189 A.D. 421 | N.Y. App. Div. | 1919
The claimant’s electric light plant was situated on the west side of the Oswego canal, at Oswego, N. Y. It was operated by water power, the water being secured from the hydraulic canal, owned by the Oswego Canal Company, which runs parallel with the Oswego canal and to the east thereof. A sunken conduit extending under the Oswego canal conducted the water from the hydraulic canal on the east to a forebay on the west and between the Oswego canal and the claimant’s plant.
The contractor for that section of the Barge canal, while working at that point, with the consent of the State Superintendent of Public Works, tore out the conduit, destroyed claimant’s forebay, and built a wall on claimant’s land. Claims were filed against the State for the damages resulting from such acts. The Court of Claims has found in favor of the claimant and has awarded it damages. (105 Misc. Rep. 231.)
We are satisfied with the disposition of the claims made by the Court of Claims except in one respect.
The conduit which furnished the claimant with water was torn out and closed on August 22, 1910. Thereafter the claimant’s forebay was partially destroyed and a wall was built on claimant’s land between its power plant and the Oswego canal. The State required the contractor for that section of the Barge canal to put in a new conduit under the new Barge canal to carry the water from the hydraulic canal for the claimant’s power purposes. That new conduit was completed on November 25, 1912. Its opening was on the west bank of the Oswego canal about ninety feet south of the old conduit opening and south of claimant’s building and forebay.
The Court of Claims has allowed the claimant damages at the rate of $6,000 per year, from August 22, 1910, to May 25, 1913. The court found that the new conduit was completed on November 25, 1912, and also found that six months would be a reasonable time within which the claimant could build its forebay and connect up with the new conduit.
The court applied the avoidable consequence rule, for reducing damages, and limited claimant’s recovery as above stated to the period ending May 25, 1913. In this we think the court erred.
The State, when it destroyed the claimant’s forebay and trespassed upon its land, did so under a claim of title. It asserted upon the trial and in this court that it owned a strip of land between claimant’s property and the west bank of the Oswego canal, and that claimant’s forebay was on the State's land. It also contended and now contends that it owns or is entitled to possession of the land upon which claimant would have to build its forebay in order to connect with the new conduit. That was one of the questions litigated before the Court of Claims, which found that the claimant owned the strip of land in question.
The claimant contends that its damages should not have been limited by the Court of Claims to the period from August 22, 1910, to May 25, 1913, for the reason that the State itself wrongfully claimed title to the land upon which claimant would be compelled to build and was not in a position, therefore, to urge that the claimant should have built its forebay at an expense of $17,000 for the purpose of lessening the damages which the State had caused by its wrongful act.
When the State trespassed upon the claimant’s land and destroyed its water power it became hable for such damages as were caused as the natural, direct and immediate result of the trespass. (Allen v. McConihe, 124 N. Y. 342; 17 C. J. 750.)
The loss of the rental value of the property is, of course, the direct and immediate result of the act of the State.
The State has thus far successfully contended, however, that
The burden of proof upon such question is apparently upon the one seeking to limit the recovery on that ground. (Costigan v. M. & H. R. R. Co., 2 Den. 609; Hamilton v. McPherson, 28 N. Y. 72; Colrick v. Swinburne, 105 id. 503; Milage v. Woodward, 186 id. 252.)
We believe claimant was not required to take the chance of being a trespasser by building a new forebay upon land which the State claimed and now claims to own. It was justified in filing its claim and in awaiting the determination of the court as to the ownership of the strip of land in question.
The findings and judgment herein should be modified in accordance with this opinion and damages allowed at the rate of $6,000 per year to August 17, 1916, with interest, and as so modified affirmed, with costs to the claimant.
All concurred.
Findings and judgment modified in accordance with the opinion, and as so modified affirmed, with costs of this appeal to claimant.