105 N.E. 99 | NY | 1914
Lead Opinion
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *109
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *110
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *111
[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *112
The statute requiring and prescribing the substance and conditions of the bond is as perfectly binding on the principal and surety as if it had been set forth in the bond in its very words. (McCracken v. Hayward, 2 How. [U.S.] 608.) The bond, conforming to the statute, *114
imposed only such obligations as the statute permits. The statute is in a sense a recognition by Congress of the inability of persons supplying contractors for public works with labor and materials to take liens upon the public property of the United States and a substitute for a mechanic's lien law. (UnitedStates v. Ansonia Brass, etc., Co.,
It should be noticed, in order that there may be a true understanding of the relevant decisions, that the statute takes up the entire subject covered by a prior statute (Act of August 13, 1894, ch. 280; 28 U.S. Stat. L. 278), and, therefore, is to be treated as a substitute act.
Obviously the entire liability of the surety company to the claimant for the materials furnished by it under the contract between it and the Church Construction Company arises through the execution of the bond by the surety company as a surety for the construction company. The claimant could reach the surety company through the bond alone, which, with the statute as a part of it, defines and limits the rights of the claimant as against it, and the method and tribunals through which those rights might be enforced. His right of action against it through any form of legal proceeding was created by the bond and the statute, and must be enforced pursuant to the terms and conditions of the statute and not otherwise. (Stitzer v. United States,
182 Fed. Rep. 513; United States v. Boomer, 183 Fed. Rep. 726;Baker Contract Co. v. United States, 204 Fed. Rep. 390.) It was, however, a qualified and conditional, and not an absolute right or cause of action. An act of Congress, which at the same time and in itself authorizes or creates a new cause of action and prescribes the limitations thereof and of its enforcement, makes those limitations conditions of the liability itself. Such an act is not a statute of limitations, and a compliance with the conditions which it prescribes is indispensable to the enforcement of the right *115
it creates, because they are parts of or elements in the right itself and not limitations of the remedy only. The limitation of the remedy is a limitation to the right. (The Harrisburg,
The surety company became the surety for the Church Construction Company as expressed in the bond. The contract between the United States and the Construction Company was completed and finally settled September 28, 1908. Within the six months from that date, terminating March 27, 1909, the United States had not instituted any action upon the bond. The statute contemplated that the rights and claims of all claimants under the bond should be adjudicated in a single action brought upon the bond. (United States v. Congress Construction Co.,
The liability of the surety company to the claimant did not become absolute and direct when, after it had supplied the materials to the original contractor, their price became due, or when the contract between the original contractor and the United States was completed and finally settled. It remained qualified and conditional. Its certainty or absoluteness depended upon the possibility that, by means of the only method provided or permitted by the statute and not then instituted, the validity and enforceability of the claim be adjudicated. A judgment for it in an action prescribed by and conducted in accordance with the requirements of the statute could alone render it complete and absolute. The means of enforcement define both the right of the claimant and the liability of the surety which it was the intention of Congress to create.
It is unnecessary to consider whether or not the presentation of the claim to the receiver and the subsequent proceeding is a suit or action brought by the claimant. We are not required to pass beyond the fact that the claimant has no right of action and the surety company no liability cognizable in this action or proceeding. Whatever right of action was in the claimant or liability on the part of the surety was conditioned upon the use of the statutory remedy. Divorced from that remedy the right and the liability are non-existent. The claimant should have conformed with the provisions of the statute and obtained in the statutory action and presented to the receiver a judgment establishing the validity and amount of his claim. His claim as presented was conditional and not absolute, and its allowance was error. (People v. Metropolitan Surety Co.,
For the reason stated the order of the Appellate Division should be affirmed, with costs. The first question should be answered in the negative and the second question remain unanswered.
