*3 n Before MILLER, BAZE- WILBUR K. FAHY, Judges. LON and Circuit BAZELON, Judge. Commission In the Federal Power Mayor petitions from the received two —one others, City and of Baltimore and Council Public Service Commis- the other from the in- Maryland requesting that sion of — justness and investigation of the stitute charges of of the rates and reasonableness Company Pennsylvania and Power Water Company Susquehanna Transmission Maryland1 regard of their to such energy as of electric sales or transmission Act, 16 subject Federal Power seq. By issued orders U.S.C.A. 791a et 1944, the September October began jurisdiction and Commission assumed LeBoeuf, City, Jr., Randall New York J. petitioners’ rates investigation of Leonard, Craigh with whom Wilkie Bush- requested by the charges. Intervention was City, Raymond Sparks, by, F. York New Commission, Pennsylvania Utility Public Daryal Await, King, Jr., C. G. Preston Commission, Maryland and Consolidat- C., were Myse, Washington, D. on A. Light and Power ed Electric Gas brief, petitioners Pennsylvania &Water Baltimore,2 permitted all were of whom Susquehanna Transmission Co. be- participate hearings and did Maryland. ofCo. hearings, Those the Commission. fore Counsel, Thomas, Pennsyl- 15, 1946, E. April Charles continu- began Commission, Harris- Utility 16, 1947, vania Public extensive July were ed until vice, special Pa., pro leave burg, hac produced voluminous record. nature and Kerrigan, Court, with M. whom Thomas January the Commission issued In Utility Counsel, Pennsylvania Public requiring Penn Water to reduce Asst. its order Harrisburg, Pa., was on charges in accordance with rates and Pennsylvania Public petitioner findings. sched- brief, The revised Utility attempt comply Commission. in an ules submitted order were consider- the Commission’s Wahrenbrock, Gen. E. Asst. Howard and, unsatisfactory on October ed Counsel, Commission, and Federal Power to . as Baltimore referred 2. Hereinafter petitioners referred to as Hereinafter Company. Penn. Water. tract, Harbor’s thirds prescribed its own sched- to receive Safe two the Commission output remaining part one Petitioners and such Penn services. ules for Water’s Water’s January third which is after Penn left review both seek turn, needs are orders, satisfied. In as does October Com- interven- is entitled to receive from Baltimore Utility Public addition, pany steam the extent ed the Commission. before Company’s aside re- parties to set is available after Baltimore have moved same quirements do appropriate alter- met. Nor the orders or obtain of Baltimore Com- contractual entitlements native relief. *4 pany necessarily represent power by used Com- proceedings before the The various disposal hydro Its entitlement is at the it. petitioners’ picture present of a mission system permit the entire in order to of operations to an under- which is essential energy lowest incremental cost us. of now before standing the issues parts used as needed at the various there- operates a both Penn Water owns and granted rights of. In return un- plant hydroelectric generating steam and a Water, der its contract Penn Balti- Holtwood, Pennsylvania, on the at which is Company Water assures Penn of River, Susquehanna some nine miles north operat- revenues sufficient to cover all of its Pennsylvania-Maryland border. of the ing expenses specified and a return on its addition, Penn Water the Transmission and Similarly, both investment. Penn Water Company together constitute intercon- Company and Baltimore assure Safe Har- system interstate nected transmission —with payment bor of a combined annual part owning Penn operating Water yields specified operating return above system of located Penn- is expenses. The function of these con- sylvania Company, and Transmission tracts and of the interconnection of facili- affiliate, Mary- wholly-owned operating the they accomplish is, ties which in the words 1 company, A land facilities. third Safe operations to achieve Corporation, Harbor Water Power owns “closely integrated which are and coordi- hydroelectric operates development economy, efficiency, nated a matter of Harbor, at Pennsylvania, Safe trans- flexibility, hy- and maximum utilization of facilities which also interconnect ”4* * * capabilities dro river Water and Com- Transmission very has a variable flow.5 pany. Company The interest of Baltimore I sys- proceedings these stems from certain have, considering challeng- the various tem foundation contracts which Before order, operations we years, will past-twenty tied its es to Commission’s petitioners’ petitioners motions Harbor. ourselves those Safe and of .address ;to contracts, re- and annul These these set aside order. Under quired provide us on December Baltimore filed with Company were shortly the United States Court of capacity all times with the avail- after hydro Circuit had plants, beyond Appeals at its and steam for the Fourth issued able phases of declaring certain part judgment of it which fulfill is needed to arrangements between Penn its own commitments Those to customers. contractual illegal must, however, Company Baltimore un- previ- customers Water laws and approved by antitrust the laws ously Company. Baltimore the federal der Pennsylvania.6 illegality The these entitled, by Baltimore also con- Commission, Appendix to Petitioners’ 3. referred to as Har- Hereinafter Safe company Brief, p. This 43. bor. affiliated with Penn Company, Baltimore each infra, discussion, 193 F.2d 241. See 5. fifty per voting cent which owns Co. Consoli W. & P. stock. Cir., 1950, 184 Co., G., & E. L. P. dated Opinion the Federal Power No. denied certiorari F.2d supervise every phase raised authorized to almost system first foundation contracts was company’s rehear- of regulated business.7 petitioners petition for in their order, charged utilities, nine- about Rates as well as ing January of the provisions de- the af- services and contractual teen before the Fourth months fecting them, “just The Commis- must be reasonable.” cision down. was handed rehearing, “just rul- And what is and reasonable” is not request for sion denied the pressures competi- alia, validity the determined ing, that the inter of. upon dependent adequacy tion but of the order is not service public, anti- the fairness the return al- legality contracts position is that lowed here investment in the com- trust laws. Petitioners’ pany, requires degree congres- us to which the decision the Fourth Circuit’s objective sional rate order. of efficient use na- the Commission’s to invalidate power tion’s resources is served. Nor was mo by the problem raised Congress problems unmindful of the of un- stat interrelation two is one of the tions field, due concentration of in this dif which reflects utory schemes—each *5 by monopolies. characterized it as is local different pressures and ferent historical In Utility Holding the Public interest. The public conceptions of the Act, seq., provided 15 U.S.C.A. 79 et it § note, 1-7, 15 Act, 15 U.S.C.A. §§ Sherman in- antitrust-like remedies to assure that attempt represent an laws related tegration power companies of be limited competition free keep channels of scope to an efficient power confined determined are prices and services that so area.9 They market. workings of free by the objectives contrasting These great indi that the the conviction derive from cate be that the number can have greatest will antitrust laws good est application regulated monopoly, monopo limited to industries preventing by attained by specific though laws, statutes. Those restraint of combinations in lizing quite properly having viewed as been in is a statute such marked contrast trade. * * * * tended “to make of ours Act. a com the Federal Power II of as Part petitive economy”,10 business con recognition that are not congressional It evidences stitutional mandates which as protection freeze all competition can assure of system, pects of our economic set for all time only in an industrial public interest pattern into the “laissez-faire.” We to a free of is conducive market ting which they may it obvious that which think not be place in industries have no and can economy beyond part public extended grant, monopolies because are- Congress nature, legislative which intended to leave to exigencies pre “Certainly operation of the free market. particular way doing busi ference for a Congress what has forbidden the Sher place competition general as a ness. In * * * modify. man Act it can prices regulator of indirect [It] ized and impotent may not is deal with what it interstate transmis field of services in the wholesale, consequences Con consider of electric dire laissez sion 11 regulatory agency gress substituted a has faire.” ' seq. Century Fund, et 824 16 U.S.C.A. (cid:127)§ Twentieth Electric Pow- Policy (1948). and Government 45 er government relationship of “In competition private Utility is Trienens, businesses most The Act as a Solu 9. See prices upon Problems, in the inter- to control Act 44 relied tion to Sherman Ill.U. consumers, (1949)'; Comment, is but such not Section ests Rev. private Holding Company Act, (b) Com- electric utilities. Yale case of the implies petition (1950). two or more sellers offer- L.J. products ing same or services their South-Eastern States v. Under- 10. United electricity public, and two sellers Ass’n, 1944, 533, 559, writers duplication territory mean same 1162, 1176, 88 64 S.Ct. L.Ed. 1140. Regulation, investment. wasteful and therefore, Adkins, 1940, may general Coal Co. 11. Sunshine sense be said in a competition.” 84 L.Ed. U.S. as a substitute to act competitive consid given con That say effect to is Courts have not to pub components may above erations not be those siderations such outlined parti by a operation sought anti lic served interest to be confining the guide statute, not hence a regulatory to those matters are cular trust laws authority fall exercise of of state product action or commission’s it. question before properly vested in a when the outside the reach of Thus, Com regulatory agency. Congress Thus, or the has been the Federal said that seq., among Act, may arrangements states munications 47 U.S.C.A. 151 authorize et “recognizes broadcasting that the producers though action without field even competition. one free The deal governmental sections sanction and enforcement broadcasting Con ing with demonstrate Simi would violate the antitrust laws.12 scheme, gress not, regulatory has monopolies13 larly, may authorize states principle competition, free price abandoned may Congress susbstitute direct railroads, the case as has done in re by public agency competition.14 fixing spect regulation sup of which involves the practice complained But when pression practices of wasteful due com protected legislative sanction, either petition, regulation of rates charges, directly being a com committed to unnecessary and other measures empowered it, the anti deal competition if permitted.’’16 free is to be trust laws have been relied a mini povides compre But where a statute protecting mal means of interest. regulation par hensive and detailed of a already net effect of what we have industry, ticular as do the Interstate Com that, though regulated said is industries *6 Act, merce seq., 49 et U.S.C.A. 1 and the per exempt are not se from the antitrust Act,17 Federal Power is, there as we have repeals by implication laws and are not indicated, only application area for favored, limited superseded the antitrust laws are of antitrust to Commission by specific considerations regulatory statutes to the of the decisions.18 repugnancy extent between them.15 869, 1037; Brown, 341, 1943,
12.
L.Ed.
Journal
Parker v.
Mansfield
317 U.S.
Co.
350-352,
Commission,
315;
Federal
307,
v.
Communications
63 S.Ct.
L.Ed.
87
U.S.App.D.C.
Royal
1950,
Co-op.,
102,
1939,
86
United States v.
F.2d
Rock
180
28.
Mackay
cf.
&
993,
But
Radio
Tel.
307 U.S.
Co. v. Fed
59
L.Ed.
S.Ct.
83
Commission,
1939,
1446;
App.
Borden,
eral Communications
United
68
States v.
336,
188,
338,
641,
(1938)
201-202,
D.C.
182,
F.2d
308 U.S.
97
643
60 S.Ct.
84
(“Though the
for
L.Ed. 181.
Communications Act.
licensing
bids the
of concerns which vio
Smith, 1904,
332,
13. Olsen v.
195 U.S.
laws,
ap
late
anti-trust
it does not
344-345,
52,
224;
S.Ct.
25
49 L.Ed.
ply
radiotelegraph
to the
business
Evans, C.C.S.C.1895,
Lowenstein v.
F.
69
policy
competition,
contrary
of free
but a
908, 911.
competition
policy. Free
means
all
that
Adkins,
compete.
14. Sunshine
Co. v.
Coal
310 U.S.
are free to
The Communica
395-396,
907,
competition by
60 S.Ct.
view
this
output
licensees with
to limit the
others
preme Court’s statement in Interstate Com-
energy,
electrical
pri
is made one of the
City,
Jersey
merce
Commission v.
objectives
mary
of Part
II.
Section
U.S.
