12 Pa. Commw. 203 | Pa. Commw. Ct. | 1974
Opinion by
This is an appeal filed by Penn-Jersey Contractors, Inc. (Penn-Jersey) from an adjudication of the Board
Even a cursory review of the record made in this case by one not directly and intimately involved in this rather typical governmental construction project permits one to wonder how a contractor bids on construction for such a project, and how any such project is ever completed without a multiplicity of lawsuits. Typically, the parties to this case, subsequent to the acceptance of Penn-Jersey’s bid, were faced with unanticipated variances which led to typical disputes, e.g., admitted changed site conditions, extras, architectural and engineering changes in design, other contractors prematurely completing work, labor disputes, misunderstandings between inspectors and performers, municipal governmental interference, landowner’s (West Chester State Teachers College) objections, bankruptcy of another contractor, misunderstandings arising out of very technical and complicated specifications and agreements, and even acts of God in the form of precipitation causing impassable mud-filled roadways. It is rather remarkable that in the present posture of this case we are faced only with the few issues presented.
On April 16, 1969, Penn-Jersey submitted a $169,-000 bid to GSA for the installation of certain underground plumbing utilities on a construction project involving new athletic facilities at the West Chester State Teachers College. Penn-Jersey’s bid was based upon not only the specifications and the proposed agreement, but also upon a prior view or examination of the site conditions. On May 6, 1969, GSA declared Penn-Jersey the low and successful bidder, and awarded a contract to it. As part of the instructions to bidders, Penn-Jersey was given the responsibility of a “careful personal examination of the site to satisfy himself as
“The Authority, by virtue of this special meeting, does recognize, under the terms of contract, 414-28’s claim of changed conditions on site. This claim falls into two categories; one being a loss in production efficiency, and the other restoration of finished surfaces. The first category will stand for arbitration. The second (restoration) will be contingent on review of the unit costs and subsequent direction to be issued.
“Any comments or clarification concerning this directive will be accepted; however, work on both 414-28 and 414-32 is to proceed immediately, with proper coordination and no further delay.”
The work did proceed on the project and Penn-Jersey completed same. During the course of the performance twelve change orders were issued by GSA to
After Penn-Jersey appealed to this Court, GSA filed a motion to quash alleging the Board was without jurisdiction over the subject matter because Penn-Jersey had not made its claim within the six months statutory period. The pertinent provisions of the statute involved are found in the Act of May 20,1937 (1937 Act),
At one point in its brief, on another matter, GSA argues bitterly that Penn-Jersey did not submit sufficient notice in writing as required by Section 6 setting forth in detail the specifications of its claim. That pertinent portion of Schedule 6, 72 P.S. §4651-6 states: “The claimants shall advise the department involved, in writing, of such claim, specifying the details thereof, and shall, within the same period, file with the secretary of the board a concise and specific written statement of this claim, signed and verified by the claimant before an officer authorized to administer oaths.” Because this record permits us to conclude that on May 19, 1869 (the date Penn-Jersey notified GSA of the changed site conditions) and on June 19, 1969 (the date of the GSA letter quoted above), Penn-Jersey could not fulfill the detailed statement of claim requirements of Section 6, we hold that Penn-Jersey’s claim did not accrue until such a detailed statement could be prepared. Under the facts of this case, that date was December 16, 1970. We will therefore at the end hereof dismiss the Motion to Quash.
In its appeal to this Court, Penn-Jersey contends that the Board erred in denying its claim in the amount
The last contention of Penn-Jersey is that the Board erred in not making an award in the amount of |400, which claim is based upon that amount being assessed against Penn-Jersey by a subcontractor for two days delay caused by nonaccess to a roadway to the job site. The Board denied this claim based upon paragraph 72 of GSA’s agreement with Penn-Jersey, which in pertinent part states: “72. No claims for increased costs, charges, expenses, or damages of any kind, shall be made by the Contractor [Penn-Jersey] against The General State Authority for any delays or hindrances from any cause whatsoever, including strikes, walkouts or work stoppages during the progress of any portion of the work. . . Penn-Jersey’s argument here is that GSA assumed the work of a defaulting contractor and in performing that work, blocked access to the sole access road to a job site for one of Penn-Jersey’s subcontractors for two days, thereby making GSA liable as a contractor. Initially it must be noted that the burden was on Penn-Jersey to prove its claim. While it is true that paragraph 24 of the general conditions of the agreement between GSA and Penn-Jersey provides, “The Authority shall provide all land upon which the work is to be done with right of access thereto . . .,” our review of this record permits us to conclude that Penn-Jersey did not meet its burden. Penn-Jersey’s proof on this claim merely indicates that there were two days of nonaccess to the job site. There is nothing in the record to indicate the basis for the two days delay except for GSA’s testimony that the reason for the delay was mud caused by rains. Penn-Jersey proved that it paid |400 to its subcontractor for
As directed by Section 8 of the 1937 Act, we affirm the order of the Board as being in accordance with the law.
Order
And Now, this 6th day of March, 1974, it is ordered that the Order of the Board of Arbitration of Claims be and hereby is affirmed, and the Motion to Quash filed by the General State Authority be and hereby is dismissed.