The suit, brought by “Newell,” an electrical subcontractor on a government contract, against “Perry,” the general contractor, was to recover $4479.86 held bade to cover outside electrical work, that is, poles, connecting wires, etc. which Newell claimed was not, and Perry claimed was, included in Newell’s subcontract. Tried to the court without a jury, there were findings and a judgment in favor of Newell, the subcontractor, and Perry has appealed.
The facts are simple. They came in without dispute. Perry agreed to furnish the material and equipment for, and perform the labor to construct and complete, motor repair shops for Fourth Echelon repairs, “including the utilities thereto” at
The district judge, in finding for Newell, found both that the outside electrical work was not included in Perry’s contract and that if it was, Newell had not agreed to do it but had expressly limited his bid and contract to electrical work in the buildings. Perry is here contesting both of these findings as erroneous on the ground that as to him the contract made the finding of the Constructing Quartermaster, that his contract did include this work, conclusive on him, and that the subcontract, by making the provisions of the main contract a part of it, bound Newell to the same extent that Perry was bound. Appellant concedes that neither he nor Newell understood that his contract covered outside wiring, and that unless it did in fact cover it, Perry could not by acceding to the Quartermaster’s unwarranted demand impose the obligation for it on Newell. He insists, though, citing many authorities,
We find it unnecessary to determine whether his contract bound Perry, for we agree with appellee that the provisions of the subcontract taken in themselves and especially in the light of the circumstances under which it was entered into and executed, leave in no doubt that its obligations extended only to inside wiring, and the district judge was right in holding that Perry had no right to withhold from Newell the sums sued for. In Hill & Combs v. First National Bank of San Angelo, 5 Cir.,
The judgment was right. It is affirmed.
Notes
This contract, among other things, provides, “Newell Elec. Co. agrees to furnish all labor, materials, fixtures, equipment, etc. necessary to completely install all electrical work and materials for the following buildings to be erected at Camp Shelby, Miss., by the Perry Construction Co. under the supervision of the Constructing Quartermaster”. Then follows: a list of the buildings where the installations are to be made. Other provisions, not .necessary to be set out are these: “All the general and special conditions of the plans and specifications, including instructions to bidders, etc., where applicable to the above mentioned work, are hereby incorporated and made a part of this contract. Newell Elec. Co. is bound under all the provisions including time limits, etc.” and “This contract shall become valid after it is approved by the Constructing Quartermaster. * * *»»
“Interpretation of Contract: * * * the contractor shall furnish all material, labor, etc. necessary to complete the work according to the true intent and meaning of the drawings and specifications, of which intent and meaning the Constructing Quartermaster shall be the interpretor.”
