107 Tenn. 409 | Tenn. | 1901
The defendant (Eberhart), as the result of competitive bidding, was awarded a contract for the construction of an oil mill, in the city of Memphis, for the Perkins Oil Co. The contract price for the work was $26,000. Eberhart, the contractor, executed a bond with the American Bonding & Trust Co., as surety, in the penalty of $7,000, for the faithful performance of the work. Toward the close of the work complications arose. Mechanics, laborers, and material men filed notices of liens upon complainants’ property, and it was threatened with vexatious litigation and serious loss. Thereupon the present bill was filed by the Perkins
The Perkins Oil Co. answered the cross bill of Eberhart, in which it denied that it was indebted to him in any amount. There was a reference to the Master to state an account between the 'parties, who, upon the proof, found the sum of $7,117 to be due Eberhart. Exceptions to the report were filed by both- sides, which were overruled by the Chancellor and the report confirmed, excepting an item of $500, which the Master reported in favor of Eberhart, but which the Chancellor disallowed, thus reducing the claim of Eberhart to $6,605.36. During the progress of the cause decrees for the sum of $9,795.91 were rendered against the property of the Perkins Oil Co., in favor of the various subcontractors and material men, which sum was fully paid off by the oil company. On final hearing, the Chancellor pronounced a judgment in favor of the Perkins Oil Co., and against Eberhart, for $3,190.55, the difference between $9,795.91, the sum which the oil company was required to pay to the several subcontractors and material men, to satisfy their liens upon the lands and buildings of the oil company,
On behalf of Eberhart the first assignment of error is that the Chancellor erred in his construction of article 1 of the contract between Eberhart and the oil company, which is in the words and figures following, viz.: “Article 1. The contractor, under the direction and to the satisfaction of A. H. D. .Perkins, or his supervisor, acting for the purposes of this contract as agents of the said owner, shall and will provide all the materials and perform all the work mentioned in the specifications and shown on the drawings, prepared by the said owner for an oil mill, according to plans and specifications, and foundations for presses, accumulators, and engine, to the amount of one hundred and twenty thousand brick (120,000), all in addition to that quantity to be $14 per thousand in Portland cement, $11.50 per thousand in Louisville cement. All fire doors single, which drawings and specifications are identified by the signatures of the parties hereto. ’ ’
It is said the learned Chancellor, in regard to this clause, held, in effect, that Eberhart was to be paid extra only for brick above the amount of 120,000, used in the foundations for presses, accu
It is insisted by counsel for appellant that the interpretation of the contract is a matter of law, for the Court, and we cannot look beyond its four corners for light. It is a cardinal rule of construction that all instruments are to be expounded and to have effect given them according to the manifest intention of the parties, as apparent from the whole instrument or agreement, if not incompatible with established principles of law or policy. Polk v. Buchanan, 5 Sneed, 726. Again, it was said by the Court in Barker v. Freeland, 91 Tenn., 116: “It is an indisputable proposition that, when a contract is in writing and its meaning is plain and unambiguous, its interpretation is a matter of law, for the Court. But, when the writing is not plain and unambiguous, parol evidence is admissible to' ascertain the situation and surrounding circumstances,
With these fundamental principles in view, we now proceed to examine the contract. The building for the construction of which the contract was awarded to Eberhart was to be used by the Perkins Oil Co. for the purpose of manufacturing cottonseed products. It was to consist of a seed shed, to be constructed mainly of wood, and a two-story machinery department, which was to be made exclusively of brick. The plans and specifications upon which the bids were invited covered the entire work to be done, excepting the brick work which was to ■constitute the foundations for the machinery, such as presses, accumulators, and its engine. These foundations were not included in the plans and specifications because, it is said, it was not definitely known
The insistence, however, of Eberhart, is that he' was to be paid extra for all brick used in the construction of the entire work, including both buildings, in excess of 120,000. The proof is that 1,240,000 brick were-used in the buildings, and the contractor’s claim is that he is entitled to be paid extra for 1,120,000 brick. This extra compensation would have amounted to $12,880, while the contract price for the entire work, excepting the machinery foundations, was only $26,000. Is it reasonable to suppose that the parties ever contemplated such a construction of the contract?
