Perdoni Brothers Inc v. Concrete Sytems IncPerdoni Brothers Inc v. Concrete Sytems Inc
Dеfendant-appellant Concrete Systems, Inc. (CSI), a New Hampshire producer of pre-cast concrete products, contracted in 1985 with plaintiff-appellee Perdoni Brothers, Inc. (Perdoni), a Massachusetts-based construction firm, to manufacture and deliver 121 custom-designed manholes, at a total contract price of $51,670.47, for installation in a new sewer system in the Town of Ashland, Massachusetts. CSI contends that the district court committed reversible error in denying its post-verdict motion for judgment as a matter of law.
See
I
BACKGROUND
The first five manholes were delivered to the Perdoni job site by CSI on July 2, 1985. The remaining 116 manholes were delivered intermittently in twenty-six shipments extending over the next thirteen months and invoiced by individual shipment.
Dissatisfied with the CSI manholes (which leaked and had to be patched), 1 Perdoni brought this diversity action in federal distriсt court on April 25, 1990, demanding $134,000 in compensatory damages for breach of the implied warranties of merchantability and fitness for a particular purpose (implied warranty claims), see Mass. Gen.L. ch. 106 §§ 2-314, 2-315, and additional damages based on a deceptive trade practices claim under Mass.Gen.L. ch. 93A (“Chapter 93A”). CSI counterclaimed for $18,561 allegedly due from Perdoni on the Ashland project and another contract.
Trial was held before a magistrate judge, with the consent of the parties.
See
Thereafter, the magistrate judge convened a charge conference to consider the jury instructions, including the instruction on the statute-of-limitations defense. Neither party requested an instruction on the
law
governing the severability-entirety issue. Although Perdoni unsuccessfully sought an instruction that the contract should be considered an entirety, CSI made no corresponding request for an instruction that the contract be considered severable. Consequently, the magistrate judge simply instruсted the jury that CSI had the burden of proving that the action was time-barred, and that the four-year limitation period ran from the “time of delivery.” Although both parties argued the severability-entirety issue, the court made no explicit reference to it and neither party
The jury found in favor of Perdoni for $48,961, and in favor of CSI for $18,561 on its counterclaim. CSI then renewed its
II
DISCUSSION
Leaving aside CSI’s failure to object to the jury instruction on the statute-of-limitations defense, the district court waiver ruling is fully supported by CSI’s failure to raise the severability argument in its pre-verdict motion for judgment as a matter of law. The law is crystal clear that a “party may not base its motion for a judgment n.o.v. on a ground that was not argued in its motion for directed verdict.”
Sweeney v. Westvaco Co.,
The pre-verdict motion for judgment as a matter of law,
see
Most importantly, the district court was never forewarned of the legal basis for the severability claim first surfaced by CSI following the adverse jury verdict. Under our precedent, therefore, on appeal CSI was not entitled to challengе the sufficiency of the evidence supporting the jury verdict on the limitations issue.
See Wells Real Estate,
Under Article 2 of the Uniform Commercial Code, the severаbility or entirety of a contract of sale turns on the intent of the contracting parties,
see, e.g., Carlo Bianchi & Co. v. Builders’ Equip. & Supplies Co.,
Next, even assuming that it failed to preserve its severability claim for appeal, CSI argues that a new trial is required due to alleged inconsistencies between the jury’s award of damages on the implied warranty claims and the magistrate judge’s resolution of the limitations defense relating to the Chapter 93A claim. We do not agree.
First, as no special interrogatory was submitted to the jury on the limitations defense relating to the implied warranty claims, it would be conjectural to conclude that the damages awarded by the jury and the finding made by the magistrate judge are irreconcilable.
See
Second, CSI posits an inconsistency between the results reached by different decisionmakers on distinct claims, and incorrectly assumes that the jury verdict must yield. Where an irreconcilable inconsistency exists between a bench decision and a jury verdict on different claims arising out of the same transaction, the jury finding must take precedence in the Seventh Amendment context: “when a party has a right to a jury trial on an issue involved in a legal claim, the judge is of course bound by the jury’s determination of that issue as it affects his disposition of an accompanying equitable claim.”
Lincoln v. Board of Regents,
Affirmed. 6
Notes
. Sewer line manholes must be watertight. A common point of leakage is the area where the sewer lines enter the manhole structure. Precise casting, as well as installation of rubber "boots” to ensure a tight fit between the wall of the structure and the sewer line itself, is necessary to ensure the integrity of the manhole. At trial, Perdoni adduced evidence that CSI had usеd a defective hole former to cast the manholes for the Ashland project. Consequently, the pipe openings in the sides of the manholes were misshapen and the seals between the boot and rim of the openings were not watertight.
. The instruction relating to the statute of limitations fоllows:
[T]here is also an issue arising from [CSI's] asserted defense based on ... the statute of limitations.
This is simply a provision that a suit be commenced on certain types of claims within a prescribed period of time, otherwise, the suit is barred or precluded. For a breach of warranty claim, the аpplicable statute of limitations for an action on a contract for the sale of goods is four years.
That means that a plaintiff has four years to bring a suit for a breach of warranty. The time limit placed upon Perdoni began to run at the time of delivery of the manholes, regardless of whether Perdoni knew of the breach. Thus within four years of the time which Perdoni received the manholes, it must have commenced this lawsuit.
}f. ‡ ‡ 3j{ * ‡
It is [CSI’s] burden to show that Perdoni has not complied with the statute of limitations, thus [CSI] has the burden of establishing that Perdoni filed a suit more than four years after the delivery of the mаnholes, and if Perdoni did not commence the suit within the four-year period, Perdoni may not recover on its warranty theories.
Trial Tr. at 168 (April 16, 1993) (emphasis added).
. The magistrate judge noted that:
This Court instructed [the jury] that, as an affirmative defense, CSI had the burden of proving ... that Perdoni filed the suit more than four years after delivery of the manholes. CSI did not object to this instructiоn. Nor did CSI submit an instruction based on the law governing divisibility of performance, entire contracts, separate contracts and installment contracts. CSI was apparently content to treat the question of what constitutes the time of delivery as an issue of fact. CSI did move for a directed vеrdict on this issue, but, again, this motion was predicated on the evidence being clear as to the tender of delivery and included no argument as to the law governing divisibility of performance, entire contracts, separate contracts and installment contracts. CSI's pretrial memorandum was no more edifying on this point.... This court finds it late in the day to be raising the legal issue, and deems the issue waived.
Perdoni Bros., Inc. v. Concrete Sys., Inc., Civ. 90-11046-WF, Memorandum Order at 7-8 (D.Mass. August 27, 1993) (emphasis added).
. Counsel argued the severability-entirety issue in their closings. CSI argued that the parties' performance under the contract demonstrated their practice of treating each separately invoiced shipment of manholes as a distinct transaction. See Trial. Tr. at 141 ("rеally what is occurring here is a series of contracts.... All the manholes were made to order. The manholes that were shipped ... in 1986 have no relation to the manholes that were delivered as of November 14, 1985.”) Perdoni, on the other hand, urged the jury to view the contract as a unitary whole, and to recognize that Perdoni required all of the manholes in order to complete its contract project. Id. at 157 ("if you ordered 12 eggs, and you get 10, you don't say, ‘Thank you for delivering my eggs.’ .... [T]he full quantity ordered was not delivered until July of 1986.”).
. As CSI advances the same arguments in support of its appeal from the denial of its
. Although counsel fees have been awarded on occasion for an appellate defense of a judgment on a Chapter 93A claim,
see, e.g., Manzoro v. McCann,