88 L.Ed.
202(a)
imposes
duty
thereof
especially pertinent:
“If upon the
encourage public
Commission to
utilities to
coming
litigants might
down of the order
combine for the interconnection of facili
rehearings
demand
as a matter of
be-
law
circumstances,
Under
ties.
certain
arisen,
cause some new circumstance has
may
order
even
such intercon
observed,
new
some
trend has
or some
regulate
nections and
the rates
con
discovered,
fact
new
there
be little
arrangements
tractual
involved therein.34
hope
process
that the administrative
could
and,
achieved
sought
The end thus
ever be
order
consummated
that would
pres
view,
served
subject
reopening.”
not be
The effect
*8
arrangement
between
Water and
ent
petitioners’
motions
granting
would be
Consolidated,
the most efficient use
disrupt
pattern
regulation
to
a
pub
consistent with
nation’s resources
problems
carefully
to meet the
drawn
complex
cheap power and
lic interest in
in Conserva-
industry.
of a
Appendix
8243(e).
Commission,
205(e),
to
§
27. Section
16 U.S.C.A.
58,
Brief
n. 21.
Petitioners’
P.
R.,
&
Robinson v. Baltimore
Ohio R.
1912,
114,
510,
506,
32
222
S.Ct.
U.S.
section,
(b), pro-
§
That
16 U.S.C.A.
115,
ability
Part
licensees would
II to
sale
pre-
interstate commerce and
the usual
greater
no
effect than would
electric
at
in interstate
situation,
energy
state com-
wholesale
Part
II
under which
commerce,
apply
reg-
shall
ordinarily
but
mission
have
deprive a
energy
its sale
State
under
of electric
or
ulating
activities
the licensee’s
authority
recapture.48 or
lawful
prior
State commission of its
regulatory
own
statute
exportation of
note, however,
now exercised over the
the Third Circuit
We
hydroelectric energy
is transmitted
pointed
has
out
essential sameness
shall
I and II.49 across State line. The Commission
the valuation
of Parts
formulas
jurisdiction
have
facilities for such
position
re
over all
our
view of
energy,
II,
sale
but
is transmission or
of electric
gard
applicability
Part
spe-
jurisdiction, except as
shall not have
unnecessary
the suffi
for us
examine
cifically provided
824-825r
sections
ciency
record
of the evidence
title,
gen-
this
used for
support
over facilities
finding under
the Commission’s
energy or
Pennsylvania eration of electric
over facilities
I
Maryland
Part
that the
only
for the
used in local
distribution
agree. But
commissions are unable to
energy
transmission
electric
in intrastate
question
the event that the
I
should
Part
commerce,
decision,
or over facilities for the trans-
appeal
arise on
our
we note
energy
wholly
electric
consumed
find
that we
examined the record and
by the transmitter.”
support
substantial
evidence
Commis
point.
finding
sion’s
on this
We
examination
are
from an
convinced
the voluminous materials submitted to
properly found
us
the Commission
Ill
part
“integrated
be
of an
Penn Water to
Rejection
petitioners’
view that Part
sys-
and coordinated interstate electric
I furnishes the
authority
sole
for federal
generated
tem.”51
at
Harbor
Energy
Safe
regulation
operations brings
of their
tous
and Holtwood flows south to Baltimore
the contention that all or almost all their and,
times,
energy
Baltimore-generated
at
sales are
intrastate
nature and hence
along
north
moves
the same line to Safe
may
regulated
not be
Part II.
it, together
Harbor
Holtwood where
(1)
is said that
sales
Water’s
there,
energy generated
is delivered
Pennsylvania customers for resale are sales
Pennsylvania
to Penn Water’s
customers.
energy produced
electric
and sold in This movement to and fro is made neces-
Pennsylvania;
(2)
the "back-feed
sary by
varying
electric loads which
generated
Baltimore
to Penn
supplied
at
must
various times
and sold
it to
Water
day.
Susquehanna River,
flow the
customers
its interstate character
loses
hydro
of Penn Water’s
source
when
is received
Penn Water and power,
irregular
is too
to carry unaided
comingled
Pennsylvania-produced
with the
large utility
up-
loads it is often called
energy. Even if these sales of back-feed
Thus, during
on to handle.
the river’s low
are considered interstate,
it is suggested periods, hydro power is scarce
Balti-
they
negligible
portion
constitute so
Company’s
generators
steam
are used
of Penn Water’s total
Pennsyl-
sales to
up”
keep
output
to “firm
constant the
vania customers that
cannot furnish
times,
hydro-
hydro plants. At such
regulation,
the basis of federal
or that
operated only
generators
electric
at the
regulation may
federal
extend
to an peak
and,
off-peak hours,
during
load
portion
allocable
of interstate sales.
impounded
plant
the river flow is
res-
201(b)
subsequent
peak périods.
Section
of the Federal Power ervoirs for
use at
“ * * *
applicable
Act50
Conversely,
makes
during
periods
Part II
when the
Corp.
824(b).
48. See
Safe
50.
Harbor
Power
16 U.S.C.A.
Cir.,
v. Federal
Opinion'No.
Federal Power Com-
179 F.2d
mission, Appendix
Brief,
to Petitioners’
p.
Id.
241
no such
operations,
can be
there
hydroelectric wholesale
Penn Water’s
high,
river is
solely
sale
particular
thing
assigning
heavy
supply the
loads
plants are used to
Each
Pennsylvania.
