. PHOA does not dispute that the Policy contains this language, but denies that the specific loss or damage at issue is "limited or excluded.” Opposition at 5, ¶ 3. This is irrelevant, however, because the stated fact does not mention the specific loss or damage at issue. It is undisputed that the Policy contains this language.
; Motion at 9, ¶ 4; Policy at II B(2)(d)(l)-(2). Undisputed by PHOA "subject to all the terms and conditions of the Policy.” Opposition at 5, ¶ 4. PHOA does not dispute that the Policy contains this language, but denies that the specific loss or damage at issue is “caused by the exclusion.” Opposition at 5, ¶ 4. This is irrelevant, however, because the slated fact does not mention the specific loss or damage at issue. It is undisputed that the Policy contains this language.
. Motion at 9, ¶ 5; Policy at 1iB(2)(f). Undisputed by PHOA "subject to all the terms and conditions of the Policy.” Opposition at 6, ¶ 5. PHOA does not dispute that the Policy contаins this language, but denies that the specific loss or damage at issue is "caused by the exclusion.” Opposition at 6, ¶ 5. This is irrelevant, however, because the stated fact does not mention the specific loss or damage at issue. It is undisputed that the Policy contains this language.
. Motion at 9-10, ¶ 6; Policy, at B(3). Undisputed by PHOA "subject to all the .terms and ..conditions of the Policy,” Opposition at 6, ¶ 6. PHOA does not dispute that the . Policy contains this language, but denies that the specific loss or damage at issue is "caused by the exclusion.” Opposition at-6, ¶ 6. This4s irrelevant, however, because the stated fact does not mention the specific loss or damage at issue. It is undisputed that the Policy contains this language. '
. Motion at 10-11, ¶ 7; Policy at ¶¶ A(6)(k)(l)(c) and A(6)(k)(6). Undisputed by PHOA "subject to all the terms and conditions of the Policy.” Opposition at 7, ¶ 7.
. Motion at 11, ¶.8; Policy at ¶ E(3)(a)(6) and (9). Undisputed by PHOA "subject to all the terms and conditions of the Policy.” Opposition at 8, ¶ 8.
. Opposition at 23, ¶ 66. Undisputed by Travelers "[s]ubject to the exclusions identified in Travelers' Motion[.]” Reply at 35, ¶ 66.
. Opposition at 24, ¶ 67. Undisputed by ' Travelers. Reply at 35, ¶ 67.
. Opposition at .24, 1168, Undisputed by Travelers. Reply at 35, ¶ 68.
. Motion at 12, ¶ 11. Undisputed by PHOA. Opposition at 8, ¶ 11.
. Motion at 12, ¶ 12. Undisputed by PHOA. Opposition at 8, ¶ 12.
. Motion at 12, ¶ 13. Undisputed by PHOA, Opposition at 9, ¶ 13.'
.Motion at 12-13, ¶ 14; Undisputed by PHOA, Opposition at 9, ¶ 14.
. Motion at 13, ¶ 15. Undisputed by PHOA. Opposition at 9, ¶ 15.
. Motion at 13, ¶ 16. Undisputed by PHOA. Opposition at 9, ¶ 16.
. Motion at 13, ¶ 17. Undisputed by PHOA. Opposition at 9, ¶ 17.
. Motion at 13, ¶ 18. Undisputed by PHOA. Opposition at 10, ¶ 18. See also Opposition at 24, ¶ 74. Undisputed by Travelers. Reply at 36, ¶ 74.
.Opposition at 25, ¶ 80. Undisputed by Travelers, Reply at 39, ¶ 80.
. Opposition at 25, ¶ 81. Undisputed by Travelers. Reply at 39, ¶ 81.
. Motion at 13, ¶ 19. Undisputed by PHOA. Opposition at 10, ¶ 19.
. Opposition at 24, ¶ 75. Undisputed by Travelers. Reply at 37, ¶ 75.
. Opposition at 24, ¶ 70. Undisputed by Travelers. Reply at 36, ¶ 70.
. Opposition at 24, ¶ 76. Undisputed by Travelers. Reply at 37, ¶ 76.
. Opposition at 24, ¶ 77. Undisputed by Travelers. Reply at 37, ¶ 77.
. Opposition at 24-25, ¶ 78. Undisputed by Travelers, Reply at 38, ¶ 78.
. Motion at 13, ¶ 20. PHOA does not dispute that the inspection proceeded, but denies that Mr. Tiernan inspected on March 2, 2012. Opposition at 10, ¶ 20.
