PENSION BENEFIT GUARANTY CORPORATION v. THE LTV CORP. ET AL.
No. 89-390
Supreme Court of the United States
Argued February 27, 1990-Decided June 18, 1990
496 U.S. 633
Carol Connor Flowe argued the cause for petitioner. With her on the briefs were James J. Armbruster, Raymond Morgan Forster, Thomas S. Martin, Richard K. Willard, and Charles G. Cole.
Lewis B. Kaden argued the cause for respondents. With him on the brief for respondents The LTV Corporation et al. were Karen E. Wagner, Michael J. Crames, Marc Abrams, and Frank Cummings. Robin E. Phelan and Kathryn C. Mallory filed a brief for respondent Banctexas Dallas, N. A. Joel B. Zweibel, Geoffrey M. Kalmus, Michael J. Dell, and Peter V. Pantaleo filed a brief for respondent LTV Bank
JUSTICE BLACKMUN delivered the opinion of the Court.
In this case we must determine whether the decision of the Pension Benefit Guaranty Corporation (PBGC) to restore certain pension plans under
I
Petitioner PBGC is a wholly owned United States Government corporation, see
When a plan covered under Title IV terminates with insufficient assets to satisfy its pension obligations to the employees, the PBGC becomes trustee of the plan, taking over the plan‘s assets and liabilities. The PBGC then uses the plan‘s assets to cover what it can of the benefit obligations. See
*Briefs of amici curiae urging reversal were filed for the United States by Solicitor General Starr, Deputy Solicitor General Shapiro, and Christopher J. Wright; for the American Society of Pension Actuaries by Chester J. Salkind; for Armco et al. by Benjamin R. Civiletti and W. Warren Hamel; and for the Retired Employees Benefits Coalition, Inc., by Bruce E. Davis.
Briefs of amici curiae urging affirmance were filed for the State of Ohio by Anthony J. Celebrezze, Jr., Attorney General, and Loren L. Braverman; and for the American Federation of Labor and Congress of Industrial Organizations et al. by Robert M. Weinberg, Jeremiah A. Collins, Peter O. Shinevar, Laurence Gold, Bernard Kleiman, Carl B. Frankel, Paul Whitehead, and Karin S. Feldman.
William J. Kilberg and Baruch A. Fellner filed a brief for Wheeling-Pittsburgh Steel Corp. as amicus curiae.
The cost of the PBGC insurance is borne primarily by employers that maintain ongoing pension plans. Sections 4006 and 4007 of ERISA require these employers to pay annual premiums. See
As noted above, plan termination is the insurable event under Title IV. Plans may be terminated “voluntarily” by an employer or “involuntarily” by the PBGC. An employer may terminate a plan voluntarily in one of two ways. It may proceed with a “standard termination” only if it has sufficient
The PBGC, though, may terminate a plan “involuntarily,” notwithstanding the existence of a collective-bargaining agreement. Ibid.
“(1) the plan has not met the minimum funding standard required under section 412 of title 26, or has been notified by the Secretary of the Treasury that a notice of deficiency under section 6212 of title 26 has been mailed with respect to the tax imposed under section 4791(a) of title 26,
“(2) the plan will be unable to pay benefits when due,
“(3) the reportable event described in section 1343(b)(7) of this title has occurred, or
“(4) the possible long-run loss of the [PBGC] with respect to the plan may reasonably be expected to increase unreasonably if the plan is not terminated.”
29 U. S. C. § 1342(a) .
Termination can be undone by PBGC.
“In the case of a plan which has been terminated under section 1341 or 1342 of this title the [PBGC] is authorized in any such case in which [it] determines such action to be appropriate and consistent with its duties under this subchapter, to take such action as may be necessary to restore the plan to its pretermination status, including, but not limited to, the transfer to the employer or a plan
administrator of control of part or all of the remaining assets and liabilities of the plan.”
When a plan is restored, full benefits are reinstated, and the employer, rather than the PBGC, again is responsible for the plan‘s unfunded liabilities.
II
This case arose after respondent The LTV Corporation (LTV Corp.) and many of its subsidiaries, including LTV Steel Company Inc. (LTV Steel), (collectively LTV), in July 1986 filed petitions for reorganization under Chapter 11 of the Bankruptcy Code. At that time, LTV Steel was the sponsor of three defined benefit pension plans (Plans) covered by Title IV of ERISA. Two of the Plans were the products of collective-bargaining negotiations with the United Steelworkers of America (Steelworkers). The third was for nonunion salaried employees. Chronically underfunded, the Plans, by late 1986, had unfunded liabilities for promised benefits of almost $2.3 billion. Approximately $2.1 billion of this amount was covered by PBGC insurance.