Maryland
operations
which to
within
Pennsylvania and
both
pool
drawn
supplied by
sale is in
sale
effect
have to be
would otherwise
n integrated interstate
system
hence in-
expensive
generation.
steam
terstate
nature.
carefully coordinated
As a result of the
by the
reached
The same conclusion was
inter-
operations
participants
this
to another
regard
Third Circuit with
reaps the
energy pool, Penn
state
participants
pool, Safe Harbor.
in this
considerable and
benefit
Baltimore’s
pointed
Safe Harbor
The court
out that
constantly
capacity while
available steam
elec-
“part
interstate
large integrated
of a
Company enjoys
the benefits
Baltimore
output
system”
tric
its electric
cheaper hydroelectric energy.
ac-
integrated
“must
an
whole.”53
be treated as
so meshed that
tivities of each are
case, the
the second
Harbor
court
Safe
peak
customers of each
demands of the
sales
again held
Harbor’s
“con-
that Safe
easily
can be met
at all times
with
stitute in fact wholesale sales
interstate
most
then avail-
economic source
they
commerce”
are “delivered to
because
pointed out,
As
has
able.
the Commission
system”.54
integrated
electric
interstate
arrangements
existence have
now
“carefully
worked out” to meet the
evidence
We
find substantial
system
“as
firm
support
needs
the interstate
record
the Commission’sfactual
requirements,
operations
energy
while
in-
findings
regard
to the interstate na
firm,
volving
interchange
emergency
sales. It is
na
ture of
Water’s
energy
are conducted at all times
a dis-
operations underlying the
ture of the
sales
system
patching
dispatch-
controlled
the basis for Commission
furnishes
office
op-
er’s
in coordination
various
legalistic
rather
niceties of ti
action
than
* * *
erating committees.
place
operations
consti-
sale.55 Those
tle
companies
tuent
of this interconnected
petitioners’ rates and services within
bring
system plan and
far in
coordinate
advance the
II of the Federal
reach
Part
Power
steam maintenance schedules which are
not assume
Act. The Commission did
largely upon
predicted
based
flows of
jurisdiction
over
direct consumer sales.
Susquehanna
River and
determina-
“was
to take in
terri
meticulous
availability
hydro
tion of the
energy dur-
held
this Court had
the states
tory which
periodic
ing
steam maintenance outages.”52
reach”56—interstate
at
could
sales
pool,
Because
such an
drawing
wholesale.
steam,
hydro capacities
extensive
:
IV
Water,
of Penn
Safe Harbor and Balti-
exists,
challenges
more Company now
both Penn Wa-
ter
and Baltimore.
have
determination of rate of re
been able Commission’s
satisfy
commitments which
turn and
of the rate
other-
calculation
base
evidentiary
wise be
legal
grounds.
capacities,
outside their individual
on both
Hope
now constituted.
since
Natural Gas57 was de
Given
Ever
such
cided,
challenges
integrated
interconnected and
interstate
in-
.become
p.
Co., 1942,
52.
Id. at
Public
314 U.S.
linois
Service
503-504,
384,
498,
371;
86 L.Ed.
62 S.Ct.
Corp.
53. Safe Harbor Water Power
v.
Jersey Central Co. v. Federal
Commission,
Cir.,
Federal Power
3
124
Commission, 1943,
seq.,
61,
et
319 U.S.
69
802,
F.2d
953,
L.Ed. 1258.
63 S.Ct.
Jersey
54. 179 F.2d at
n.
also
See
Pipe Line Co.
Feder-
56. Cf. Panhandle
v.
Central Co. v. Federal Power Commis
Commission, 1947,
507,
332 U.S.
al Power
sion, 1943,
61,
319 U.S.
242 upon case the Commission
creasingly difficult to sustain. That evidence can such required con- Federal determine what is ‘to assure proposition established that the “ integrity in of the en- Power hound to the fidence the financial Commission is ‘not terprise, to so as maintain its credit and any combination to single use formula or ”61 capital.’ rates’, long attract This “standards formulae determining in so finance facts”62 was effect,’ resting as on stubborn ‘impact’ the ‘total result’ ‘end by satisfied which care- to un- Commission the rate ‘cannot be said be order investigated position fully just Penn Water’s limits unreasonable.’ The set relation to that other con- broad, resulting utilities and deliberately Court are subject that it was less risk than special competence cluded from notions of both companies. most utility The as- conception primar- as rate-making surance it from Baltimore Com- pub- receives ily legislative process. as long So pany, existing presently arrange- e., lic con- interest —i. of investors ments, oper- of revenues cover safeguarded, sumers —is it sufficient seems n expenses ating fair and a return on its in- may stand- formulate own 58 even vestment small removes much of may adopt any ards.” The “Commission amount of risk found ordinarily purposes method of base valuation rate companies. utility refer, To Penn so of the rate order long the end result does, extraordinary risk involved unjust and ‘cannot be to be unreason- said 59 Company’s Baltimore abatement of produces “ade- If a order able’.” rate payments it it to deliver fails if quate expenses operating above revenues because of acts of is illustrate how God depreciation) interest on (including pay carefully really insulated bonds, and, in on the stock dividends vari- substantial risk. Nor general, integrity the financial maintain Susquehanna ability of the flow enterprise”,60 of the will be it dis- not present factor at Bal- substantial risk since us, however, turbed. still remains for Company’s payments timore to Penn Water Com- theory examine dependent upon company’s are not the latter purported to assure that to act output. the realm action within of allow- prove Water’s It does case supported able substan- discretion point higher re than cent tial evidence. 554 Per utility. by the average earned turn Safe Rate a. return Harbor, example, allowed part Turning of Penn first to that per five cent return Commission. On " * * * petition addressed to said, review, Water’s Third return, per argued that the we find 5]4 It would difficult to conceive of .a 63 part proj on that hydroelectric the Commission cent secure ect” and affirmed allowed actual representing similarity bonds of the and stock view the rate order. satisfy the test es arrangements, does not financial investment their market and to above. Hope ap and referred that Penn tablished would seem Water’s risks the fairness of a rate of proximate more than Safe Harbor’s Determination study capital utility. “average” of the requires “a do those of the “Each return business, presents problem.”64 as service an individual utility costs income, stock, proximity on the the Stability and dividends of market and the debt capital en company markets, investments in other returns on light of Only satisfactory earnings risk long history a similar factor. terprises having —all Light Washington Baker, v. v. Co. 62. Interstate Co. Gas Colorado 58. Commission, 1945, U.S.App.D.C. 115, 581, 11, 824 U.S. F.2d 14- 188 88 U.S, 952, 1950, 605, L.Ed. denied S.Ct. 1206. certiorari 571. 199. 63. F.2d at p. Id., 188 F.2d at 18. 59. Light Co., & Power Driscoll Edison 64. 119-120, p. Id., at 15. S.Ct. 188 F.2d L.Ed. page Id., 188 F.2d
