Lead Opinion
The defendants Halligan appeal from a judgment of the district court foreclosing a mechanic’s lien for labor and materials in the sum of $1,576.82 furnished in the construction of a basement on defendants’ property.
In his petition plaintiff alleges that he was employed to construct and furnish the material for a basement on the defendants’ premises and that the fair and reasonable value of the labor and material charges was in the sum of $1,576.82. Defendants, in an answer and cross-petition, allege that the plaintiff did perform work and labor on their premises under an oral contract; that the plaintiff entered into an oral contract with the defendants to construct a basement and a frame addition to the trailer home of the defendants for the agreed sum of $2,850; that thereafter the plaintiff did construct the basement; that it was defectively constructed by reason of the failure of the plaintiff to properly seal and
Outside, the question of defective workmanship in the construction of the basement, the basic question involved in this case is whether the parties entered into a contract for an agreed price for the, construction of a basement and the trailer house addition. In approaching this problem, we bear in mind th'e basic rule that a fundamental and indispensable basis of any enforceablei agreement is that there be a meeting of the minds of the parties as to the essential terms and conditions of the proposed contract. Voss v. Linn,
Peters testified he told the Halligans, with reference to the construction of the addition, that he did not know actually when he could do it; that he could not give them any possible date; that at all times in his conversation with them he stressed there was no way he could give an exact figure because he did not know exactly what they had in mind; that he did not know what he might run into; that he had never done anything like that before; and that the cost of an ordinary basement was at least $1,000 for the blocks and laying.
It appears from the plaintiff’s evidence that he did not do any plumbing or electrical work and, in the preliminary negotiations, there was no discussion as to the electrical work or the plumbing other than hooking up a temporary toilet drain in the trailer prior to the time of the construction of the addition. The testimony is that the, defendants were securing an F.H.A. loan to finance the basement and the addition. Peters testified that in giving the Halligans a figure of $1,800 on the addition and a figure of $1,000 on the basement these
Defendant Halligan’s testimony varies considerably from the plaintiff’s testimony. He testified that when Peters came out to discuss the addition they discussed “what ideas we had as far as the addition to the kitchen.” He says they discussed the size of the addition, the, construction and size of the basement, the floor covering, the details of the walls, the building of the walls out 12 fee,t from the trailer, the exterior to be aluminum covered, the interior to be of wood paneling, the ceiling, the placement of the stairway, the building of cabinets and their location, the installation of insulation and aluminum windows, the moving of the, sink, and the electrical outlets around the top of the counters. They made a trip to the basement site where they discussed the details of the, construction and Halligan advised Peters about the spring and asked him about a water problem in the basement. He says that the plaintiff was taking notes in a small notebook during this period of time and after these conversations Peters left and returned and told defendant Halligan that it would cost $1,850 to build the kitchen. He had previously given him a figure of $1,000 on the basement. Halligan told him that he needed these, figures for the F.H.A. in order to get a loan. He does not testify that they had a specific conversation or agreement that this would be the contract price. That inference must be drawn from the following testimony on the párt of Halligan: “When
We observe that no explanation appears as to why the defendant Halligan’s wife did not testify in this case and corroborate his testimony. We observe further that Peters’ repeated and precise testimony that the figures he furnished the Halligans were only estimates and the reasons he gave therefor stand undenied in the, record by Halligan.
