Opinion
Plaintiff Richard H. Perley appeals from the denial of his petition for a writ of mandate directing respondent Board of Supervisors of Calaveras County (board) to vacate its decisions approving a conditional use permit and a reclamation plan for a proposed mining project of real party Western Source, Inc. (WSI), and to enjoin further action on the project by the county or the developer pending the preparation of an adequate environmental impact report (EIR). Plaintiff contends the board abused its discretion in adopting a “negative declaration” (i.e., a statement that the proposed project would not have a “significant effect” on the environment), rather than requiring an EIR, since there was “serious public controversy” about the environmental impact of the project in question and it could be “fairly argued based on substantial evidence” in the administrative record that it would have a “significant effect.” We affirm the trial court’s denial of the writ of mandate.
Facts
In early 1979, WSI acquired approximately 170 acres of property and control over additional acreage under a reciprocal use agreement for a talc mining operation. Six to seven acres of property would be used in the operation, while the remaining land, which is basically open, hilly grassland, would continue to be devoted to agricultural and ranching uses and would serve as an “environmental buffer zone.” After discussions with the county planning department, WSI applied for a zoning change attaching a surface mining designation to the subject property; the change was approved by the board on October 16, 1979. Subsequently, on November 21, WSI applied for a conditional use permit and submitted a reclamation plan (pursuant to Pub. Resources Code, § 2772).
On January 17, 1980, the planning commission conducted a public hearing on WSI’s application, at which several owners of neighboring property “voiced
After receiving the requested reports on noise, dust and traffic from WSI, the planning department recommended that the use permit be granted, subject to certain conditions which in its opinion answered the environmental concerns covered in the reports, and that a negative declaration accordingly be adopted pursuant to Public Resources Code section 21080, subdivision (c). Nevertheless, after another public hearing on February 21, 1980, the planning commission voted to require the preparation of an EIR on the grounds that “1. [t]he proposed project [might] have a significant effect on the environment, particularly with regards to groundwater, noise, dust, and roads[, and] [¶] 2. [t]here [was] serious public controversy concerning the environmental effects of the project. ” WSI appealed the planning commission’s decision to the board, which held a public hearing on the matter on March 31, 1980. At the conclusion of the hearing, the majority of the board (four to one) found that, despite the concerns of nearby residents regarding increased traffic, noise, dust, and possible groundwater depletion or degradation, “[t]he proposed project ha[d] been revised and amended by the conditions of approval to satisfactorily mitigate any significant impacts upon the environment.” The board therefore adopted a negative declaration regarding the project and approved the application for a use permit and the mine reclamation plan subject to the conditions (except one) proposed by the planning department. 1 The notice of determination was issued April 9, 1980. (Pub. Resources Code, § 21108.)
Discussion
To achieve its objective of protecting the environment by the establishment of administrative procedures that “ [ejnsure that the long-term protection of the environment . . . shall be the guiding criterion in public decisions” (Pub. Resources Code, § 21001, subd. (d)), “CEQA [the California Environmental Quality Act of 1970, Pub. Resources Code, § 21000 et seq.)] and the guidelines issued by the State Resources Agency to implement CEQA [Cal. Admin. Code, tit. 14, § 15000 et seq.] establish a three-tiered structure. If a project falls within a category exempt by administrative regulation (see Pub. Resources Code, §§ 21084, 21085), or ‘it can be seen with certainty that [there is no possibility that] the activity in question [may] have a significant effect on the environment’ (Cal. Admin. Code, tit. 14, § 15060), no further agency evaluation is required. If there is a possibility that the project may have a significant effect, the agency undertakes an initial threshold study (Cal. Admin. Code, tit. 14, § 15080); if that study demonstrates that the project ‘will not have a significant effect,’ the agency may so declare in a brief Negative Declaration. (Cal. Admin. Code, tit. 14, § 15083.) If the project is one ‘which may have a significant effect on the environment,’ an EIR is required. (Pub. Resources Code, §§ 21100, 21151; see Cal. Admin. Code, tit. 14, § 15080.)” (Fn. omitted.)
(No Oil, Inc.
v.
City of Los Angeles
(1974)
In this case, the board determined that the proposed mining operation would not have a significant environmental effect so long as it was conducted in compliance with certain stated conditions. The guidelines provide that in such a
At the outset, plaintiff extends a basic challenge to the propriety of issuing a “mitigated negative declaration” as called for in the foregoing guideline; he characterizes such a negative declaration as an administrative “invention” which is “a clever means for cutting members of the public out of a process designed specifically for their benefit.” While the failure to require an EIR in such a situation may deprive the public of the benefit of some of the information an EIR would disclose and does, in any case, absolve the agency of its critical responsibility to respond meaningfully to public and other agency comments (Cal. Admin. Code, tit. 14, § 15146, subd. (b);
People
v.
