Peterson v. Granger Irrigation District

243 P. 847 | Wash. | 1926

The appellant secured from the respondents a deed for a right of way for a pipe line across respondents' land, accompanied by an agreement, wherein it was provided that, in the event the parties could not agree upon the amount of damage occasioned by the construction of the pipe line, that amount was to be determined in this way:

"If the parties hereto shall fail to agree upon the amount of said damage within thirty days after the completion of the construction of said pipe line, then *669 the parties hereto agree that the differences shall be submitted to a board of appraisers, one to be selected by each of the parties hereto, and the third by the two thus selected, who shall appraise any and all damages resulting to the property or improvements thereon by virtue of the construction of said pipe line, exclusive of the actual value of the land occupied by the pipe, and the parties hereto agree to be bound by such appraisement, and the district shall, within thirty days after said appraisement, pay the amount thereof to the parties of the second part."

The respondents' suit was brought to recover the damages which, they allege, were caused them by the pipe line construction, and the complaint alleges that more than thirty days have elapsed since the completion of the work, and the damages have not been paid. The answer admits the making of the contract and sets up that an appraisal had been made according to its terms and the amount of respondents' damages fixed, and that the respondents had refused to accept that amount. In the reply the appointment of appraisers was admitted, but it was alleged that they had performed their services under a misapprehension and misunderstanding of their rights, and had taken into consideration improper elements, thus having proceeded upon a fundamentally wrong basis, and that the award was inadequate. Upon the trial, judgment was entered for the respondents for an amount more than twice that fixed by the appraisers. This appeal raises three assignments of error.

[1] It is the first contention of the appellant that the contract provides for arbitration, and that, the matter in dispute having been submitted to arbitration and the award having been made, the statute (§§ 420-430, Rem. Comp. Stat.) affords the only method by which the court may review the question. If what was called for by the contract is what is known to the law *670 as arbitration, the appellant's contention would have to be sustained. But the contract is not one calling for arbitration, but one calling for appraisement. That there is a distinction between these two methods of determining controversies, or elements connected with controversies, has been recognized by this court, after a thorough consideration of the question, inMartin v. Vansant, 99 Wn. 106, 168 P. 990, Ann. Cas. 1918D 1147. The rule was there announced that there exists in this state, in addition to the statutory arbitration, the common law appraisal. Criticism of the Martin case is made by the appellant, and it is suggested that it has been overruled, because not noticed by this court in subsequent opinions dealing with arbitration, attention especially being called toMitsubishi Goshi Kaisha v. Carstens Packing Co., 116 Wn. 630,200 P. 327, Hatch v. Cole, 128 Wn. 107, 222 P. 463, andJackson v. Walla Walla, 130 Wn. 96, 226 P. 487. Those cases, however, it will be seen upon examination, do not deal with the question of whether the agreements were for arbitration or for appraisal. They were cases not dealing with appraisement, but with arbitration, and therefore it was not necessary that the question under consideration in the Martin case be discussed; and the distinction drawn in that case is a still continuing one.

It was, therefore, unnecessary for the statutory procedure outlined in cases of arbitration to be followed here, and the respondents were justified in proceeding to sue for their damages, irrespective of the result of the appraisers, and, their conclusions having been arrived at on a fundamentally wrong basis, the superior court was correct in ignoring the award and proceeding to determine, from the evidence presented to it, the amount of damages to which the respondents were entitled under the contract. *671 [2] The next assignment of error is that there has been a departure between the complaint and the reply, and that on that account the motion of the appellant to dismiss should have been granted. It is urged that the complaint negatives the fact of an appraisement, and that the reply admits the appointment of appraisers and the decision made by them, and alleges that the appraisers acted under a misapprehension and upon a fundamentally wrong basis, which constituted a fraud, and that the award was grossly inadequate. We cannot take the view of these pleadings which is held by the appellant. The allegations contained in them are not at variance and do not constitute a departure. The theory upon which the case was brought continues throughout the complaint and the reply, and the subsequent pleading is fully justified by § 277, Rem. Comp. Stat. There is nothing inconsistent between the allegations in the reply and those contained in the complaint. Henry v. Bruhn Henry, 110 Wn. 321,188 P. 506; McCorkle v. Mallory, 30 Wn. 632,71 P. 186; Erickson v. McLellan Co., 46 Wn. 661, 91 P. 249;Duncan v. Parker, 81 Wn. 340, 142 P. 657, L.R.A. 1915A 804.

[3] The last assignment of error urged by the appellant is that the amount of damages awarded by the trial court to the respondents is too great. Without any extended review of the testimony in regard to the amount of earth necessary to be removed and the other minor items of damage, it will suffice to say that the amount awarded by the court is well within the evidence submitted for its consideration, and we find that there is no reason for disturbing the court's judgment in this regard.

Judgment affirmed.

TOLMAN, C.J., PARKER, MAIN, and MITCHELL, JJ., concur. *672

midpage