delivered the opinion of the court:
Defendant, Joshua C. Hampton, was charged with robbery (
On November 4, 2007, defendant was arrested. The next day, the trial court set bail, found probable cause to hold defendant, remanded him to the custody of the sheriff, and ordered him to appear on November 29, 2007. On November 29, 2007, the court appointed the public defender to represent defendant and, on defendant’s motion, continued the cause to December 6, 2007. On December 6, 2007, defendant filed a “Demand for Speedy Trial” under
On February 15, 2008, the State moved to continue “to a future date for trial.” At a hearing that day, Assistant State’s Attorney Jamie Mosser explained that the State had tried unsuccessfully to serve the complaining witness and could not go to trial without her. Defendant’s attorney, Brenda Willett, objected on speedy-trial grounds The court set March 24, 2008, for trial.
On February 28, 2008, the State again moved to continue the trial because another material witness would be unavailable on March 24, 2008. At a hearing also on February 28, the judge summarized the State’s motion. The hearing concluded as follows:
“MS. WILLETT: Judge, we have previously demanded a speedy trial. We would continue in that demand.
THE COURT: It’s People’s time now. Do you want me to go forward or backwards? Should I go past this date, or do you want me to try and advance the date?
MS. WILLETT: March 31st.
MR. STAJDOHAR [assistant State’s Attorney]: March 31st would be fine. Ms. Mosser says the week before or week after, and court is still unavailable the 17th.
Is that an accurate statement?
THE COURT: Yes. All right. Then I shall mark you down for March 31st. People’s motion to continue is granted. Final pretrial conference is the Friday before, March 28th.”
On March 27, 2008, defendant moved to dismiss, based on
“Every person in custody in this State for an alleged offense shall be tried *** within 120 days from the date he was taken into custody unless delay is occasioned by the defendant ***. Delay shall be considered to be agreed to by the defendant unless he or she objects to the delay by making a written demand for trial or an oral demand for trial on the record.”725 ILCS 5/103 — 5(a) (West 2006).
Defendant argued as follows. The 120-day period automatically began when he was taken into custody on November 4, 2007. See People v. Campa,
The State responded first that, because defendant did not affirmatively demand a speedy trial until December 6, 2007, any time that he spent in custody before then — including the period from November 4, 2007, through November 29, 2007 — was attributable to him. Also, when the judge later set the trial for March 31, 2008, allegedly outside the 120-day period, defendant did not object to the proposed violation of his right to be tried within 120 days. Indeed, his attorney actually requested the date. Therefore, under People v. Cordell,
At a hearing on the motion, the trial judge agreed with defendant that the statutory 120-day period automatically began when defendant was taken into custody. Thus, the judge counted the first 25 days (November 5, 2007, through November 29, 2007) against the State. Noting that the continuances from November 29, 2007, to December 20, 2007, were attributable to defendant, the judge excluded this period from the 120-day calculation. The remaining question was how much of the remaining time, between December 20, 2007, and March 31, 2008, a total of 102 days, should count against the State. The judge noted that the continuances in that period had been on the State’s motion and that, in each instance, defendant had objected on the specific ground of his statutory right to a speedy trial. The judge concluded that, because 127 days of delay in all were attributable to the State, defendant had been denied his right to a speedy trial. After the trial court dismissed the charge, the State timely appealed.
On appeal, the State argues that the trial court erred in holding that defendant was denied his statutory right to a speedy trial, and it contends specifically that: (1) the period between defendant’s arrest and November 29, 2007, was attributable to him; and (2) under Cor-dell, when defendant agreed to a continuance to a date beyond the statutory period, the delay past the deadline was attributable to him. The State notes that accepting either contention defeats defendant’s speedy-trial claim.