. PHOA Board Meeting Minutes of March 1, 2012 at 1, Exhibit 8 to Motion, docket no. 30-9, filed October 13, 2015.
. PHOA Board Meeting Minutes of March 1, 2012 at 1, Exhibit 8 to Motion, docket no. 30-.9, filed October 13, 2015 (parenthesis omitted). PHOA does not dispute that the minutes contain the foregoing statement, but argues that the minutes were “unapproved.” Opposition at 10, ¶ 21. PHOA is incorrect. The Minutes of the March 1 Board Meeting were approved by the Board on March 14,. 2014. See Regular Board Meeting Minutes, Exhibit '2 to Reply, docket no. 41-2, filed Decémber 11,2014.
.Motion at 14, ¶ 21. Undisputed by PHOA. Opposition at 10, ¶ 21.
. Motion at 14, ¶ 22; Oakes Depo. at 60:10-22, Exhibit 7 to Motion, docket no. 30-8, filed October 13, 2015. Undisputed by PHOA. Opposition at 11, ¶ 22.
. Motion at 14, ¶ 23. Undisputed by PHOA. Opposition at 11, ¶ 23.
. Motion at 14, ¶ 24. Undisputed by PHOA. Opposition at 11, ¶ 24.
. Motion at 14, ¶25. Undisputed, by PHOA. Opposition at 11, ¶ 25.
. Motion at 14, If 26, Undisputed by PHOA. Opposition at 12, ¶ 26.
. Motion at 15, ¶ 29. Undisputed by PHOA. Opposition at 12, ¶ 29.
. Motion at 15-16, ¶ 30. Undisputed by PHOA. Opposition at 13, ¶ 30.
. Mption at 16, ¶ 32. Undisputed by PHOA. Opposition at 13, ¶ 32.
. Opposition at 13-14, ¶33. Undisputed by Travelers. Reply at 21, ¶ 33.
. Motion at 16, ¶ 34. Undisputed by PHOA. Opposition at 14, ¶ 34.
. Motion at 18, ¶ 37. Undisputed by PHOA. Opposition at 16, ¶ 37.
. Motion at 21, ¶ 52. Undisputed by PHOA. Opposition at 19, ¶ 52
. Opposition at 26, ¶ 83. Undisputed by Travelers. Reply at 40, ¶ 83.
. Opposition at 25, ¶ 82. Undisputed by Travelers. Reply at 39, ¶ 82.
. Motion at 16-17, ¶ 35 (emphasis added by Travelers). Quoted portion undisputed by PHOA. Opposition at 15, ¶ 35.
. Motion at 17-18, ¶ 36. Undisputed by PHOA, Opposition at 16, ¶ 36.
. Opposition at 26, ¶ 84. Undisputed by Travelers, Reply at 40, ¶ 84.
. Opposition at 26, ¶ 85. Undisputed by Travelers. Reply at 41, ¶ 85.
. Opposition at 26, ¶ 86, Undisputed by Travelers. Reply at 41, ¶ 86.
.Opposition at 26, ¶ 87. Undisputed by Travelers. Reply at 41, ¶ 87.
.Opposition at 26, ¶ 88. Undisputed by Travelers. Reply at 41, ¶ 88.
.Opposition at 26, ¶ 89. Travelers, Reply at 41, ¶ 89, Undisputed by
.Motion at 18, ¶ 39, n. 47. Undisputed by PHOA. Opposition at 16, ¶ 39.
. Opposition at 26, ¶ 92. Undisputed by Travelers. Reply at 42, ¶ 92.
. Opposition at 26, ¶ 91, Undisputed by Travelers. Reply at 42, ¶ 91.
. Motion at 18, ¶ 40. Undisputed by PHOA. Opposition at 17, ¶ 40.
. Motion at 19, ¶41. Undisputed by PHOA. Opposition at 17, ¶ 41.
. Opposition at 27, ¶ 95. Undisputed by Travelers. Reply at 42, ¶ 95.
. Opposition at 26, ¶ 93. Undisputed by Travelers. Reply at 42, ¶ 93.
. Opposition at 27, ¶ 94. Undisputed by Travelers. Reply at 42, ¶ 94.
. Opposition at 27, ¶ 98, Undisputed by Travelers. Reply at 43, ¶ 98.
. Motion at 19, ¶ 42. Undisputed by PHOA. Opposition at 17, ¶ 42.
