22 Kan. 716 | Kan. | 1879
On the first day of September, 1875, defendant in error was the owner of lot 27, in block 25, in the city of Parsons, and one Michael Galvin was the owner of the adjoining lot, 26, in the same block, and each of said parties, contemplating erecting a brick store-building on his said lot, entered into an agreement by which the west wall of Conroy’s building should be placed on the line between said lots 27 and 26, to be built by Conroy in the first instance, and one-half of the cost thereof to be paid by Galvin when he completed his building on his lot. Conroy completed the said wall on the 26th of September, 1875, and had his entire building completed on the 1st day of November, 1875. On the 10th of November, 1875, Galvin commenced the erection of the. building on his lot, .26, and continued in and about the erection of the building at irregular intervals, until July 23, 1876, when he ceased to do any work. At that time the outer walls were erected, the dooi’s and window sash were in, the lower floor was laid, but no finishing was done on the sides or top of the r.oom, and no roofing save with sheathing-boards.
At the May term, 1876, of the district court, held in Labette county, Robert Whittaker, Henry Staub, and Patrick Stafford recovered judgments against said Galvin for labor performed and material furnished in the erection of the building on his lot, 26, which judgments were declared a lien on said lot; and at the same time and in the same court, A. A. Smith recovered a judgment against Galvin for $720, and a decree foreclosing a mortgage on said lot 26, subject however to the liens of Whittaker, Sfcaub, and Patrick & Stafford.
On the 12th of August, 1876, plaintiff in error, without any actual notice of the claim of the defendant in error, purchased the said judgment of A. A. Smith, and on that day had the same assigned to him on the judgment record.
On the 16th of August, 1876, the defendant in error filed
On the 19th of August, 1876, said lot 26 was sold by the sheriff under the judgments of Staub and others (rendered .at the May term of the district court), and bid off by plaintiff in error, who did not then have actual knowledge of the claim of defendant in error.
On the 1st of January, 1877, plaintiff in error completed the building on said lot 26, which was after the commencement of this suit in the district court -by defendant in error.
The case was tried in the district court at the May term, 1878; judgment was given for plaintiff (defendant in error), foreclosing his mechanic’s lien on lot 26. The defend ant Perry (plaintiff in error) excepts, and brings the case to this court for review.
The questions of the existence of a mechanic’s lien, and the methods of enforcing one, depend entirely upon the státute. It may be conceded that judgment was properly rendered against Galvin upon the breach of his personal contract to pay for one-half of the wall, and yet such concession in no manner determines the question of the existence of a lien upon the lot on which the half-wall was built. Unless the statute concerning liens was complied with, no lien exists; and if a lien exists, no action will lie, unless brought in the time and manner prescribed by statute.
Now upon the facts as they appear in the findings and by the record, one of two things is clear: either the half-wall was an independent improvement upon lot 26, or it was part and parcel of the building erected on said lot. It is not necessary to determine this question, and perhaps other facts should be found before it could be satisfactorily determined. Prima facie, it was part of the building, yet the intention of Galvin at the time of making this arrangement with Conroy in reference to erecting a building may have been such as to have compelled us to consider this a separate improvement. (Jean v. Wilson, 38 Md. 288.) If the former, then as the improvement was completed by September 26, 1875, and no
The other proposition of counsel is, that inasmuch as Gal
“Galvin commenced to build, and appropriated our wall November 10th, 1875, and continued in the erection and inclosure of the store eight months, to July 23d, and then finally abandoned it. It was then being advertised fpr sale on the 19th of August. It was on that day sold, and Galvin could no further finish it; and-suppose that Perry, the purchaser, wodld not, so that Conroy may have no day ‘ within four months from the absolute completion of the building ’ to file his lien statement: can the purposes of the act be thus thwarted, and Conroy lose the price of the half-wall? Can the owner always by refusing, or, being unable to finish according to the original design, elude or defeat the lien? Is the statute really a mere snare? It seems clear enough that when the owner finally concluded his labor in and about the building, it must be deemed finished and completed by his election within the lien act; that when he gave up the lot and building to public sale, and it was sold, that was an election to consider the building completed, and a completion within the act as to the materialman whose property has been furnished; at least, if the materialman or workman, whose labor is rendered, so elects, it is a completion of the work and building, and the purchaser may use it for what he chooses. The building is sold and bought as completed, and the materialman has no. resort to the purchaser for the price of material in the building, nor can either compel the other to receive or pay for undelivered material. There is no privity between them. The building as to them is completed.”
Notwithstanding, we cannot yield our assent to the proposition, as broadly at least as it is stated, or even so far as will be necessary to support the judgment in this case. It is not within the letter of the statute. That names the completion of the building, and here the building was manifestly incomplete. Grant that the parties solely interested may agree to treat the building as complete: here there was no such
We conclude, therefore, that the action was prematurely brought, and the judgment will be reversed, and the case-remanded with instructions to render judgment for costs on. the findings in favor of the defendant, plaintiff in error.