County of Kern
(1974)
This does not mean that the concerns voiced by plaintiff regarding public participation in environmental assessments must be ignored. In response to such concerns, courts have stressed that CEQA mandates an EIR “not only when a proposed project
will
have a significant environmental effect, but also when it ‘may’ . . . .”
(Friends of Mammoth
v.
Board of Supervisors
(1972)
In
No Oil, Inc.
v.
City of Los Angeles, supra,
The Supreme Court also noted in No Oil, Inc., “the importance of preparing an EIR in cases ... in which the determination of a project’s environmental effect turns upon the resolution of controverted issues of fact and forms the subject of intense public concern. . . .
“[T]he existence of serious public controversy concerning the environmental effect of a project in itself indicates that preparation of an EIR is desirable.” (Fn. omitted.) (No Oil, Inc. v. City of Los Angeles, supra, 13 Cal.3d at pp.75, 85-86.)
The CEQA guidelines reflect the foregoing rule for agency determinations of whether an EIR should be required:
“(a) If the Lead Agency finds, after an initial study, that the project may have a significant effect on the environment, the Lead Agency must prepare or cause to be prepared an Environmental Impact Report.
“(b) An EIR should be prepared whenever it can be fairly argued on the basis of substantial evidence that the project may have a significant effect on the environment.
“(c) An EIR should be prepared when there is serious public controversy concerning the environmental effects of a project. Controversy not related to an environmental issue does not require the preparation of an EIR.” (Cal. Admin. Code, tit. 14, § 15084.)
Plaintiff posits the existence both of substantial evidence that the mine would have significant adverse effects on the environment and of a serious public controversy concerning such effects. The record belies his claims.
The only
evidence
pointed to by plaintiff in his brief regarding the potential environmental effects of the mining project is admissions by WSI in documents appended to its “Mine Reclamation Plan” that vehicular traffic would increase and noise levels would be “slightly elevated,” that there would be a change in the amount of dust in the vicinity and the mine would alter the contours and character of the area. They also stated therein that the mine was related to “a larger project or series of projects,” which, WSI explained in connection with its use application, referred to its intended construction of a mill at another site. These admissions do not constitute substantial evidence
4
of significant en
Finally, plaintiff argues that an EIR was mandated in light of the “serious public controversy” about the environmental effects of the mining project. (Cal. Admin. Code, tit. 14, § 15084, subd. (c).) That such a controver
The judgment is affirmed.
Puglia, P. J., and Regan, J., concurred.
A petition for a rehearing was denied November 16, 1982, and appellant’s petition for a rehearing by the Supreme Court was denied February 3, 1983. Bird, C. J., was of the opinion that the petition should be granted.
Notes
The conditions imposed by the board were: “ 1. The open pit operation shall be limited to the hours of 7 A.M. to 7 P.M. Monday thru Sunday. Underground activity may operate 24 hours per day consistent with the other conditions.
“2. A water truck shall be kept at project site during all operations and used to water roads on site.
“3. The applicant shall comply with Environmental Protection Agency (EPA) and Mine Safety and Health Administration (MSHA) for dust control.
“4. Noise levels from onsite mining activity shall not exceed 60 dBA from 7 A.M. to 7 P.M., as measured at existing exterior offsite premise residences, except that a level of 75 dBA may be reached for a period not to exceed one minute per occurrence for a total of 5 minutes per hour.
“5. Noise levels from onsite mining activity shall not exceed 55 dBA from 7 P.M. to 7 A.M., as measured at existing exterior offsite premise residences.
“6. No slopes shall exceed 60° in disposal site areas.
“7. The applicant shall do the following:
“a. Prior to the beginning of the use of Redhill Road for hauling ore Western Source Inc. will make and finance necessary modifications as described in Roark Weber’s report of Feb. 3, 1980.
“b. Load fees will be calculated on a quarterly basis. Truck count will be provided by Western Source Inc. based on weight bills.
“c. Should Western Source Inc. in any quarter not haul, there will be no minimum
“d. Prior to initiation of project, the County and applicant shall enter into an agreement for the capital improvements and maintenance of Red Hill Road between Highway 49 and the project site.
“8. The top soil removed from area to be surface mined will be stabilized and revegetated no later than one year from the date of Board of Supervisor approval.
“9. The applicant shall meet the requirements of Regional Water Quality Control Board.
“10. The applicant shall be responsible to insure all vehicles associated with the mining operation shall not exceed a maximum speed of 25 miles per hour on Redhill Road.
“11. No highway vehicles utilized for hauling of material shall be used between 7 P.M. and 7 A.M., onsite or offsite.
“12. All loaded or unloaded vehicles used for hauling material shall exit and enter Redhill Road from Highway 49, not Highway 4.
“13. Any oral or written representations made by the applicant or his agent at the Board of Supervisors hearing shall be incorporated as a condition of this Use Permit.