Dissenting Opinion
The condition of the bond was that the principal, the Church Construction Company, "shall promptly make full payments to all persons supplying it labor and materials in the prosecution of the work provided for in said contract." Indisputably, that condition was broken before the commencement of this action to dissolve the surety for its insolvency. The principal had not only failed to make payments as stipulated in the bond but had itself been dissolved for insolvency. The contract, for the performance of which the bond was given, was completed on September 28th, 1908, more than three months before this suit was brought. The full extent of the principal's default was fixed and determinable on that date. The liability of the surety was no longer contingent. The event upon which it had been contingent, a breach, had happened. Its liability may not have been liquidated, but there is a vast difference between a contingent, and an unliquidated liability or claim. If the surety's liability was contingent when this suit to dissolve it was brought, then every claim not reduced to judgment is contingent. In People v.Metropolitan Surety Co. (
I quite agree that the statute and the bond are to be construed together. My brother COLLIN construes the contract of the surety as one to become liable for the default of its principal but only after a judgment has been procured against it in the manner specified. I construe its contract as one to be liable absolutely within the sum named in the bond for the default of its principal upon the condition, however, that that liability, in case of its failure to discharge it, shall be enforced only as provided by the statute. There is a vital distinction between a condition of liability and a condition of the enforcement of that liability. It will introduce a novel and dangerous doctrine in the law of suretyship, especially in view of the extent to which that has become a business, to hold that the liability of a surety on a statutory bond does not arise *120 until resort has been had to the statutory method of enforcement. The contract of the surety is to pay on the default of its principal, and it should not be construed as one to pay only after a judgment has been recovered against it. The rule applied in People v. Metropolitan Surety Company (supra) would be doubly harsh if applied to a case like this. The necessity for its application in that case and in the many cases cited therein by Judge VANN does not exist in this case, because in this case the event, upon which liability depended, had happened and was no longer contingent and uncertain.
The question whether the claim must first be adjudicated in a suit brought in the Circuit Court of the United States for the Southern District of New York requires a closer analysis of the statute. (Chap. 778, 33 Stat. at L. 811; U.S. Comp. Stat. Supp. 1909, p. 948.) It is entitled, "An Act for the protection of persons furnishing materials and labor for the construction of public works." It is to be liberally construed to accomplish that purpose. (Hill v. American Surety Co.,
The statute, then, requires a bond to be given for the benefit of those supplying labor and materials. If it stopped there, as the earlier statute did, a claimant could have brought suit in any court having jurisdiction of the parties. Recognizing that, on a breach of the condition of the bond, persons furnishing labor and materials had "claims" against the surety, the statute provided in effect that they could be adjudicated in a suit brought by the United States within six months after the final completion of the contract, or, in case the United States did not sue, in a single suit brought within a year in the Circuit Court in the district in which the contract was to be performed. Undoubtedly, the remedy provided is exclusive. Undoubtedly, the Circuit Court for the Southern District of New York had exclusive jurisdiction of a suit against the surety on a claim arising on the bond. But I insist that this is not such a suit, and that the claim and the exclusive remedy provided for its enforcement are distinct.
The appellant was enjoined from bringing any action against the insolvent corporation or the receiver, the corporation becameciviliter mortuus, and the Supreme Court took possession of its assets to distribute them, not among creditors whose claims had been adjudicated, but "among its stockholders and its fair and honest creditors." An officer of the court took the place of the dissolved corporation, and the duty, theretofore resting on the corporation to pay its debts, without putting creditors to a suit to recover them, devolved on the receiver to the *122
extent that he had assets. The remedy provided for the recovery of a claim against the corporation before it was dissolved can have no application to a proceeding in an action like this to determine the claims of creditors. I grant that a suit is a proceeding in a court of justice for the enforcement of a right. (Drake v. Gilmore,
Doubtless the Supreme Court might have permitted an action to be brought in the Federal court for the purpose of determining the amount of the claims arising on the bond, but it was not bound to do so. "The court which appoints a receiver of the property of a corporation itself *123
holds and administers the estate, through the receiver as its officer, and must decide whether it will determine for itself all claims of or against the receiver or allow them to be litigated elsewhere." (Porter v. Sabin,
Having acquired jurisdiction, the Supreme Court could determine the priority of claims arising on the bond and whether a prorata deduction was necessary because of an excess of claims over the liability of the surety, precisely as that could have been determined in a suit in the Circuit Court of the United States. There is no difficulty on that head, as the total claims are less than that liability. It would have served no useful purpose to require the claimant to bring a suit in the Federal court, and the exclusive remedy provided for the enforcement of a claim against the defendant corporation ceased to apply the moment the Supreme Court dissolved the corporation, took possession of its assets and enjoined all creditors from bringing suits against the corporation or its receiver.
The cases of Fourth National Bank of N.Y. v. Francklyn
(
In my opinion, the decision of the Special Term was right.
WERNER, CHASE and HOGAN, JJ., concur with COLLIN, J.; WILLARD BARTLETT, Ch. J., and HISCOCK, J., concur with MILLER, J.
Order affirmed.