The contract stipulates that the contractor is to furnish all the material ■ and perform all the work mentioned in the plans and specifications for an oil mill. The brick building would require at least 1,120,000 brick in its construction, and yet, according to the contractor’s contention, the contract only obligates him to furnish 120,000 brick, and for ail
The only reasonable construction of this contract, as we see it, is that the contractor was to be paid extra for all brick used in the machinery foundations in excess of 120,000. This was the understanding of all the competing contractors at the time the bid was awarded to Eberhart, and, so far as we can see, the latter made no contrary claim dur
If the brick used in these foundations exceeded 120,000, the contractor was to be paid extra, but if not, this work was also included in the original contract. The Clerk and Master, in executing the order of reference, so construed it.
In addition to this, the fact that the foundations for the machinery were to be laid in Portland and Louisville cement, and not in common mortar, the compensation of $14 per thousand for Portland cement and $11.50 per thousand for Louisville cement, related alone to the foundations for presses, accumulators, and engines. If counsel for Eberhart is correct in his construction of this contract, then no provision whatever is made in the contract for the brick laid in common mortar, and yet, probably seven-eighths of the brick used in the building were laid in common mortar. Complainant’s counsel, in
Counsel say: “It will thus be seen that the top eight courses of brick and the capping itself were to be practically the same as the foundations, and the rest of the brick above ground was to be in rich lime mortar. But we find that these specifications were changed by an addition, viz.: Louisville Black Diamond cement to be used, instead of Portland cement, in all brick work, except engine foundations and the capping or finishing touches on walls, which will be Portland.”
“It will thus be seen,” says learned counsel, ‘£ that by this important change in the specifications the foundations for the machinery and the capping were to be Portland cement as before, but that all brick work besides was to be finished in Louisville cement. Clearly, then, the intention of the parties,, at the time the contract was executed, was that none of this work should be laid in ordinary mortar. All that not laid in Portland cement was to be laid in .Louisville cement.”
We have thus quoted, in full, the exact position of complainant’s counsel on this subject. It is not
We are of opinion that the changes in the specifications, upon which complainant’s counsel rely, relate only to the character of the cement to be used, and was not designed to affect the quantity of brick that should be laid in cement and the amount to be laid in common mortar. The modification of the specifications was simply intended to permit Louis
It is insisted, however, that the decree against Eberhart for $3,190.55, was wholly unwarranted by the pleadings. It is said that in no pleading does the Perkins Oil Co. claim that Eberhart owes it anything or will owe it anything on final accounting. It is said that the bill was not filed to obtain decree against Eberhart, but that the object was to protect the company against a multiplicity of suits threatened by the various subcontractors and material-men. Counsel is mistaken, however, in his assumption that no judgment was asked against Eberhart. The bill, after setting forth the complications about to arise from the threatened suits of the lien claimants,
“If, by this proceeding, the Court shall adjudge any liability as against complainant, under the claims of the various defendants, which shall, together with the complainant’s claim for damages, arising from the failure of defendant, Eberhart, to carry out his contract, exceed the balance now in complainant’s hands, of the contract price, together with the amount due for extras, then, and in that event, complainant is advised it is entitled to a judgment for such amount, together with the amount of whatever expense it shall incur for Court costs, etc., against the defendant, The American Bonding and Trust Co., under the conditions and provisions of its bond hereinbefore set out.”
The bill asks for an account and contains a prayer for general relief.
The American Bonding and Trust Co., as the surety of Eberhart for the faithful performance of the work, was made a party defendant, because complainant expected to recover a judgment against Eberhart and would look to the bond of the Trust Co. for indemnity. Moreover, it is shown by the correspondence in the record that whenever lien
The second assignment of error is, viz.: The learned Chancellor erred in holding that Eberhart was not entitled to recover from the Perkins Oil Co. the full value of the lumber and the various woodwork, which became useless to Eberhai’t because of changes in the plans and specifications made by the Perkins Oil Co. itself. The complainant having, by its own fault, caused these plans and specifications to be changed, the loss should fall upon it. In addition to this, the said lumber and woodwork was left with the complainant company, was retained in its possession, and used by its officers, agents, and servants. It should, therefore, be compelled to pay for what it took and used.
