55 S.E. 877 | N.C. | 1906
This action is brought by the plaintiffs, citizens of the town of Washington, for the purpose of enjoining defendant corporation from constructing and maintaining a bridge across the Pamlico River, (487) a navigable waterway, wholly within this State, at the said town, for that "said bridge will materially burden, impede and obstruct navigation over said river and will constitute a public nuisance by rendering it difficult to pass said bridge with sailing vessels and floating rafts, barges, and other crafts, which are constantly plying the waters of said stream in their commerce with the said town and counties bordering on the waters of Pamlico Sound." The plaintiff S. R. Fowle alleges that "he is the owner of a large sawmill situated on said river above the proposed bridge, and is engaged in the manufacture of lumber, and is compelled, in the prosecution of his business, to float his logs to his said mill on the waters of said river in rafts and to ship lumber from his said mill in barges. Plaintiffs Pedrick and Rose are the owners of sailing vessels and engaged in the occupation of running the same between the docks of the said town and parts of the said river below the proposed bridge and the counties bordering on Pamlico Sound. Plaintiffs alleged that sailboat navigation will be peculiarly obstructed by said bridge, because of the effect of adverse winds, in the presence of which cannot be done in the space of seventy feet, the width of the draw in said bridge. They further allege that barges and floating rafts will be practically impossible of navigation because of the manner in which they are drawn by tugs, using ropes of such length that they cannot be controlled, but are subject to be dashed against the bridge by side-winds, etc. They further allege that the charter of defendant corporation does not authorize the construction of said bridge at the proposed point. That the construction of said bridge above the docks of the town would fully accomplish the purpose of defendant's charter and but slightly affect the navigation above the town. They further allege that the (488) *372 charter only authorizes defendant to construct a bridge across Tar River, the mouth of which is at a point about three miles above the town of Washington.
The defendant admits that it has begun the construction and proposes to complete a railroad bridge across the river near Washington, at a point where said river is about one-half mile wide and at which there is but one channel of eight feet in depth and one hundred feet in width. That the said bridge is being constructed under the authority of the Legislature of this State and by virtue of authority of the Secretary of War and the Engineering Department of the Government of the United States. That prior to granting such authority, the said Secretary of War investigated and passed upon all matters pertaining to or affecting the navigation of the said river by vessels of every character. That said bridge is being constructed under the rules and regulations specified by the Secretary of War, and will be, when completed, with the draw across the channel of said river, in all respects a modern structure of the most approved construction, and will not interfere with, obstruct or retard navigation by vessels of the character navigating said river. A map showing the channel, piers and construction at the channel, is attached to the answer.
Defendant further avers that the aforesaid railroad running from the city of Raleigh to the town of Washington was not practicable of construction in any other place or in any other manner than that in which it has been laid out, located and is being constructed and that there was no other practicable way of entrance and crossing of the aforesaid river than that which has been adopted by the board of directors, authorized by the Legislature and approved by the Secretary of War, in the (489) place and at the point where it now proposes to construct the aforesaid bridge. That it is admitted that the plaintiff S. R. Fowle is the owner of a sawmill situated on said river, but this defendant avers that his aforesaid sawmill is only one of many mills located above said bridge, and the construction of this bridge will not and has not in any manner affected the aforesaid plaintiff S. R. Fowle in any other way or manner than the general public using said river for navigation; and it is further averred that no sailing vessel can now utilize said channel under adverse winds without the aid of a steam or power craft, and they aver that when their proposed bridge is completed that, instead of a channel 100 feet in width and 8 feet in depth, there will be two channels 70 feet in width each, dredged to a depth of 9 feet for the use of such vessels, and it is denied that the construction of the aforesaid bridge will inconvenience, obstruct, or hinder navigation on said river by any manner of craft, and it is further denied that the plaintiffs or either of them have any peculiar or especial property or interest in the navigation *373 of said river, or would be affected by the construction of said bridge to any greater extent than the general public by reason of the construction thereof, and that either of them would suffer any special irreparable damage thereby.
That in 1903 the Legislature of the State of North Carolina granted to this defendant power to locate, construct and operate a railroad for the transportation of passengers, freight, mail and express, from Raleigh in Wake County; thence in an easterly direction through Wilson County, running near the town of Wilson; thence through Pitt County, running to or near the town of Greenville; thence on the south side of Tar River to some point on or near, across said river in Pitt or Beaufort counties above or near the town of Washington; thence to or near the town of Washington or to some point in an easterly direction to tidewater in the eastern section of North Carolina, on or near the Pamlico River or Sound, as shall be determined by the said board of (490) directors. That pursuant to the power in said charter granted, the defendant company proceeded to lay out, locate its line of railroad as in its charter authorized to do, and at said time located and determined upon the crossing of the aforesaid river at the point at which it now proposes to construct its said bridge; that thereafter, to-wit, after its aforesaid line has been run and located, and after its board of directors has determined upon a crossing of said river at the point designated, the Legislature of North Carolina further extended the rights, powers and privileges of the defendant company by Private Laws of North Carolina, Acts of 1905, ch. 5, ratified 2 February, 1905, to construct said road from the town of Greenville, thence in an easterly direction through Pitt County to or near some point on the south side of Tar River in Pitt or Beaufort counties; thence to or near the town of Washington or to some point in an easterly direction to tidewater in the eastern section of North Carolina, on or near the Pamlico River or Sound, as shall be determined by the board of directors. That undertaking to locate its aforesaid line of railroad, this defendant has made careful examination and has made accurate surveys, and to this end has expended a large amount of money in its attempt to locate its railroad, and that there is no other point at which the crossing of said river can be established consistent with the powers and rights and privileges granted by the aforesaid Legislature; and this defendant avers that the right to build the aforesaid bridge at the point at which it proposes to build the same and the adoption by its boards of directors of this point of crossing the aforesaid river, was in strict compliance and in accordance with the granted power and authority of the Legislature of the State of North Carolina and the general law of said State. That pursuant to the granted authority and power of the Legislature and the authority of the (491) *374 Secretary of War so obtained, this defendant began and is actively engaged in the construction of a railroad about 140 miles in length, and to this end has expended many hundred thousands of dollars, and is now expending many thousands of dollars each day for the completion of its aforesaid railroad. That it has fully constructed about twenty-five miles of railroad, and will have completed the construction of about forty miles more of railroad by 15 January, 1907, and is in the process of constructing the entire line of its railroad. That in its work aforesaid, in the process of completion, this defendant company has been and is acting in good faith, upon the assumption and belief and advice that its aforesaid charter authorized and empowered it to cross the river at Washington as it is proposing to do, and if it were now stopped in the construction of said bridge it would entail a loss upon this defendant company of many thousands of dollars, and each day's delay it may be forced to suffer to gratify the plaintiff and others would be an inestimable damage, and would seriously affect this defendant in carrying out its purposes and plans regarding the development of the eastern section of North Carolina and the completion of its line of railroad for the use and convenience and advantage of all the people of Eastern Carolina.