243 complex penditures the flashboards go were renewal of these are factors which into experimentation regard testing of in or for of fair return. Under the circumstances improvement to thought flashboards, ex- company, this the of 5}4 Commission periments per applied ultimately rate base and abandoned. to the were cent return bonds, that must re- designed provide cent for record per 3.17 flashboards discloses placed often, 8.64 carried per preferred being a result of 5.21 cent for stock and so water, surplus away part high per in whole or in cent common stock expenditures that therewith had sub think connection “fair.” We the Commission expense properly it its are support operating treated as stantial evidence before phase hence the rate base. the case and not includible in findings this of of fact on need the the test Nor the Commission include in meet that the rates allowed experiments do rate abandoned Hope the Nor do we base down in case. laid upon property manifest useful the not that rate based themselves think return ample public evi- petitioners’ service.66 There is capital historical cost thereof, competi that dence in the record to demonstrate approximation milder experiments capital, part necessary to necessary neither were tive cost of is a these improve- point nor contributed to flashboard that test. think it sufficient We adopted. ultimately ment capital that such as the out studies cost presented Commissionhave with to the one during 2. Interest construction—The too judicial many cases stood review per on allowed 6 cent interest Commission reject prop one as a now before us us period of con- during costs construction rate er criterion of of return. struction in the to be included rate base Rate base b. period that theory “during operating construction ‘there is income that no contend the Com
Petitioners which to meet neces- available with these improperly excluded more than two ” 67 sary charges incident to construction.’ from the amount found dollars million disputes finding property But Penn Water gross investment in to be the it construction for there was cessation of in the service. Com used and useful year depre 22 months during reserve for than six mission deduction of period of attendant investment in arriv construction gross ciation exclusion from rate base interest for ing investment rate base also at net $700,000. period, amounting to propriety over challenged. The a deduc of such objects also regulatory like that exclusion of formula under a tion other losses found the Commission well settled our to be to warrant Part II too traceable the cessation of Nor would Part construction. discussing it this time. interest justify “To require during a different allowance I, applicable, conclus if part the cost proj- construction from the As to items excluded ion.65 appear must ect it that the carried base, the Commission licensee we think acted * * * obligation prosecute out evidence. substantial his properly (cid:127) important diligence.”68 due construction with pnly the more will discuss We Here, the cessation of construction them: was due inability to obtain developement 1. Flashboard costs—The found funds financing after included in the rate base the inadequate. Even if be conceded that the 1912 in 1911and in connection cost incurred time market at the financial of cessation original project installation as unsettled as $50,- construction was Penn Wa- system almost but excluded flashboard expended says, it payers from 1913to 1921. ex-' ter does follow that rate 000 Such v. Corp. Light Puget & & Power Power Co. Harbor Water 67. Sound 65. Safe Commission, 1943, Commission, Cir., Power Power 78 Federal Federal U.S. App.D.C. 143, F.2d at 194. F.2d Light & Power Co. v. Ibid. Cir., F.2d ready should now bear the burden its failure recovered investors provide adequate financing in advance form of charges operating annual ex- project. penses depreciation construction to entire sustain reserve.71 *14 risk of the Such losses are much to a due
business as
from
were
excluded
the losses
V'
the rate
We
Puget
base in
Sound case.
Balti
Commission found that
agree
view,
ex-
$1,733,318
entitled
Company was
to
brief,
pressed in
that “Interest
the idle
on
its
$1,954,261
total rate reduction of
or
investment
financial
due to
losses
it,
by
operations.
dered
based
on
This
inability
operation
go
to
into
as soon as
petitioners
allocation is challenged by
who
physical conditions
normal construction
argue,
alia,
inter
that it
upon (1)
is based
an
permit
recouped
are no more to
incorrect reading
governing
of certain
con
payers
past
years
from
rate
later
than
provisions;
(2)
tract
an incorrect measure
*
*
operation
losses in
generated
cost
steam
energy
3. Claimed' costs
issuance
com- capacity supplied by
Company
Baltimore
from
properties Twenty
mon stock
thousand
Water;
(3)
improper
and Penn
over
—
shares of common stock in Penn Water’s statement of revenues due to Baltimore
predecessor,
Ferry
Company,
McCall
Power
Penn
from
Water.
In view of
part payment
issued as
for certain
were
we
already
have
said about the
what
effect
properties.
repre-
These
are
to
shares
said
upon
of the Fourth Circuit decision
this rate
$500,000 plant
sent
cost which should be proceeding, supra,
233-238,
193 F.2d
there
There
included
base.
was sub-
rate
there is no need
consider whether the
to
support
stantial evidence
the Commis-
to
part
various contracts involved herein are
all
sion’s
that almost
conclusion
shares
arrangement
illegal
of an
declared
acquired
were
one
Hutchinson in a the antitrust laws.
length
transaction which
not at arm’s
(1)
Water’s generating capacity
represented
beyond the
profit
cost of
inadequate
alone is
its
to meet
commitments
properties
part
him. Hutchinson was
to
Pennsylvania
to its
up
customers. makes
pooled properties
group which
of a
part
deficiency
through
use
project
necessary
services
banking
contractual entitlement
one third
to
of Safe
beyond
stock
what
and issued
to itself
and,
output
Harbor’s
extent of a de-
compensa-
proper
to be
found
Commission
thereafter, by
part
ficiency
diversion of
properties and services. Under
tion for
Baltimore’s two-thirds
entitlement
Safe
circumstances, especially
“neith-
since
output.
