59 Ct. Cl. 892 | Ct. Cl. | 1924
delivered the opinion of the court.
The facts are removed from controversy by a stipulation and the questions for determination are not complicated.
The chief contention arises by reason of a provision in the contract for the assessment of liquidated damages for delay in performance together with the cost of inspection and superintendence during the period of delay, accom-
The Comptroller General declined to accept the finding of the contracting officer as conclusive but considered the facts bearing upon the question, concluded that the delay in the completion of the contract was because of the plaintiff’s failure in the first instance to fabricate the pipe according to specifications, and assessed and withheld $1,550 on account of liquidated damages and $125.30 as expense of inspection and superintendence.
Much has been said in argument on the question of the right of the Comptroller General to review the finding of a contracting officer clothed with powers similar to those given him by the contract in this case, in connection with which the accounting statutes of a century past are cited.
It is not our province to determine the powers of the Comptroller General unless, perchance, action taken by that officer becomes material for consideration in connection with the determination of the rights of litigants when those rights are asserted in this court, and in this instance, while) argument has included a discussion of those powers, we do not understand it to be contended that action by the comptroller could in any way conclude this court in the determination of the rights of the parties under the contract. Contractual rights once fixed in a proper contract executed by authority are inviolate. They may be forfeited by one party or the other, construction is permissible if the terms are ambiguous, but in the absence of ambiguity or forfeiture of rights by conduct, such a contract can not but be enforced as written.
“Provisions in Government contracts reposing in some designated official the right to determine certain questions and making his determination thereof conclusive are of frequent occurrence. Such provisions are inserted largely for the protection of the Government, and the cases in which such a determination by the designated official has been upheld by the courts have been largely cases in which the rule has been invoked in favor of the United States and against the plaintiff, but the rule is none the less effective if perchance it occasionally may operate the other way.”
In the defendant’s brief the rule as stated above in the Gleason case and as applied by this court in the Brinck case, 53 C. Cls. 170, and in the two cases last above cited, is
The statutes referred to are those relating to the accounting system culminating, after many years, in the Dockery Act of 1894, followed by the present accounting act, which embodies the main features of the Dockery Act but broadens to some extent the powers of the head of the accounting-system, now the Comptroller General, and provides reorganization.
If we could conceive it to be the theory of counsel that these acts authorized the Comptroller General to go behind the finding of the contracting officer and review the facts on which it was based and conclude that it was unjustified and therefore of no force and thus substitute his judgment for that of the contracting officer and thereby eliminate from the case the finding of the contracting officer when the rights of the parties are in this court for adjudication, the power of the Comptroller General in that respect would certainly be for our consideration, but while there is contention that the finding of the contracting officer is not binding on the General Accounting Office, we are still unwilling to conceive it to be the intention to carry the contention so far as stated above. It may be suggested that the whole question as to the effect of such a provision in a contract has been fully covered by the Supreme Court, the “last word” on the subject, in many cases, and we find no intimation that there is anywhere any authority to impair the obligations of valid contracts except under circumstances stated.
It is sought to distinguish this case from those cited by the contention that in those cases the authorized officers were finding facts while the officer in this case was reaching a legal conclusion. If the contention could be of any force under any circumstances it is sufficient to say that the determination by the contracting officer that the delay was the fault of the United States ivas the determination of a fact.
Another question is presented. Plaintiff’s claim in the sum of $2,591.80 was settled in the General Accounting-Office and as settled $1,675.30 was disallowed and $916.50 allowed, for which latter sum a Treasury check was sent to plaintiff. Plaintiff made application to the Comptroller General for a review of the settlement and therewith returned the check. This was in exact compliance with the practice under the Dockery Act, when the settlement ivas first made by an auditor from whom, the appeal was to the comptroller, and is perpetuated now with the substitution of a division in the General Accounting Office for the office of the auditor. An acceptance of the check sent would have precluded an appeal or review, as now designated, of the settlement. After the Comptroller General, upon review, had sustained the settlement as made the check was again sent to plaintiff who received it and cashed it, without further protest, and five months thereafter brought this suit. It is contended that by this acceptance without further protest the plaintiff estopped itself from recovery in this court and decisions of this court are cited in support of the contention.
TTe have denied recovery in a number of cases where settlements made by auditors have been accepted without protest and where long delay or other circumstances have justified the conclusion that there was acquiescence in the settlement as made, and we have rather stringently held to the rule, for reasons stated, that there must be some course
The plaintiff did protest the settlement as made. Whether in direct terms of protest we are not informed, but it declined to accept the payment tendered, returned the check to the Comptroller General and asked a review of the settlement, certainly an effective protest. When the Comptroller General affirmed the settlement as made and returned the check to the plaintiff, it had already protested this identic settlement to the General Accounting Office, it Avas left but one recourse, and of this it availed itself without undue delay. BecoA'ery is not precluded on this ground.
Upon the Avhole case we have determined that the plaintiff is entitled to recover and have directed judgment accordingly in the sum of $1,675.30.