For the reasons that follow, we disagree with the State’s first contention but agree with its second contention, and thus we hold that the trial court erred in dismissing the charge. Defendant may not be charged with any of the delay preceding November 29, 2007, as the statutory speedy-trial clock automatically started when he was taken into custody. However, under Cordell, defendant was responsible for the continuation of the trial from February 28, 2008, to a date outside the statutory 120-day period. Defendant not only acquiesced in, but affirmatively sought, this date, and he was not entitled to have the case dismissed merely because the trial was set for a date of his own choosing.
Preliminarily, we note that the parties disagree on whether our review should be de novo or deferential. The State contends that, because the facts are not in dispute, the issue on review is one of statutory construction, which we decide de novo. Defendant responds that a trial court has broad discretion in deciding which party is responsible for delay and that we should affirm the judgment unless the trial court abused its discretion. Under the circumstances, we view the distinction as academic. The essential points are that (1) under settled case law, the trial court correctly charged the initial 25-day period to the State; and (2) under Cordell, defendant must be charged with the delay of the trial past the statutory period. Whether we say that (a) the trial court was correct as a matter of law in the first respect and incorrect as a matter of law in the second or (b) the court acted within its discretion in the first instance and abused its discretion in the second, our analysis and our result are the same. We do note, however, that because the pertinent facts are not in dispute, there appears to be no reason to defer to the trial court’s judgment. See People v. Crane,
We consider the State’s first contention: that the trial court erred in holding that the first period of delay, from November 4, 2007, through November 29, 2007, a total of 25 days, was attributable to the State.
1
The State concedes that we have held that
The State cites no authority supporting its construction of
The State’s argument here amounts to saying that a defendant in custody need not demand a speedy trial in order to start the statutory clock running — but that he must make such a demand in order to preempt any action that the trial court may take, or else he will be deemed to have consented to the trial court’s delay of the proceedings. That would make the provision run much less than “automatically” (Peco,
In Peco, we relied not only on
We turn to the State’s second contention: that the trial court erred in holding that the State was responsible for the delay from February 28, 2008, through March 31, 2008. (The parties agree that the State was responsible for the delay from December 20, 2007, through February 28, 2008.) We agree with the State that, under Cordell, the trial court erred in attributing this period to the State, at least insofar as doing so caused the trial to be set outside the 120-day period.
In Cordell, the defendant was arrested on January 24, 2002, and remained in custody until his trial. On April 26, 2002, at a status hearing, the defendant’s attorney asked the trial judge to set a trial date. The judge suggested June 11, 2002, for the trial. The defendant’s attorney did not object that the proposed date was outside
The supreme court rejected the speedy-trial argument that underlay the ineffectiveness claim. The court explained that “delay” (
Applying this reasoning, the supreme court held that, when the trial court set a trial date outside
Cordell’s reasoning also defeats defendant’s claim here. When the trial judge set defendant’s trial for March 31, 2008, beyond the 120-day limit, defendant did not object to the apparent violation of his right to a speedy trial; indeed, it was his attorney who proposed the date. Later, in making his speedy-trial claim, defendant used the very delay that he had not only agreed to, but had proposed, as a ground to dismiss the case. Defendant’s strategy exemplifies what the Cordell court intended to prevent — the use of
This case differs somewhat from Cordell in that, when the State moved for the continuance at issue, defendant did object on speedy-trial grounds. However, that difference is not material. In initially objecting to any continuance, defendant properly asserted his right to a speedy trial. Nonetheless, after the trial judge did decide to grant the State a continuance, defendant could not stand mute (or affirmatively propose a date outside of the speedy-trial term) if he wanted to successfully invoke his rights under
While this scenario differs from that in Cordell, it is completely harmonious with its reasoning. In Cordell, the defendant made a demand for trial before the trial court proposed any trial dates, and the defendant voiced no objection to any of the proposed trial dates. The court held that “[a] simple request for trial, before any ‘delay’ is proposed is not equivalent to an objection for purposes of
The judgment of the circuit court of Kane County is reversed, and the cause is remanded.
Reversed and remanded.
ZENOFF, EJ., and BOWMAN, J., concur.