It is undisputed that one of LTV Corp.‘s principal goals in filing the Chapter 11 petitions was the restructuring of LTV Steel‘s pension obligations, a goal which could be accomplished if the Plans were terminated and responsibility for the unfunded liabilities was placed on the PBGC. LTV Steel then could negotiate with its employees for new pension arrangements. LTV, however, could not voluntarily terminate the Plans because two of them had been negotiated in collective bargaining. LTV therefore sought to have the PBGC terminate the Plans.
To that end, LTV advised the PBGC in 1986 that it could not continue to provide complete funding for the Plans. PBGC estimated that, without continued funding, the Plans’ $2.1 billion underfunding could increase by as much as $65 million by December 1987 and by another $63 million by December 1988, unless the Plans were terminated. Moreover, extensive plant shutdowns were anticipated. These shut-
Because the Plans’ participants lost some benefits as a result of the termination, the Steelworkers filed an adversary action against LTV in the Bankruptcy Court, challenging the termination and seeking an order directing LTV to make up the lost benefits. This action was settled, with LTV and the Steelworkers negotiating an interim collective-bargaining agreement that included new pension arrangements intended to make up benefits that plan participants lost as a result of the termination. New payments to retirees were based explicitly upon “a percentage of the difference between the benefit that was being paid under the Prior Plans and the amount paid by the PBGC.” App. 181. Retired participants were thereby placed in substantially the same positions they would have occupied had the old Plans never been terminated. The new agreements respecting active participants were also designed to replace benefits under the old Plans that were not insured by the PBGC, such as early retirement benefits and shutdown benefits. With respect to shutdown benefits, LTV stated in Bankruptcy Court that the new benefits totaled “75% of benefits lost as a result of plan termination.”
The PBGC objected to these new pension agreements, characterizing them as “follow-on” plans. It defines a follow-on plan as a new benefit arrangement designed to wrap around the insurance benefits provided by the PBGC in such a way as to provide both retirees and active participants substantially the same benefits as they would have received had no termination occurred. The PBGC‘s policy against follow-on plans stems from the agency‘s belief that such plans are “abusive” of the insurance program and result in the PBGC‘s subsidizing an employer‘s ongoing pension program in a way not contemplated by Title IV. The PBGC consistently has made clear its policy of using its restoration powers under
LTV ignored the PBGC‘s objections to the new pension arrangements and asked the Bankruptcy Court for permission to fund the follow-on plans. The Bankruptcy Court granted LTV‘s request. In doing so, however, it noted that the PBGC “may have legal options or avenues that it can assert administratively . . . to implement its policy goals. Nothing done here tonight precludes the PBGC from pursuing these options....” Id., at 261.
The Director issued a notice of restoration on September 22, 1987, indicating the PBGC‘s intent to restore the terminated Plans. The PBGC notice explained that the restoration decision was based on (1) LTV‘s establishment of “a retirement program that results in an abuse of the pension plan termination insurance system established by Title IV of ERISA,” and (2) LTV‘s “improved financial circumstances.” See App. to Pet. for Cert. 182a.5 Restoration meant that
LTV refused to comply with the restoration decision. This prompted the PBGC to initiate an enforcement action in the District Court.6 The court vacated the PBGC‘s restoration decision, finding, among other things, that the PBGC had exceeded its authority under
The Court of Appeals for the Second Circuit affirmed, holding that the PBGC‘s restoration decision was “arbitrary and capricious” or contrary to law under the APA,
Because of the significant administrative law questions raised by this case, and the importance of the PBGC‘s insurance program, we granted certiorari. 493 U. S. 932 (1989).
III
A
The Court of Appeals first held that the restoration decision was arbitrary and capricious under
The PBGC contends that the Court of Appeals misapplied the general rule that an agency must take into consideration all relevant factors, see Citizens to Preserve Overton Park, Inc. v. Volpe, 401 U. S. 402, 416 (1971), by requiring the agency explicitly to consider and discuss labor and bankruptcy law. We agree.
First, and most important, we do not think that the requirement imposed by the Court of Appeals upon the PBGC can be reconciled with the plain language of
Even if Congress’ directive to the PBGC had not been so clear, we are not entirely sure that the Court of Appeals’ holding makes good sense as a general principle of administrative law. The PBGC points out problems that would arise if federal courts routinely were to require each agency to take explicit account of public policies that derive from federal statutes other than the agency‘s enabling Act. To begin with, there are numerous federal statutes that could be said to embody countless policies. If agency action may be disturbed whenever a reviewing court is able to point to an arguably relevant statutory policy that was not explicitly considered, then a very large number of agency decisions might be open to judicial invalidation.
