214 Ill. 376 | Ill. | 1905
delivered the opinion of the court:
Under section 293 of chapter 24, Hurd’s Revised Statutes of 1903, where the owner fails to comply with an ordinance providing for the construction of a sidewalk along his property, the same may be constructed by the city, town 01-village, and if the municipality has contemplated, in the event of such failure, collecting the cost of the improvement from the owner by special taxation,- the ordinance providing for the construction of the sidewalk must direct “that a bill of the cost of such sidewalk, showing in separate items the cost of grading, materials, laying down arid supervision,” shall be filed in the office of the clerk of the municipality, certified to by the officer or officers having charge of the construction of the sidewalk.
The contract under which the sidewalk in the case at bar was constructed was a general one, providing that the contractor, Larsen, should furnish all-materials and labor required to build all concrete sidewalks ordered by the president and board of trustees for the fiscal year, excepting such as should be constructed by the owners of abutting property, the compensation to be 16% cents per square foot.
Objectors contend that where the municipality constructs the sidewalk, it cannot be done by contract. We see no objection to a contract providing for the construction of a sidewalk. The statute is as well satisfied by a contract made by the village which provides, for example, that another shall furnish the labor necessary to construct the sidewalk as it is by an arrangement whereby the village employs laborers 01-mechanics to do the necessary work at so much per hour or per day; but where the municipality, instead of buying the materials by the quantity and paying for labor and supervision by the day or hour, elects to make a contract by which labor and materials shall be furnished for a certain sum, the contract must specify separately the sum to be paid for each of the items of grading, materials and laying the walk, so that from the contract itself the bill of cost contemplated by the statute can be prepared as to the three items last mentioned.
Here the contract was for 16% cents per square foot. The bid upon which the contract was made was in the alternative, setting out the various items for grading, materials and the labor of laying the walk at a certain price per lineal foot for a sidewalk five feet and four inches in width, or, in the alternative, the bid was for the equivalent by the- square foot, viz., i6}i cents for the three foregoing items. In making up the bill of cost recourse was had to the bid, and the items for grading, materials and laying the walk were obtained from that alternative proposition contained in the bid, which the village did not accept. It is impossible to know whether the village, at the time of making the contract, regarded the division of the cost of the walk made by that branch of the bid which it did not accept as a proper division or not. It elected to make the contract by the square foot, and having made that contract, could not properly say to the property owners that the cost, so far as they were concerned, was so much for each of the various items, but so far as the contractor was concerned was so much in the aggregate per square foot.
In Miservey v. People, 208 Ill. 646, it was said: “The right to levy a special .tax is purely statutory, and the statute requires that an itemized bill of the cost of the walk shall be filed. This requirement is for the protection and benefit of the property holder and cannot be dispensed with and a certified bill of the amount contracted by the village per lineal foot substituted.” If a bill of cost of so much per lineal foot is invalid, manifestly one by the square foot is equally so, and this objection cannot be obviated by the act of the officers of the village in dividing the contract price in such a manner as to make an apparent compliance with the statute when the contract was in fact for one certain sum per square foot for everything necessary to complete the walk.
It is unnecessary to consider other objections made by appellees in the court below.
The judgment of the county court will be affirmed.
Judgment affirmed.