107 Mich. 553 | Mich. | 1895
This case was commenced in justice’s court, where plaintiff had judgment. On appeal by defendants, the cause was tried in the circuit court, and plaintiff again prevailed.
The plaintiff is a carpenter and joiner, and entered into á written contract with the defendants to do certain work on a house which they were building for John J. Black, the owner. The contract under which plaintiff was to perform his work provides, among other things, as follows:
“All work to be done in a good and workmanlike manner, for the sum of $100; part payment when work is two-thirds completed, and balance when the job is finished, and it is accepted by the architect and owner. All work to be done without delay. C. W. Perine is to furnish no material of any kind, but to do the labor.”
This contract was signed by the parties to this cause.
The plaintiff admitted on the trial that he had been paid $70, and claimed the right to recover the other $30 due under the contract, as well as for loss of time, which was occasioned, as he contended, by the defendants’ not furnishing material from time to time, as he called for it; that he did call for material, and was told by the defendants that it would be furnished, and not to quit work, as Mr. Black, the owner, would find fault if he did so. The defendants contended that the work was not performed in accordance with the contract; that there had been no acceptance of the work at the time the suit was commenced; that there had been no such loss of time as plaintiff claimed; and that, if any time was lost, they were not responsible for it.
On the trial the plaintiff put in evidence the contract between himself and defendants, and testified that he had performed it in accordance with the plans and speci
The court, in its charge, speaking of the contract between plaintiff and defendants, stated:
“It being silent, I deemed the defendants were to furnish the material, and, if you should find from all the testimony that any other arrangement was made about the furnishing of the material, I will leave that to you. I will not be arbitrary about it, but the whole matter is before you as to who furnished all the material.”
1. There was evidence from which the jury might well find that the contract was completed and the work accepted by the architect and owner, and that question was fairly left to the jury.
2. Even if the court was in error in leaving to the jury the question whether the defendants were to furnish the material, the defendants’ rights were not prejudiced, as it could not matter whether the defendants or the owner was to furnish the material, so far as the right of the plaintiff to recover for loss of time was concerned. The contract under which he was to do the labor provided that he was not to furnish any of the material. It was
We find no error in the record, and the judgment must be affirmed.