Harbor’s
The Commissionincluded
any interest
to reduce the
party
er
had
this
Company’s
diversion from Baltimore
capitalization”,70
repre-
the stock
nominal
supplied by
entitlement
energy
Baltimore
paper capitalization
anticipated
sented
to Penn Water for which Baltimore was en-
corporate
profits rather than actual
assets.
against
titled
a credit
Penn Water’s
20,000
exclusion of the
Commission
shares
it.
argues,
cost of
Penn Water
services
merely
resulting from
transaction was
this
nowever,
2:1 entitlement to Safe
water in the
an elimination
stock
output does
Harbor’s
not arise until after
original
as measured
estimated
cost
obligations,
Safe Harbor has met
it
plant.
Water,
shares
with Penn
jointly
to certain
Expenditures
of Penn Water’s
charged
customers.
previously
4.
expense
depreciation
reading
contract
operating
Such
would mean
re-
expenditures
that the
said to be
serve—These
total almost
diverted from
Company by Penn
$100,000. They
properly
Baltimore
Water to
were
satis-
excluded
fy
those
base
customers
because
from
al-
Baltimore’s
Respondent’s Brief, pp.
Federal Power Commission
See
v. Nat
71-72.
Pipeline Co., 1942,
ural Gas
Niagara
Falls Power Co. v. Federal
1037;
86 L.Ed.
Cir., 1943,
137 F.
Washington
Light
Baker,
Gas
Co. v.
2d
U.S.App.D.C.
litigation
Penn
and Balti-
between
entry
aof
to the District Court
the back
Baltimore, asking that
District Court at
declaratory judgment
in accordance
unen-
provisions be declared
arbitration
the
opinion
Appeals for
the
of the Court
enjoined
that Consolidated
forceable and
remand, a con-
Fourth
After the
Circuit.
gave notice
It
proceeding thereunder.
from
as to
District Court
arose in the
troversy
in an
termination to Consolidated
agree-
of the
the invalidation
1931 whether
the
complaint asked that
amended
1927be-
agreement of
ment had revived
entirety.
an
in its
down
agreement be struck
sale
parties
interstate
tween the
applied to the
Thereupon Consolidated
that Con-
energy so
delivery of electric
order and
restraining
for a
District Court
de-
to continued
solidated was entitled
court restrained
February
on
Water,
in accordance
liveries
Penn
Water,
final determination
pending
therein, regardless of
the terms set forth
issues,
in re-
anything
doing
contract
invalidity
amendatory
spect
generation, transmission
by Penn
response
a motion
1931. In
(cid:127)of
disposition
covered
interpret its
Water that the Fourth Circuit
different from
agreement
manner
controversy, that
mandate and settle
per-
followed in
procedure theretofore
opinion on
a second
court delivered
Jan-
District
The
formance of the contract.
uary
1951.7
February
opinion4
on
Court filed
agreement of
court held the earlier
valid,
1950, declaring the 1931 contract
amendatory
revived when
1927was not
directing
proceed.
arbitration to
illegal, and
contract of 1931 was declared
appealed
Penn Water
to the United
terms
former
reiterated in unmistakable
Appeals
States Court of
for the Fourth
was invalid
holding
1931 contract
that the
court,
September
and that
Circuit
opinion,
entirety. In the course
in its
opinion5
handed down an exhaustive
said,
186F.2d at
Fourth
District
reversing
judgment
amendatory contract
into the
entering
appellate
the 1931
Court. The
court held
“
**
*
contrary
public policy
contract invalid
its in-
up
gave
Clayton
and as violative
the Sherman and
producer and seller
dependent status as a
Pennsyl-
Acts
utility
and the
subjected
laws
com-
itself so
electric
opinion,
vania.
the course of
Consolidated
pletely
the dominance of
page
said,
Fourth Circuit
Consolidated’s
after it has been
give
for certiorari was
Supreme
period.
denied
long
on December
Court
therein
so
buried
11, 1950,6
perish
relationship
along
result
with the
of which
case went must
Pennsylvania
constituting
Hessey
al.,
4.
&
Water
Power Co.
Co. and
et
v.
Maryland
Light
of
Consolidated Gas
Commission
Electric
& Power
Public Service
Co.,
Pennsylvania
(two
D.C.Md.,
F.Supp.
v.
& Power
Water
Co.
cases),
S.Ct.
Pennsylvania
Water & Power Co. v.
Light
Gas,
Power Co. v.