. Motion at 19, ¶43. Undisputed by PHOA. Opposition at 17, ¶ 43.
. Opposition at 26, ¶ 90. Undisputed by Travelers. Reply at 42, ¶ 90.
. Motion at 20, ¶ 44. Undisputed by PHOA. Opposition at 18, ¶ 44.
. Motion at 20, ¶45. Undisputed by PHOA. Opposition at 18, ¶ 45.
. Opposition at 27, ¶ 96. Undisputed by Travelers. Reply at 43, ¶ 96.
. Motion at 21, ¶ 51. Undisputed by PHOA. Opposition at 19, ¶ 51.
. Motion at 21, ¶ 53. Undisputed by PHOA. Opposition at 19, ¶ 53.
. Motion at 21, ¶ 54, PHOA disagrees with Mr, Tiernan, but does not dispute that Mr. Tiernan cаme to this conclusion. Opposition at 20, ¶ 54. It is an undisputed fact that Mr. Tiernan concluded that the additional charges did not represent reasonable and necessary costs that were related to the Windstorm. Opposition at 20, ¶ 54.
. Motion at 21, ¶ 55. PHOA disagrees with Mr. Tiernan, but does not dispute that Mr. Tiernan made this statement. Opposition at 20, ¶ 55, Therefore, it. is an undisputed fact that Mr. Tiernan made this statement.
. Motion at 21-22, ¶ 56. PHOA disagrees with Mr. Tiernan, but does not dispute that Mr. Tiernan made this statement. Opposition at 20, ¶ 56. Therefore, it is an undisputed fact that Mr. Tiernan made this statement. ‘ '
. .Motion at 22, ¶ 57. Undisputed by PHOA. Opposition at 21, ¶ 57.
. . Motion at 22, ¶ 58, PHOA disagrees with Mr. Tiernan, but does not . dispute that Mr. Tiernan made this statement. Opposition at 21, ¶ 58. Therefore, it is an undisputed fact that Mr. Tiernan made this statement.
. Motion at 23, ¶ 59. Undisputed by PHOA. Opposition at 21, ¶ 59. See also Opposition at 27, ¶ 99. Undisputed by Travelers. Reply at 43, ¶ 99.
. Motion at 23, ¶ 60. Undisputed by PHOA. Opposition at 22, ¶ 60.
. Motion at 23, ¶ 61. Undisputed by PHOA. Opposition at 22, ¶ 61.
. Motion at 23, ¶ 62. Undisputed by PHOA. Opposition at 22, ¶ 62.
. Opposition. at 24, ¶ 73. Undisputed by Travelers. Reply at 36,-¶ 73.
. Motion at 15, ¶ 27. Disputed by PHOA. ■Opposition at 12, ¶ 27, Travelers argues that PHOA never indicated to Travelers that there was any issue with the "agreement'' that was made. Reply at 17-18, ¶ 27.
. Motion at 15, ¶ 28. Disputed by PHOA. Opposition at 12, ¶ 28. Travelers argues that PHOA never indicated to Travelers that there was any issue with the "agreement” that was made. Reply at 18, ¶ 28.
. Motion at 16, ¶ 31. Disputed by PHOA. Opposition at 13, ¶ 31 ("Deny that there was a mutually agreed upon scope of repairs.”). Travelers argues any disagreement was never communicated to Travelers. Reply at 20, ¶ 31.
. Motion at 16, ¶ 33. Disputed by PHOA.. Opposition at 13-14, ¶ 33 ("Deny. Admit that Mr. Lewis wrote an email dated -May 14, 2012, attaching a repair estifnate from HWC. Further, the email states that "[w]e believe the necessary repairs, to restore the property to its pre-loss condition as owed by the policy of insurance, can be completed for $1,357,535.92.”)
. Motion at 18, ¶38. Disputed by PHOA. Opposition at 16, ¶ 38.
. Motion at 20, ¶ 46. Disputed by PHOA. Opposition at 18, ¶46 ("Plaintiff objects to paragraph 46, as such is not a factual asser
. Motion at 20, ¶ 47. Disputed by PHOA. Opposition at 18, ¶ 47 ("Deny. The WA Report explains that the underlayment on low slope roofs is required by manufacturer specifications and code.”).
. Motion at 20, ¶ 48. Disputed by PHOA. Opposition at 18, ¶48 ("Deny. The WAS Report explains that the damaged wood decking violated manufacturer specifications, and damaged sheathing discovered during demolition is to be replaced with the installation of new materials.”).
