85 N.J. Eq. 551 | N.J. | 1916
The opinion of the court was delivered by
The complainant, a building and loan associátion, is seeking to foreclose a mortgage given after the commencement of a
August 4th, 1913, the complainant gave to the mortgagor its check for the balance due, and she endorsed and delivered it to the counsel of complainant, who, September 19th, paid out of it $750 to a materialman who had furnished materials for the construction of the building, and on September 23d, 1913, he paid to the complainant the balance he had in hand towards interest and fines due to it. The contest in this case relates to the disbursement of this balance, and the advisory master to whom the cause was referred to hear and advise the chancellor what decree should be made, advised that the lien claimant was entitled to priority as to the $750, and that the balance paid on account of interest and fees was not applied towards the erection of the building, and therefore not an advance which it was entitled to make and to that extent the mechanic’s lien was also prior to the complainant’s mortgage.
The question raised by this appeal is whether the defendant is entitled to priority to the extent of the amount retained by complainant for interest and fines, and also to the $750 paid on account of materials used in the construction of the building to a person other than the defendant, because it was paid after defendant had obtained a judgment on his lien claim. We do not deem it necessary to determine the question whether the mortgagee may lawfully pay out of the mortgage fund the debt of a materialman who has furnished materials used in constructing the building in preference to one who has filed a mechanic’s lien claim and reduced it to judgment, because the case can be disposed of for reasons not based upon nor involving that question.
“generally against the builder and specially against the lands and building in complaint described, subject to the lien of the mortgages of the Peoples Building and Loan Association of Ridgefield Park, N. X, and Carl Ilallberg respectively.”
The proceedings leading to this judgment are not shown in the present record, but in the title of the cause under which the foregoing judgment was entered the complainant was a defendant as mortgagee, as provided by the statute (3 Comp. Stat. p. 3307 § 23), which requires that
“Suit shall be commenced by summons against the builder and owner of the land and building, and every person holding a mortgage of record against the property affected by said claim, whose mortgage would be cut off by a sale under said claim.”
Section 24 provides,
“and any defendant mortgagee may have a further plea that said lien claim is subject to such mortgagee’s lien, and the judgment in any such case shall determine the priority of the liens of the plaintiff and each of said defendants.”
This court held in Culver v. Lieberman, 69 N. J. Law 341, that the purpose of this statute was to settle in a single suit the liens of all persons who have any interest in the property, and to determine, among other matters, “what mortgage encumbrance is upon each piece of property and the priorities between the mortgagees and the plaintiff’s special judgment.” In determining “what mortgage encumbrance” there is on a property, the court must of necessity ascertain the amount which is entitled to priority, for if it be assumed that the amount cannot be inquired into, then the real priorities could not be
Under these conditions the presumption must be that when the judgment was entered in the suit brought by the lien claimant, the defendant in this cause, adjudging that such judgment was subject to the lien of complainant’s mortgage, that the trial court found that it was subject to the entire sum for which the mortgage was given. This judgment was entered September 11th, 1913, and was not appealed from by the present defendant, and thereupon the counsel of the mortgagee, on September 19th, 1913, paid the $750 to a materialman on account of his claim for material furnished and used in the erection of the building. Under these circumstances the judgment plaintiff is estopped from now denying the force and effect of the judgment entered by him, and relying upon which the complainant applied the balance in hand towards the payment of an unsatisfied claim for materials used in the erection of the building. The natural effect of the act of the defendant in procuring a judgment to be entered in his favor subject to complainant’s mortgage, in an action where the court had jurisdiction to determine priorities, and in which the complainant was a party asserting the priority of its mortgage, would be to induce the complainant to believe that its mortgage was a prior lien, and if it acted on such inducement, so that if the plaintiff in that suit be permitted to deny the truth of-the judgment record the complainant must suffer harm, such plaintiff will be estopped such denial. Mutual Life Insurance Co. v. Norris, 31 N. J. Eq. 583. It was the duty of the plaintiff in the judgment record to know that the effect of the judgment was to make the entire mortgage a lien prior to the judgment, and he is presumed to know that the complainant would so treat it and could safely do so. The
“that said order as amended be further amended so as to read as follows * * * that said judgment is subject to the mortgage (of the complainant) to the extent of the sum of eighteen hundred and sixty ($1,860) dollars actually advanced thereon at the time of the trial, and also to the extent of such further moneys advanced thereon, not in excess of the principal thereof as shall be adjudged by a competent court to be entitled to priority over the said lien and the judgment thereon.”
What the original amendment was does not appear in this record, but the above order, even if the court had the power to amend the judgment so long after its entry, which we are not to be considered as conceding, could not, and did not change the status of the parties which resulted from their previous conduct based upon the original judgment.
In addition to this the attempted amendment does not conform to the requirement of the statute because it does not determine the respective priorities in the action brought to settle that question, but leaves a part of it to be settled by some other tribunal, a situation which the statute does not provide for or contemplate. The original judgment was entered in conformity with the statute, and determined the respective priorities of the liens and it has not been expressly vacated or set aside, nor impliedly altered by this inefficacious order which did not adjudge the issue as directed by the statute requiring that, “the judgment in any such case shall determine the priority of the liens of the plaintiff and each of said defendants,” and this the amended order does not do. The fact that the order was made by consent does not confer on the court jurisdiction to
The decree will be reversed, with costs.