The Court of Appeals’ directive that the PBGC give effect to the “policies and goals” of other statutes, apart from what those statutes actually provide,7 is questionable for another reason as well. Because the PBGC can claim no expertise in the labor and bankruptcy areas, it may be ill equipped to undertake the difficult task of discerning and applying the “policies and goals” of those fields. This Court recently observed:
“[N]o legislation pursues its purposes at all costs. Deciding what competing values will or will not be sacrificed to the achievement of a particular objective is the
very essence of legislative choice-and it frustrates rather than effectuates legislative intent simplistically to assume that whatever furthers the statute‘s primary objective must be the law.” Rodriguez v. United States, 480 U. S. 522, 525-526 (1987).
For these reasons, we believe the Court of Appeals erred in holding that the PBGC‘s restoration decision was arbitrary and capricious because the agency failed adequately to consider principles and policies of bankruptcy law and labor law.
B
The Court of Appeals also rejected the grounds for restoration that the PBGC did assert and discuss. The court found that the first ground the PBGC proffered to support the restoration-its policy against follow-on plans-was contrary to law because there was no indication in the text of the restoration provision,
In Chevron U. S. A. Inc. v. Natural Resources Defense Council, Inc., 467 U. S. 837 (1984), we set forth the general principles to be applied when federal courts review an agency‘s interpretation of the statute it implements:
“When a court reviews an agency‘s construction of the statute which it administers, it is confronted with two questions. First, always, is the question whether Congress has directly spoken to the precise question at issue. If the intent of Congress is clear, that is the end of the matter; for the court, as well as the agency, must give effect to the unambiguously expressed intent of Congress. If, however, the court determines Congress has not directly addressed the precise question at issue, the court does not simply impose its own construction on the statute, as would be necessary in the absence of an
administrative interpretation. Rather, if the statute is silent or ambiguous with respect to the specific issue, the question for the court is whether the agency‘s answer is based on a permissible construction of the statute.” Id., at 842-843 (footnotes omitted).
Here, the PBGC has interpreted
Turning to the first half of the inquiry, we observe that the text of
“(1) to encourage the continuation and maintenance of voluntary private pension plans for the benefit of their participants,
“(2) to provide for the timely and uninterrupted payment of pension benefits to participants and beneficiaries under plans to which this subchapter applies, and
“(3) to maintain premiums established by [the PBGC] under section 1306 of this title at the lowest level consistent with carrying out the obligations under this subchapter.”
29 U. S. C. § 1302(a) .
Nor do any of the other traditional tools of statutory construction compel the conclusion that Congress intended that the PBGC not base its restoration decisions on follow-on plans. The Court of Appeals relied extensively on passages in the legislative history of the 1974 enactment of ERISA which suggest that Congress considered financial recovery a valid basis for restoration, but which make no mention of follow-on plans. The court reasoned that because follow-ons were not among the bases for restoration discussed by Members of Congress, that body must have intended that the existence of follow-ons not be a reason for restoring pension plans. See 875 F. 2d, at 1017.
We do not agree with this conclusion. We first note that the discussion in the legislative history concerning grounds for restoration was not limited to the financial-recovery example. The House Conference Report indicated that restoration was appropriate if financial recovery or “some other factor made termination no longer advisable.” H. R. Conf. Rep. No. 93-1280, p. 378 (1974). Moreover, and more generally, the language of a statute-particularly language expressly granting an agency broad authority-is not to be regarded as modified by examples set forth in the legislative history. An example, after all, is just that: an illustration of a statute‘s operation in practice. It is not, as the Court of Appeals apparently thought, a definitive interpretation of a statute‘s scope. We see no suggestion in the legislative history that Congress intended its list of examples to be exhaustive. Under these circumstances, we conclude that ERISA‘s legislative history does not suggest “clear congressional intent” on the question of follow-on plans.
The Court of Appeals also relied on the legislative history of the 1987 amendments to ERISA effected by the Pension
Having determined that the PBGC‘s construction is not contrary to clear congressional intent, we still must ascertain whether the agency‘s policy is based upon a “permissible” construction of the statute, that is, a construction that is “rational and consistent with the statute.” NLRB v. Food & Commercial Workers, 484 U. S. 112, 123 (1987); see also Sullivan v. Everhart, 494 U. S. 83 (1990). Respondents argue that the PBGC‘s anti-follow-on policy is irrational be-
Consequently, follow-on plans may tend to frustrate one of the objectives of ERISA that the PBGC is supposed to accomplish-the “continuation and maintenance of voluntary private pension plans.”