. Motion at 20, ¶ 49. Disputed by PHOA. Opposition at 19, ¶ 49 ("Deny.").
. Motion at 20, ¶ 50. Disputed by PHOA. Opposition at 19, ¶ 50 ("Deny. The WA Report explains that the flashing is required by manufacturer specifications, among other reasons.").
. Opposition at 25, ¶ 79. Travelers denies that HWC/PHOA "explicitly maintained that position when the Agreed Scope was arrived at and distributed ” Reply at 38 ¶ 79
. Opposition at 27, ¶ 97. Disputed by Travelers. Reply at 43, ¶ 97 ("Travelers objects to PHOA's” additional statement of fact because it is not supported by the cited testimony from Mr. Lewis).
. First Amended Complaint at 3, 4, attached as exhibit to Notice of Remоval, docket no. 3, filed May 8, 2014.
. Motion at 2-3 (“Because Travelers has paid what was actually owed for covered damage caused by the windstorm and relied on an outside expert to guide its decision, it is entitled to summary judgment on Plaintiff’s claims for breach of contract and bad faith.”).
. Bair v. Axiom Design, L.L.C.,
. Motion at 26 (some capitalization omitted).
. Id. at 27 (some capitalization omitted).
. Id. at 26 (citing Policy, ¶£(3)^)(6) and (9), pp. TRAV000082-83).
. Motion at 26.
. Id. at 26-27.
. Cardella v. Mountain Reservations, Inc., No. 2:07-cv-01003-BCW,
. -Id. at *1.
. Id. at *15 (quoting Aquagen Int'l Inc. v. Calrae Trust,
. Opposition at 26, ¶ 85. Undisputed by Travelers. Reply at 41, ¶ 85.
. Motion at 11, ¶ 8; Policy at HE(3)(a)(6) and (9).
. Motion-at 11, ¶ 8; Policy at ¶ E(3)(a)(6) and (9). ■ •
. Motion at 15, ¶ 27. Disputed by PHOA. Opposition at 12, ¶ 27. Travelers argues that PHOA never indicated to Travelers that there was any issue with the "agreement” that was made. Reply at 17-18, ¶ 27. ■
. Motion at 27. ’
. Id. at 15, ¶ 27. Disputed by PHOA. Opposition at 12, ¶ 27. Travelers argues that PHOA never indicated to Travelers that there was any issue with the "agreement” that was made. Reply at 17-18, ¶ 27.
. See, e.g., Motion at 22, ¶ 58. PHOA disagrees with Mr. -Tiernan, but does not dispute that Mr. Tiernan made this statement. Opposition at 2 T, ¶ 58; Opposition at 33 (citing Joe Hoffman Expert Report, Exhibit 16 to Motion, docket no. 30-17, filed October 13, 2015).
. Opposition at 21, ¶ 58. PHOA disagrees with Mr. Tiernan, but does not dispute that Mr. Tiernan made this statement. Opposition at 33 (citing Joe Hoffman Expert Report at 1,
. Reply at 42, ¶ 94.
. Motion at 33 (some capitalization omitted)
. Id. at 14, ¶ 26. Undisputed by PHOA. Opposition at 12, ¶ 26.
. Opposition at 34.
. Id. at 35.
. Id.
. PHOA does not dispute that the Policy limits Travelers’ liability for code repairs at $25,000 for "each described premises.” Motion at 33-34 (citing Policy, A(6)(k)(6) ("The most we will pay for [additional repairs required by enforcement of law and ordinance] in any one occurrence is $25,000 at each described premises.”). To thfe extent any repairs or replacement was required by code, Travelers’ liability is capped at $25,000 for "each described premises.”
. Beck v. Farmers Ins. Exch.,
. Brehany v. Nordstrom, Inc.,
. Craner v. Northwestern Mut. Life Ins. Co.,
. Beck,
. See Reply at 52.
. Billings v. Union Bankers Ins. Co.,
. Jones v. Farmers Ins. Exch.,
. Billings,
. Reply at 3; Jones,
. Jones,
. Id. at 305 (internal quotation marks and citation omitted, alterations in original).
. Callioux v. Progressive Ins. Co.,
. Prince v. Bear River Mut. Ins. Co.,
. Billings,
. Jones,
. Callioux,
. Motion at 21 ¶ 51. Undisputed by PHOA. Opposition at 19 ¶ 51.
. Prince,
. Motion for Summary Judgment ("Motion”), docket no. 30, filed October 13, 2015.