In support of this assignment, counsel for appellants states, viz.: In this assignment of error are
'The total amount of these claims under these different exceptions is $1,499.09. We will state, as a general proposition, what is claimed in all of these exceptions. It is substantially this: The Perkins Oil Company, by contract with Eberhart, employed him to erect an oil mill for the company. In the erection of this mill certain plans and specifications were to be followed, and the parties signed a contract which made the plans and specifications a part thereof. Now, after the contract was made, the Perkins Oil Company, of its own accord, made many changes in the original plans and specifications. In changing these plans and specifications a great deal of lumber, woodwork, etc., furnished by Eberhart, became utterly useless. For instance, he would order an eight-foot plank, and after it had come, the company would change the plans so that a ten-foot plank, instead of one of eight-foot dimensions, would be required, so the eight-foot plank would be thrown away and would then become a dead loss to Eberhart.
The Clerk and Master, in disposing of this matter, says in his report, viz.: “13. The Master, in
The first assignment of error made on behalf of the bonding and trust company is that jurisdiction of the property, by attachment, for the assertion of mechanic’s lien, cannot be acquired on cross bill, it appearing that the property was not brought before the Court by the original bill or attachment^ or other process issued under it. It appears that the claims of lienholders are all based upon cross bills and attachments issued thereunder. It is, then, insisted the attachments issued upon the prayer of the several cross bills being illegal, the bonding and trust company is not bound by any decree based thereon. The original bill in the cause was filed in the nature of a bill of interpleader against all the parties in interest, with a view of preventing a multiplicity of suits and settling the rights of all parties in this litigation.
The lien claimants were all made defendants, and filed answers and cross bills attaching the property of the Perkins Oil Co., with a view of asserting their several liens.
The American Bonding and Trust Co. assigns error to the decree below, viz.: (2) ‘ ‘ The trial Court erred in rendering a decree against the American Bonding and Trust Co., for the reason that the changes made in the plans and specifications and the large amount of extra work required to be done was not made in accordance with the terms and conditions of the contract under which the bond was issued. First, in this, that the alterations made in the work shown and described by the drawings and specifications were not made upon the written order of the architect, and the value of the work added or omitted was not computed by the architect, and the amount of extra work so ascertained was not added to the contract price by the architect (article 3 of the contract, page 16 record, Yol. 1), and, second, that the changes made in the plans and specifications were so radical, and the burden imposed upon the contractor, Eberhart, was so much greater than those provided in the original contract, and under which the bond was made, that the bond company are entirely relieved from any obligation whatever under its bond.”
Article 3 of the contract provides that: “No alterations shall be made in the work shown or described by the drawings and specifications except upon a written order of the architects, and, when
The bond provides that the written contract entered into is attached to the bond and made a part thereof, and it is insisted that .any changes or variations from the conditions in the contract affected the surety on the bond. It is claimed, on behalf of the bonding company, that the extras and changes made in the contract from the time it was executed until the building was completed amounted in value to $6,291.73. It is then stated that there is no proof' or statement made in the record by any witness that any of the changes in the work, as shown by the original drawings and specifications, were made upon the written order of the architect, nor is there any statement or proof that the value of the work added or omitted was computed by the architect, and the amount so ascertained added to or deducted from the contract" price.
Counsel for appellants are mistaken in the assumption that the cost of the extra work, over and above the contract price, was $6,291.73. The Clerk and Master found, ás a fact, that the total cost of the extra work was $3,090.29. The Chancellor concurred with the Master, and this finding of fact is, therefore, conclusive, there being evidence to support it.
We do not find that any material alteration of the plans and specifications was made during the progress of the work. A number of expert building contractors and mechanics, after the completion of the work, made a thorough inspection of it, with the plans and specifications before them. Each of them testified on the trial that the buildings were constructed practically according to the plans and specifications, and that no material changes were made. The changes made were in respect to the details of the work, and there were no changes in the plans and specifications enlarging the buildings or adding new buildings.
■ The only change specifically referred to in the brief of counsel is that a wall was partially torn
The decree of the Chancellor is, in all respects, affirmed. The costs of the* .appealj- will be paid by appellant.