Petrie v. Haddock

384 Pa. 7 | Pa. | 1956

Opinion by

Mr. Justice Jones,

In this case a draft of a proposed agreement for the leasing of coal lands with certain surface rights for a stripping operation was submitted to the prospective contracting parties. Following a description of the properties, the writing contained eleven consecutively numbered paragraphs of terms and conditions. Paragraph 9 provided that “No modification, alteration, waiver or addition to this agreement or any part thereof, shall be valid or binding or be set up or relied upon by either party unless the same is in writing and signed by Haddock and Petrie. No evidence of any such modifications, alterations, waiver or addition shall be received in any controversy arising out of this agreement, unless it is in writing and signed as aforesaid.”

*9The agreement, as drawn, was not acceptable to tbe lessors because of tbe limitation, under tbe terms and conditions of paragraph 2, placed upon tbe lessee’s responsibility for tbe filling in of excavations with tbe waste and spoil from tbe coal stripping. Tbe lessors were unwilling to enter into an agreement, and so stated, unless it provided that, after tbe coal bad been removed from tbe tracts of ground by tbe stripping method, tbe lessor would “back fill all of tbe excavations, restoring tbe land as near as possible to its present contour.” This condition was assented to by tbe lessee subject, however, to tbe addition of a further clause that tbe provision last above-quoted “does not mean that [tbe lessee] shall bring on to tbe property new ground.” This qualification was satisfactory to tbe lessors and a new paragraph 2 was drafted with an introduction that “Tbe following paragraph is substituted for paragraph 2 of the original agreement.” A presently immaterial clause (c) was also included as an addition to paragraph 7 of tbe contract. A copy of tbe additional writing, titled “Addenda”, was then attached to tbe original draft agreement in triplicate following tbe place provided for tbe signatures of the contracting parties. That was done with tbe assent and approval of all parties who thereupon formally executed tbe contract, as so amended, by signing it at tbe place provided in tbe original draft for tbe signatures of tbe parties.

After tbe lessee removed all of tbe coal, tbe lessors sued to recover damages for tbe lessee’s alleged failure to back fill the excavations made in tbe stripping operation so as to restore tbe land as nearly as possible to its original contour. At trial, tbe plaintiffs offered, and tbe learned trial judge admitted over tbe defendant’s objection, testimony supporting tbe plaintiffs’ complaint. Tbe defendant’s objection to tbe proffered *10evidence was that paragraph 9 of the contract, which appeared above the signatures of the parties, by its terms excluded any reference to the substitute paragraph 2 because the latter was unsigned by the parties. The jury returned a money verdict for the plaintiffs upon which the court below entered judgment after refusing the defendant’s motions for a new trial and judgment n.o.v. The defendant appealed and assigns here for error the trial court’s admission of the testimony as to the defendant’s failure to comply with the condition of substitute paragraph 2 as to back-filling excavations so as to restore the land as nearly as possible to its original contour.

The action of the learned trial judge was proper. A party’s signature to a contract is designed to evidence his intention to be bound thereby. There is no requirement that a contract be signed at any particular place so long as the signatories attest the meeting of their minds on the basis of the agreed-upon writings and their intention to be obligated accordingly. What the parties to the contract in suit agreed upon before they signed it was that the attached written paragraph 2 was a substitute for paragraph 2 as contained in the original draft. In short, the substitute paragraph 2 was neither a modification, alteration, waiver nor addition to the agreement but was an integral part of the proposed contract at the time the parties executed it. In such event, a party to a contract may show by parol that an added, although unsigned, written provision was an intended constituent part of the agreement between the parties at the time they appended their signatures to the contract. The ruling in Cox v. Burdett, 23 Pa. Superior Ct. 346, 348-350, is directly in point.

In the Cox case, supra, the plaintiffs sued in replevin on a contract that had originally been drawn *11as a bailment of a mill. The defendants alleged, however, that a part of the contract was an agreement by the plaintiffs to “ ‘furnish sufficient (timber to keep the mill in constant operation and . . . not to permit the mill to remain idle for more than twenty days at a time’ ” and that this condition was written at the time the original agreement was made, before signing, and was assented to by all the parties, but that their signatures to the contract were placed above the written addition because the place for the signatures had been arranged before the new provision was added. The Superior Court said that the defendants’ offer to prove default by the plaintiffs in furnishing timber for the mill “was not an offer to contradict or change in any way a written agreement by parol. It was simply an effort to prove that the addition was part of the original agreement and, notwithstanding the fact that the signatures were above it, that it was as much a part of the agreement as though it was above the signatures.”

The extended and convincing review of the evidence in the instant case by Judge Thompson in the opinion for the court below renders unnecessary our entering upon a consideration of the sufficiency of the testimony adduced by the plaintiffs to support their allegations respecting the timely adoption of the substituted paragraph 2 of the contract. It is beyond dispute, indeed it is conceded by the defendant, that substitute paragraph 2 was an intended part of the original contract by agreement of the parties prior to their signing the contract. All that the appellant argues is that the parties failed to effectuate substitute paragraph 2 as a part of the contract when they neglected to sign the attached writing.

Judgment affirmed.