970 F.2d 1340 | 4th Cir. | 1992
OPINION
This is an appeal from the district court’s order granting summary judgment to Pepper Burns Insulation, Inc., a second-tier subcontractor on a federal construction project. Pepper Burns had brought suit against Artco Contracting, Inc., the general contractor on the federal project, to collect under a Miller Act
I.
The parties do not dispute the facts of this case. In March 1987, Artco received a contract from the U.S. Army Corps of Engineers to construct the SOCOM Operations Complex
Artco hired Pyramid Contracting, Ltd. as a subcontractor. Pyramid, in turn, hired Pepper Burns as a second-tier subcontractor to' install flooring. According to an agreement entered into between Pyramid and Pepper Burns dated June 2, 1987, Pepper Burns was to receive $59,466.00 for its work on the project.
Pepper Burns completed its work on July 27, 1989,
Section 2(a) of the Miller Act requires that the party seeking recovery on a payment bond “giv[e] written notice to said contractor within ninety days from the date on which such person did or performed the last of the labor or furnished or supplied the last of the material for which such claim is made_” 40 U.S.C. § 270b(a). Therefore, on October 20, 1989, less than 90 days after July 27, Pepper Burns mailed the required notice to Artco of its claim on the bond. Artco received the notice several days later on October 31. Pepper Burns then filed suit against Artco on July 27, 1990.
Artco appeals the decision, contending that the district court erred in not granting Artco summary judgment.
II.
We consider this case de novo under the familiar standard for reviewing motions for summary judgment. See Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986).
Although Artco raises two claims on appeal, we find it necessary only to consider its notice claim in order to dispose of this case. The parties do not dispute that notice was mailed by Pepper Burns on October 20, within the statutory ninety-day period, but not actually received by Artco until October 31, outside the statutory window. Thus, we must decide whether mailing or receipt satisfies the notice requirement of § 270b(a).
Section 270b(a) states in part:
Every person who has furnished labor or material in the prosecution of the work provided for in such [federal] contract, in respect of which a payment bond is furnished under section[ ] 270a ... and who has not been paid in full therefor ..., shall have the right to sue on such payment bond ...: Provided, however, That any person having direct contractual relationship with a subcontractor but no contractual relationship express or implied with the contractor furnishing said payment bond shall have a right of action upon the said payment bond upon giving written notice to said contractor within ninety days from the date on which such person did or performed the last of the labor or furnished or supplied the last of the material for which such claim is made....
40 U.S.C. § 270b(a) (emphasis in original). The statute clearly requires timely notice as a condition precedent to the right to maintain suit on a payment bond. Our decision turns on the meaning of “giving written notice.” We can then determine if the properly given notice was timely.
The issue presented here is one of first impression for our Court. We look to other Miller Act decisions for rules of general construction.
Given its plain meaning, the language “giving written notice to said contractor” requires receipt of the notice by the contractor. Mailing does not fully accomplish the condition to “giv[e] ... notice.” Such condition requires that the notice actually be “giv[en],” that is, put in the possession of the contractor. In other words, we hold that the statute’s language requires actually notifying the contractor. Had Congress chosen different language, we could have reached another outcome. For example, it seems that a statute providing a right of action “upon written notice” would not impose the same requirements on a subcontractor. In that case, mailing would satisfy the statutory condition. Similarly, a right of action granted “upon mailing written notice” would obviously require only mailing. Thus, the statute’s authors could easily have stated its directive as a mailing requirement if that was the desired intent. In fact, the statute later discusses mailing as a permissible method of service,
This construction is consistent with the legislative purpose underlying section 2(a). In Honeywell, we held that the notice provisions of section 2(a) should be strictly enforced in to order to carry out the design of the statute, that is:
to give contractors ... ninety days after completion of their work within which to assert a claim against the general contractor and its surety. If it does not do so within that period, the contractor may make final payment to the subcontractor with impunity. It would be quite unfair to the general contractor to expose it to stale claims of which it had no notice during the' ninety day period.
Honeywell, 677 F.2d at 386. Likewise, our ruling here provides contractors with a date certain after which they are no longer at risk of liability to second-tier subcontractors. Certainty facilitates payments to first-tier subcontractors and closure of the project finances. Any alternative ruling, it seems, could potentially extend liability for
Having decided that section 2(a) requires receipt of notice by a contractor, the application of the statute to the facts here is a simple matter. The parties agree that the claim notice was not received until October 31, more than ninety days after completion of work by Pepper Burns. Thus, Pepper Burns did not satisfy the statutory prerequisite for filing an action against Artco on the payment bond.
Accordingly, we reverse the district court order granting summary judgment to Pepper Burns and remand this case for entry of an order dismissing the case against Artco.
REVERSED AND REMANDED WITH INSTRUCTIONS.
. 40 U.S.C. §§ 270a-270d (1988).
. SOCOM is an acronym for Special Operations Command. The complex serves as a planning center for special military operations.
.This is the last day Pepper Burns performed any work for or supplied materials to the project.
. Pepper Burns brought suit against Artco, Pyramid and the bond sureties. Neither Pyramid nor the sureties answered the complaint and default judgment was entered against them. Actions against Pyramid were stayed when it filed a Chapter 7 bankruptcy proceeding.
. Although other courts have expressed views on this particular question, we find no guidance in their conflicting statements. Only two courts have expressly ruled on the issue. The district court in United States ex rel. Crowe v. Continental Casualty Co., 245 F.Supp. 871, 873 (E.D.La.1965), specifically held that notice mailed on the ninetieth day was sufficient for purposes of the Miller Act. Subsequently, the court for the Eastern District of New York, relying on the Crowe decision, reached the same conclusion. United States ex rel. Lincoln Elec. Prod. Co. v. Greene Elec. Serv., 252 F.Supp. 324, 327 (E.D.N.Y.1966) (mailing notice within the ninety
The Second Circuit in dicta expressed an opposing view in an opinion issued shortly before it affirmed Lincoln Electric. See United States ex rel. Gen. Elec. Co. v. H.I. Lewis Constr. Co., 375 F.2d 194, 200 (2d Cir.1967) ("notice, however conveyed, must reach the party ... within the statutory time for its receipt”). Similarly, other district courts, in dicta, have indicated that receipt is necessary to satisfy the Miller Act requirement. See, e.g., United States ex rel. Greenwald-Supon, Inc. v. Gramercy Contractors, Inc., 433 F.Supp. 156, 163 (S.D.N.Y.1977); United States ex rel. Excavation Construction, Inc. v. Glenn-Stewart-Pinckney Builders and Developers, Inc., 388 F.Supp. 289, 296 (D.Del.1975).
. The last sentence of § 270b(a) provides:
Such notice shall be served by mailing the same by registered mail, postage prepaid, in an envelop addressed to the contractor at any place he maintains an office or conducts his business, or his residence....