“14. Construction and operation of said project shall be in substantial conformance with the approved plot plan and application, as amended by these conditions.”
At the time the board acted on the project, section 15080, subdivision (d)(2), provided: “Where a project is revised in response to an Initial Study so that potential adverse effects are mitigated to a point where no significant environmental effects would occur, a Negative Declaration shall be prepared instead of an EIR. If the project would still result in one or more significant effects on the environment after mitigation measures are added to the project, an EIR shall be prepared.”
Effective February 6, 1982, the subdivision has been amended to provide: “A mitigated Negative Declaration shall be prepared instead of an EIR where the significant effects of a project identified in an Initial Study are clearly mitigated to a point where no significant environmental effects would occur. [¶] (A) The mitigation under this section shall be limited to changes in the project resulting from either: [¶] 1. Revisions in the project plans made by the applicant or [¶] 2. An enforceable commitment from the applicant to include the mitigation measures in the project, (¶) (B)Where a mitigated Negative Declaration is approved, the agency shall make a finding that the project as approved will not have a significant effect on the environment.”
We do not identify the precise point at which the project is submitted for approval such as to trigger the determination whether the project is subject to an EIR. That point must occur sufficiently in advance of the final decision by the board to allow public comment on that issue. The procedure by which the decision is reached cannot occur by incremental modifications of the proposal which cumulatively preempt the function of public input required by the EIR procedure.
The parties disagree as to the proper standard of judicial review of an agency determination to adopt a negative declaration. Respondents cite
Pacific Water Conditioning Assn., Inc.
v.
City Council
(1977)
We need not join this conflict in decisional authority. In addition to upholding the board’s action under the Pacific Water Conditioning standard, the trial court “further conclude[d] that there [was] no substantial evidence in the record to support a reversal of the Board’s decision, either under the California Environmental Quality Act or CCP § 1094.5.” We conclude, infra, that plaintiff has furnished us no ground for rejecting this finding.
Plaintiff’s only references to specific comments at the board hearing are made in connection with his argument that an EIR was mandated by the existence of a “serious public controversy” (see discussion, infra). The remarks cited by plaintiff in this regard (see post, fn. 6) express the speakers’ concern and suspicions about possible environmental (and other) effects of the project, but contain no evidence of such effects.
Plaintiff completely ignores evidence adduced in favor of the board’s finding that any potential noise, dust, groundwater and traffic effects were mitigated into insignificance. Concerning noise, there were reports of two consultant firms which indicated that operation of the mine so as not to exceed 60 decibels during the day and 55 at night, as measured outside the nearest residence, would be “clearly acceptable” in a residential area. WSI asserted that dust would not be a problem at the mine, based on a consultant’s observations of a nearby landfill operation, the lack of wind at the project site during the summer (when it might otherwise be a problem), and the lack of any harmful substances in the ankerite talc-schist being removed. Conditions 2 and 3 required maintenance of a water truck for dust control on the site and compliance with applicable dust control regulations, respectively. The Regional Water Quality Board anticipated no water quality problems resulting from the operation, and groundwater was determined by a consultant to be at least 200 feet below the surface, deeper than the proposed surface mine, so no depletion problem should arise. The question was raised whether Red Hill Road, a narrow,
Plaintiff excerpts comments of six individuals (including himself):
1. “...Iam saying to you today, I’m a concerned citizen of the area, as I have looked under the project I’ve found a lot, if not distortions, incomplete truths, the trucking traffic being as such.”
2. “[T]he [p]lanning commission did [a lot],of [thorough] work on what they did and what they recommended and I am hopeful you will uphold their decision [to require an EIR].”
3. (Plaintiff) “. . .1 would try to establish in my own mind and for others, how you could [evaluate] the effect of the mine going in and I would prepare a report of which you folks have copies, . . . [I]f the activity adds to the area, I’d give it a plus one. If it doesn’t affect the area, I’ll give it a zero. If its bad on the area, I’ll give it a minus one .... And when I add all the numbers up I come up with a horrifying large negative number.”
4. “I’d like to know what [the project’s] going to do with my drinking water. I abandoned my well because it wasn’t sufficient and now what am I going to do with the other water when it gets polluted? I [thank] you for your time, and again I’d like to ask for an EIR.”
5. “We have lived in the County most of our life, we purchased this beautiful property four years ago and built our home. So I feel that any new mining company coming in this County who feels operation can run anywhere from 25-40 years, it is real important and only fair to the immediate property owners and the residents of the county for a full formal EIR study to be done by an unbiased] party.”
6. “What’s left of our land is really a very precious commodity, and a strip mine that would last up to 40 years[ ] is quite a serious and a large undertaking. Now I’m not against progress or industry in our county, and I’m very keenly aware of the need we have for it. But I am against something of this magnitude, trying to be pushed through just as fast as possible, without all of our County officials finding out every possible ramification that an industry of this magnitude could possibly hold.”