Pennsylvania
&
Consolidated
Electric
& Pow-
Water
Light
Co., Cir.,
Gas,
er
Electric
& Pow-
of which it has been made future illegal were the restrictions on the part. activities Penn Water which resulted j|e í}í j|c sfc sfc contract. invalidation of the whole this case and “Throughout the trial of required Therein Penn to obtain Water was motion, pending argument approval enter- before of Consolidated its desire to Penn Water has reiterated any agreement or ing into sale to Con- supply continue electric purchase energy and of electric and solidated; close relation- and in view of the approval be- obtain the of Consolidated ship parties, the existence of between the disposing- making fore or investment equipment the control and interconnecting excess of property having its value bodies, there regulatory rates over its $50,000. were conditions These restrictive the interests is no reason to fear that safeguard Consolidated included in order to Maryland electricity will consumers of performance promises and it in the its the exist- suffer the invalidation through is conceded them the contract that without two utilities. ing contract between the impracticable would have been a declar- “The District should issue Court not have been made.” judg- atory aside judgment (1) setting 1950; (2) and order of March ment Although judgment a court of a final agreements December declaring competent jurisdiction invalidated had thus 29; September June 1931.and the entire contract between effect; and (3) no are void Consolidated, the Federal Power Com- February order of dissolving restraining regarded mission still it as desirable (Emphasis 1949.” supplied.) interest that the facilities of Presumably the District Court at Balti- companies operated two as one declaring judgment entered a more then system. integrated and interconnected agreements between Penn Water opinion, the Being of Commission was effect, as no Consolidated to be void co-oper- understandably anxious no it had been directed do. There interchange use facilities ative equivocation limitation in the Fourth or energy be I think it should have continued. simply hold directive. It did not Circuit’s required parties called in and them to con- provisions, but void the restrictive immediately out contract in work new entirety. agreement in its demned the 1931 form conventional which would accord obviously con- This because court opinions Appeals of the Court of depend- arrangement that the whole sidered the Fourth Circuit. which fettered Penn ed the restrictions however, thought, that the Fourth Circuit paragraphs containing and that the para- condemn the two meant therefore, restrictions, were not sever- agreement graphs pro- the 1931 remainder the contract. able from the hibited Penn buy- Water from selling excerpt appears following from the This and from ing energy increasing re- opinion, 186 F.2d from the Fourth Circuit’s plant investment ducing without Con- agreement, “The 1931 at 936: *20 consent. It solidated’s reasoned that hand, provided that Consolidated should be require the could continuance of the old capacity all the electric and entitled to paragraphs if contract those were elim- available to Penn Water and not inated. This would leave in effect the con- performance disposed of in the otherwise of definition Consolidated’s tractual residual contracts, and in consideration existing of payment type and residual entitlements the. thereof, agreed pay Penn Consolidated But the Fourth Circuit rate. said those of equal operating to its ex- an amount Water closely provisions were so associated with specified of a return on exist- penses, illegal restrictions on the the future ac- facilities, and the cost facili- of new ing Penn that of Water the whole tivities con- depreciation, and Consolidated was less ties invalid. The opinions court’s tract credit for the amount the sales allowed a of abundantly clear its persons. Penn intention to energy by of Water to make strike relationship the Consolidated consti- just which arrangement, down the a entire —not statutes tuted violation of anti-trust the provisions. restrictive ? them when established contract between significant Water It that Penn question should One who considers that that, un- without the Consolidated conceded proposi- indisputable bear in mind three former, the the lawful restraints on per tions are not Regulated : 1. industries impracticable have heen contract would exempt Act. 2. Part se from the Sherman an made. That wotild not have been II of the give the Act does not Com- Power and the re- admission the restrictions that the lift ban anti- the “closely- so mainder the contract were implication repeals by trust As laws. 3. restrictions illegality associated” that favored, only repugnancy clear complete invalidity. if resulted in Even law new results between old and the paragraphs agreement were unlawful way only giving and then the former severable, provisions would remaining repugnancy. pro tanto to extent incompatible Fourth Circuit’s be with the Pennsylvania Georgia Company, Railroad un- free and decision because under them 456-457, U.S. im- competition would still be restrained 1051; 89 L.Ed. United Borden States v. possible. two Welding facilities Company, 1939, seq., 198 et system companies integrated into one —the S.Ct. 84 L.Ed. objective conducive not—is In competition. denying holding the motions and that power, "has the Commission the ma- Ill such jority the court first con- necessarily “system contracts” After foundation cluded that II Power Part of the Federal void, had been held null and impliedly repealed superseded Act had December entered a motion in this court on “ exempt * * * the anti-trust so as to statutes 29, 1950, asking we set that prohibitions their the combination between aside, annul and dismiss the orders of Water Consolidated sought Commission be in these reviewed Commission ordered to continue. alternative, or, proceedings, remand proceedings In in bold relief the these to the Commission order show think- my majority ing and set aside its brothers of instructions annul orders * * conclusion, sought to be reviewed led them I have skele- herein pertinent portion opin- tonized the of their Pennsylvania Utility Public Commis ion: moved this court on sion also December. 29, 1950, problem raised “To dismiss orders “The motions annul sought statutory one of the Federal Power Commission interrelation two 10,239 No. on the schemes —each reviewed Case different reflects pressures concep- the decision historical and different ground United public Appeals for the Fourth tions of the The Sherman interest. States Court Act, 1-7, note, Pennsylvania re- & Power 15 U.S.C.A. §§ Utility attempt represent keep Public lated laws Company and competition prices Electric free Consolidated Gas channels of so Commission v. Company of Baltimore are determined the work- Light and Power services ** * Mary free ings of market. marked Public Commission of Service De Part II (1950), cert. denied contrast statute land, 184 F.2d invalid, null, Power Act. con- renders void the Federal evidences cember competition gressional recognition that can the orders of the Federal no and of effect proceedings protection and the assure interest *21 setting which is conducive pursuant which said industrial to orders an it before place market and can have no free issued.” to a were monopolies are because of industries which presented question by these motions The ** public grant *. have called basic issue: what I objectives indicate contrasting Power Commission law- “These the Federal can only limited laws can have that the antitrust establish between Penn Water and fully application spe- regulated tion of the facilities utilities!. iby industries two to of * * * any But neither that other cific nor sec- statutes. section “ * * * of what we tion Part II the Commission The net of authorizes effect require that, though regulated have to interconnection already said is co-ordina- of exempt from the tion facilities per industries are not se under terms conditions- repeals implication which will a antitrust result violation of the laws and favored, laws are Sherman Act. The are not the antitrust Commission can exer- superseded regulatory cise its of specific and under all § up arrangement Part II repugnancy setting statutes to without extent. * * * which is unlawful between them. where a statute under