210 A.D. 584 | N.Y. App. Div. | 1924
The plaintiff entered into a contract in writing with the Pollock Lumber Company, Inc., by the terms of which the company agreed to build a house for the plaintiff upon property which he owned. When the building was finished the plaintiff was to pay the company $5,600 for constructing the house by delivering to the company the net amount realized upon any first mortgage loan which might be obtained on the premises, and if that amount was not sufficient, by delivering a bond and second mortgage in a sum not to exceed $2,000 to be executed by the plaintiff, and by paying the balance then remaining, if any, in cash. To secure the company the plaintiff was to deliver a deed to the company and the company was to reconvey the premises to the plaintiff free from lien and incumbrance, except taxes and assessments, upon receiving the payments mentioned. As a part of the same transaction, the plaintiff signed and delivered to the Pollock Lumber Company, Inc., his promissory note for $5,600 to enable the Pollock Lumber Company, Inc., to obtain funds for the carrying out of the contract. The note was payable in three months. There was no consideration for the note other than the promises of the Pollock Lumber Company, Inc., contained in the contract, and payment for constructing the house in accordance with the terms of the contract was to constitute payment of the note. All these facts were
Under these circumstances we agree with the learned trial court that the bank was not a holder of the note in due course but that the note in its hands was subject to the terms of the contract and that payment in accordance therewith would constitute payment of the note. The provisions in relation to payment constituted a definite agreement not dependent upon any future compliance with the contract by the Pollock Lumber Company, Inc. When the plaintiff tendered such payment to the bank, he was entitled to a surrender of the note and a reconveyance of the property. (Title Guarantee & Trust Co. v. Pam, 232 N. Y. 441.) The decision in National Bank of Watervliet v. Martin (235 N. Y. 611, affg. 203 App. Div. 390) is not inconsistent with this view when the ground for the affirmance stated in the memorandum of the decision of the Court of Appeals is taken into consideration.
One circumstance, however, remains to be considered. A mechanic’s lien against the property has been filed by the defendant Domenico Giamberardino for $442.72, with interest from July 6, 1923. The judgment which has been entered requires the bank to pay this hen. It was the duty of the Pollock Lumber Company, Inc., under the terms of the contract, to reconvey the premises to the plaintiff free of hens but the bank made no contract in this respect. It did not take the notes subject to defenses which might arise through the failure of the Pollock Lumber Company, Inc., to carry out its contract, but only subject to the agreement as to the payment which was to be made by the plaintiff when the contract was fully performed. The bank as the purchaser of the note “ was not affected by equities that might never come into being.” (Title Guarantee & Trust Co. v. Pam, supra, 457; Tradesmen’s Nat. Bank v. Curtis, 167 N. Y. 194.) Reconveyance by the bank subject to Giamberardino’s hen is ah the plaintiff can require.
The fourth conclusion of law is disapproved; the fifth conclusion of law should be modified by inserting after the words “ water
Hubbs, P. J., Clark, Crouch and Taylor, JJ., concur.
Judgment modified in accordance with the opinion and as so modified affirmed, without costs of this appeal to either party.