The basement was finished about October 25, 1965. In November or December 1965, defendants received a partial bill for $1,356 and a final one for $1,586.31. In their conversations Peters demanded payment and we observe that Halligan did not object to the amount or assert that the contract was for $1,000 but merely stated to the plaintiff that he had not finished cleaning up the material at the site of the excavation. In a conversation in the first part of November 1965, Halligan told the, plaintiff that he was planning on him constructing the addition and was wondering when he could start it. Halligan not only made no objections to the bill rendered him for the cost of materials and labor but we could reasonably infer that he intended to proceed on the same basis of payment with reference to the addition when he inquired of the plaintiff and insisted that the plaintiff begin work on the addition. We are further aided in the determination of this issue by the rule that where there is irreconcilable conflict on a material issue, this court will, in determining the weight of the evidence of witnesses who appear in court to testify, consider the, fact that the trial court observed them and their manner of testifying and must have accepted one version of the facts rather than the other. Uptegrove v. Elsasser,
The defendants strongly contend, nevertheless, after the basement was done, that the plaintiff Peters refused to perform the contract for the building of the trailer addition; that he, gave no excuse for his action except that he would not and could not do it; that therefore he abandoned the contract; and that he is not entitled to recover on a quantum meruit basis for the reasonable cost and charge, of the labor and materials furnished. There is no question, under the evidence, that in November 1965 the plaintiff informed the defendants that he could not construct the addition. Accepting defendants’ own testimony in this respect, Halligan testified that the plaintiff told him that he had a man hired who he was going to send out to complete the addition on the trailer house but Halligan told him, “Well, if you are not going to complete the job, I will do my own hiring, as far as completing it.” The evidence shows that the, defendants did hire a contractor by the name of Hopken to construct the trailer addition on a labor and material basis at a total cost of $4,580.84 which represented the fair and reasonable cost therefor. Assuming, therefore, that the plaintiff did contract to build the trailer addition and that his failure and refusal to construct it constituted a lack of substantial performance, the question arises as to whether this action forfeits the plaintiff’s right to establish a mechanic’s lien fqr the reasonable value of his services performed and the labor and material furnished. Our mechanic’s lien statute provides as follows: “Any person who shall perform any labor or furnish any material, * * * for the construction, erection, improvement, repair, * * * of any house, * * * building, or appurtenance, * * * by virtue of a contract or agreement, expressed or implied, with the, owner
. Our mechanic’s lien statutes are cumulative and remedial in nature, and require a liberal construction so as to effectuate their objects and purposes, and they find their basis in the equitable principle that everyone who, by his labor and materials, contributes to the, preservation or enhancement of the property of another, thereby acquires a right to compensation. Muenchau v. Swarts,
We feel that the conclusion we come to follows the language and the purpose, of the statute and the holding that if the furnishing of material and labor under a contract is sufficient to create an indebtedness or liability, it is sufficient to create a lien under the provisions of the statute. Rosebud Lumber & Coal Co. v. Holms,
We further note that there were two distinct parts to this contract, one for the construction of the basement and one for the trailer addition. The parties considered them separately, both during their negotiations and during the conversations that followed the construction of the basement. The general rule is that a party who has failed fully to perform his contract cannot recover on the contract for part performance applies only to entire indivisible, and not to severable, contracts; and there may be a recovery on the contract for a part performance of a divisible contract. 17 Am. Jur. 2d, Contracts, § 386, p. 831. We therefore hold that the plaintiff is entitled to recover on a quantum meruit basis for the reasonable cost and charge of labor and materials furnished in the construction of the defendants’ basement and that the defendants’ rights are fully protected because they may, and have, set up a breach of the contract as a basis for the claim of damages.
The only remaining question is whether the defendants are entitled to recover on their counterclaim for the breach of the contract. Defendants in their brief do not contend that they are entitled to any net affirma
Affirmed as modified.
Concurrence Opinion
concurring.
We concur in the decision of the, court that the judgment of the district court as modified should be affirmed upon the ground that the contract between the parties was severable and the record will support a finding of substantial performance of the contract to construct the basement.
We do not agree that a party may recover on a quantum meruit basis for partial performance for the value of benefits conferred even though he abandons the contract or refuses to perform it, subject to any counterclaim for damages that the other party has sustained by reason of the breach of the agreement. Generally, substantial performance is a condition precedent to any recovery where there is an express contract between the parties. See, Rickertsen v. Carskadon,
Recovery upon a quantum meruit basis where there has been no substantial performance should be limited to the circumstances specified in Restatement, Contracts, § 357, p. 623.