anti-trust statutes. Fourth provides comprehensive for The intimated much detailed as suggested regulation particular industry, as do when it that the interconnection Act, facilities interchange energy the Interstate Commerce 49 U.S.C.A. seq., “by 1 et Act, and the Federal Power there continued some method that § is, indicated, only approval as we meet with the appropriate limited area of the application regulatory of antitrust considerations and will authority not offend either the utility to Commission decisions.” anti-trust laws or the laws Pennsylvania.” F.2d The [184 568.] generalities These boil down to the thesis opinion majority suggest any does not rea- that Part of the Federal Power Act is II why son cannot be done the Com- repugnant the- and there- anti-trust laws mission. supersedes them to the extent of the repugnancy; repugnancy and that ex- per- Since the Power Commission -can exempt tends far as the anti- so all its form functions under Part II with- trust laws the combination of utilities or- out creating a violation of the Sherman by the Act, dered Commission which other- is there is repugnancy no between the illegal under statutes. clearly wise those statutes, two and no room court ' superseded say that II Part anti-trust point par- The do out with majority not statutes. ticularity repugnancy rely. They “con- to find in the seem said, Circuit, I have as did the Fourth objectives” trasting acts anti-trust that neither Part nor I Part II of the Act, saying and Part II of Power .the purports suspend Federal Power Act designed first was to obtain the benefit respect anti-trust statutes to licensees competition, to eliminate free regulated utilities On the thereunder. .and competition having place utility no as contrary, Sherman sub § Act regulatory field and to substitute for repeated stantially 10(h), found § only repugnancy agency. being the This Act, I Part Power 16'U.S.C. § majority, suggested holding their 803(h), follows: “Combina necessarily is that the anti-trust laws are arrangements, tions, agreements, or under superseded II Act by Part of the Power express standings, implied, to limit the objectives the extent of the two output energy, of electrical to restrain legislation are in Let forms of contrast. trade, fix, maintain, prices or increase any really repugnancy see if there is us hereby for electrical or service are II between the Act Part Sherman prohibited.” the Power Act. Penn Water is a licensee under Part I of former, section The first subject prohibitions the Act so is illegal con- every declares 15 U.S.C. § 10(h). majority considers that § tract, conspiracy in restraint combination or omission that section from Part II or commerce. The-1931 contract of trade only repealed 10(h) not but also amounted Consolidated was Penn Water and between repeal prohibitions the Sher- of that section. held violative companies regulated far man Act as ' saying That Section found in Part II of concerned. amounts Act, empowers apply the Commission to the anti-trust laws do n require regulated industry provisions and co-ordina- unless their the interconnection *22 annul, in ad- regulatory for the motions to repeated substantially denying in the are theory the anti- to that anti- dition the fallacious opposite the is true: the statute. Just regulated in- apply to trust laws do not regulated industries apply laws to trust however, examination, the expressly dustries. exemption is On unless therefrom upon the statute, to rest ground or must additional is seen provided regulatory in the in stated inevitably same It is thus implied provisions of the erroneous idea. be motions opinion: petitioners’ clearly repugnant grant the “To regulatory act time would set at this prohibitions. aside the order to anti-trust be criteria those to antitrust substitute noted, too, must that Penn Water It be * * Act, . the Federal Power under its status as licensee does not lose simply regulated I is also Part because it it would be By this the court meant that nevertheless, continues, It under II. Part improper orders to annul the for- continues to be to a licensee so be “a handed ground on the mere that decision by 10(h) engage in the com- bidden § private parties in a un- down suit between illegal arrangements binations made non-controlling destroyed der a statute” had that, the thereby. when Com- It follows only they arrangement to which could required Con- mission possibly application. If Penn Water combination solidated remain in “wishes,” the Fourth Circuit’s because of courts, condemned which had been decision, change make some old only authority it not did not act under arrangement the Com- contractual power, it no gives of Part II which retained, be the ma- has ordered to affirmatively but also 10(h) violated § say only can do is to sub- jority thing it its own act. basic Then, proposed arrangement. mit new opinion says, however, majority The that disposed of the after Commission has a Part II when a I is also Part licensee .peti- proposal, file Penn Water can a new company, is, longer no it is aggrieved. tion for That review if feels subject provisions anti-trust § Penn Water wanted to would true if 10(h), simply language of because the that legal change existing arrangement. appear section not in Then does Part II. key reasoning The error the court’s repealed by 10(h) the notion that § is revealed its allusion to the decision opinion: Part II is thus stated “ * * * Fourth as one “handed down prohibitions 10(h) of § private parties between suit apply to a which is also licensee non-controlling statute.” It shows that regulated under Part II extent deny- assigning this additional reason prior repealed by not that statute is annul, the court is the motions to still ing repugnancy clear it and later between lawfully assuming Commission can that the statute.” require form a combination these utilities to suppose say I the court meant that legally form cannot their clearly repugnant Part II 10(h) is to § own contract. language not similar because it does contain repealed and therefore im- section already sufficiently think I I have shown plication. repugnant II is But Part not controlling the Sherman is the Act 10(h) that it same reasons is § which the Commission is not em- statute repugnant to the laws: it is not anti-trust powered judgment to override. That necessary for the Commission to cause not invalidating arrangement existing fully 10(h) a violation of in order to ex- private suit between handed down II regulatory ercise its under Part is, parties course, It immaterial. is subject over a Part I licensee which private parties, yet binding those this II regulation. Part disobey required it. has them It court idea phase portion done so erroneous has One superseded by has been opinion motions Act which denies the the Sherman court’s Act and that in which Part II of the so remains to be noticed. statute.” give “controlling another reason purports court *23 rendered, re- it can therefore opinion being it is majority portion In the quire the service discussed, says it is the continued rendition being now the court rates, un- no unlawful. reflecting matter if existing “services and the sub- derlying operations, which were the motions For I think given, the reasons im- ject order.” should to annul order the Commission’s has plication is that all the Commission My have dissent. granted, been and so I ac- prescribe rates service done majority, having denied brothers of the rendered; if the rates tually being explore motions, proceeded then service, just reasonable for order merits of the rate reduction findings in that re- if the Commission’s Com- which the implementing rate schedule evidence, supported by substantial spect are affirmed or- prescribed, those suggest an end.” I review is at “our action, from that I dissent also ders. operations” were the sub- the “underlying orders should have set I think the been ject and therein of the Commission’sorders I improper. prolong do not aside as But They did not deal lies the vice in them. by discussing the this merits dissent contractual with rates but ordered the alone orders, perfectly clear that as I think operations” “underlying to continue. being set aside should without that, boot-strap argument say after the applicability Fourth Cir- basis or pre- because the Commission has judgment long became final. existing scribe rates service so as cuit’s