None of this is to say that financial improvement will never be relevant to a restoration decision. Indeed, if an employer‘s financial situation remains so dire that restoration would lead inevitably to immediate retermination, the PBGC may decide not to restore a terminated plan even where the employer has instituted a follow-on plan.9 For present purposes, however, it is enough for us to decide that where, as here, there is no suggestion that immediate retermination of the plans will be necessary,10 it is rational for the PBGC to disfavor follow-on plans.11
C
Finally, we consider the Court of Appeals’ ruling that the agency procedures were inadequate in this particular case. Relying upon a passage in Bowman Transportation, Inc. v. Arkansas-Best Freight System, Inc., 419 U. S. 281, 288, n. 4 (1974), the court held that the PBGC‘s decision was arbitrary and capricious because the “PBGC neither apprised LTV of the material on which it was to base its decision, gave LTV an adequate opportunity to offer contrary evidence, proceeded in accordance with ascertainable standards . . ., nor provided [LTV] a statement showing its reasoning in applying those standards.” 875 F. 2d, at 1021. The court suggested that on remand the agency was required to do each of these things.
The PBGC argues that this holding conflicts with Vermont Yankee Nuclear Power Corp. v. Natural Resources Defense Council, Inc., 435 U. S. 519 (1978), where, the PBGC contends, this Court made clear that when the Due Process Clause is not implicated and an agency‘s governing statute contains no specific procedural mandates, the APA establishes the maximum procedural requirements a reviewing court may impose on agencies. Although Vermont Yankee concerned additional procedures imposed by the Court of Appeals for the District of Columbia Circuit on the Atomic Energy Commission when the agency was engaging in informal rulemaking, the PBGC argues that the informal adjudication process by which the restoration decision was made should be governed by the same principles.
Respondents counter by arguing that courts, under some circumstances, do require agencies to undertake additional procedures. As support for this proposition, they rely on Citizens to Preserve Overton Park, Inc. v. Volpe, 401 U. S. 402 (1971). In Overton Park, the Court concluded that the
We believe that respondents’ argument is wide of the mark. We begin by noting that although one initially might feel that there is some tension between Vermont Yankee and Overton Park, the two cases are not necessarily inconsistent. Vermont Yankee stands for the general proposition that courts are not free to impose upon agencies specific procedural requirements that have no basis in the APA. See 435 U. S., at 524. At most, Overton Park suggests that
Nor is Arkansas-Best, the case on which the Court of Appeals relied, to the contrary. The statement relied upon (which was dictum) said: “A party is entitled, of course, to know the issues on which decision will turn and to be apprised of the factual material on which the agency relies for decision so that he may rebut it.” 419 U. S., at 288, n. 4. That statement was entirely correct in the context of Arkansas-Best, which involved a formal adjudication by the Interstate Commerce Commission pursuant to the trial-type procedures set forth in
IV
We conclude that the PBGC‘s failure to consider all potentially relevant areas of law did not render its restoration decision arbitrary and capricious. We also conclude that the PBGC‘s anti-follow-on policy, an asserted basis for the restoration decision, is not contrary to clear congressional intent and is based on a permissible construction of
It is so ordered.
JUSTICE WHITE, with whom JUSTICE O‘CONNOR joins, concurring in part and dissenting in part.
I join the Court‘s opinion except for the statement of the judgment and footnote 11. In particular, I agree that the anti-follow-on policy at issue here is not contrary to the statute and that the PBGC would not have been prohibited from applying that policy as a basis for restoration in this case. Unlike the Court, however, I cannot read the notice of restoration as relying on the anti-follow-on policy and respondents’ alleged improved financial position as alternative, independent grounds for restoration. The notice, as I read it, clearly rested on both grounds in conjunction. Furthermore, it would make good sense to rely on improved financial position, for without it there would be a risk of an early retermination of the plan. At the very least, there is serious doubt about the matter, and if the Court of Appeals was correct that the PBGC‘s assessment of respondents’ financial position was inadequate-and I think it was-the case should be remanded to the agency to consider whether the antifollow-on plan by itself provides sufficient grounds for a restoration order.
I would therefore reverse the Court of Appeals in part, affirm in part, and remand with directions to return the case to the PBGC.
JUSTICE STEVENS, dissenting.
In my opinion, at least with respect to ERISA plans that the PBGC has terminated involuntarily, the use of its restoration power under
A company that is undergoing reorganization under Chapter 11 of the Bankruptcy Code continues to operate an ongoing business and must have a satisfactory relationship with its work force in order to complete the reorganization process successfully. If its previous pension plans have been involuntarily terminated with the consequence that the PBGC has
According to the Court, the PBGC policy is premised on the belief that if the company cannot adopt a follow-on plan, the employees will object more strenuously (1) in the case of a
In the case of an involuntary termination, if a mistake in the financial analysis is made, or if there is a sufficient change in the financial condition of the company to justify a reinstatement of the company‘s obligation, the PBGC should use its restoration powers. Without such a financial justification, however, there is nothing in the statute to authorize the PBGC‘s use of that power to prevent a company from creat-
Accordingly, I respectfully dissent.