The defendant further averred that it was amply solvent and able to respond in damages for any injury which plaintiffs might sustain by reason of the construction of said bridge, etc.
The complaint is verified by plaintiff S. R. Fowle, and the answer by C. O. Haines, president.
Summons was issued 24 September, 1906. Pursuant to notice, a motion for an injunction to enjoin the construction of said bridge was heard before McNeill, J., 15 October, 1906. Both parties filed a number of affidavits tending to support their several contentions. (492) Motion for injunction was denied, and plaintiffs appealed. This appeal was argued before us with marked ability and learning, counsel citing authority for the which he based his judgment refusing the injunction.
It will be convenient, in the discussion of the question presented, to support of their several positions. His Honor did not find the facts upon state the uncontroverted facts material to the decision. The town of Washington, conceded to be a prosperous commercial community, containing about 8,000 inhabitants, is located on the north side, we will assume, of Pamlico River, about thirty-six miles above its mouth and (for *375 this purpose about three miles below the conjunction of said river with Tar River. The said river from its mouth to and above said town is navigable. That considerable traffic has been and is now carried on by the people of said town, over said river, with people living above and below Beaufort and adjoining counties. That said traffic is carried on by means of sailing, steam and gas vessels of considerable tonnage; that said river flows by and past the entire length of said town; there are a large number of wharves, stores, warehouses, together with several sawmills to which logs are brought in rafts from above and below said town, and the lumber is carried to market on barges towed by tugs down said river. That these mills and wharves are located both above and below the county (or highway) bridge which crosses said river, abutting on one of the streets of said town, the larger number of said mills and wharves being below said county bridge. The county bridge has a draw of thirty-six feet.
The defendant's resident engineer makes an affidavit to which is attached a map showing the formation of the banks of the (493) river, width of the channel, location of bridge, distance, etc. We find no contradiction, in any material respect, of the statement made in this affidavit. After stating his opportunities for knowing the facts to which he testifies, he says:
"That from a point below the draw of the said bridge, a distance of 2,500 feet, the channel runs a practically straight course, about northwest by north coming up, and southeast by south going down. That the channel continues then in a straight line above the said draw for a distance of 1,300 feet. That any vessel coming up the said river has a direct approach to the said draw of 2,500 feet, and any vessel going down the said river has a direct approach of the said draw for a distance of 1,300 feet. That a direct approach to the draw in the county bridge, which crosses the said river from Bridge Street, in said town, going up the said river, is about 450 feet; and that coming down the said river a direct approach can be made to the said county bridge draw for a distance of about 950 feet. That above the town of Washington the channel becomes more winding and crooked, and there is no point on the river between the town of Washington and the point three and one-half miles up the said river where the channel continues a straight course for a longer distance than 2,400 feet. That affiant has had opportunities of experience and observation in the matter of the construction of bridges across navigable waters, and knows that the bridge now being built by the said company is modern in character and of approved design, and that the draw of the said bridge is of a character recognized by the experts as being safe, convenient and readily opened and closed, and such as is in common use in railroad bridges at this time. That from Willow *376 Point above, the course of the river is very winding, with sharp turns and short stretches of water, and the location of a bridge across the (494) stream above Willow Point would, of necessity, more seriously interfere with the navigation of said river above Willow Point than can the bridge located as is now proposed be to navigation upon the river from Washington to points below. That during the month of September pilings were driven at the points at which will be placed the center pier and end piers of the draw of the said railroad bridge. That from the time of the driving of these pilings until this date there has been left open and clear for the passage of water craft something more than half of the total space that will be provided for the passage of such craft after the said draw is completed. That during this time, that is to say, from the early part of September, affiant has been daily either on the said river or on the shore thereof opposite the proposed draw, and has seen every day numbers of sailing vessels, steamers, gas-boats, tugs and barges, and tugs with rafts of logs in tow, pass through said space without delay, inconvenience or difficulty. That affiant has at times seen a tug with two barges in tow, the said barges lashed together, pass through the said space, and has, at other times, seen the tug with two barges, one behind the other, pass through the said space without difficulty. That during the period of time referred to, the wind has been variable; unusually heavy tides have prevailed, and a considerable portion of the time the weather has been what is commonly called stormy. That the construction of the said bridge, in accordance with the plans, will not have the effect of causing the channel of the river, either at the draw of the bridge or above or below the same, to fill up, but on the contrary, the tendency would be to avoid the result. The plan upon which said bridge is being constructed will leave a space in the channel of the said river not less than seventy feet wide, and another space of the same width, which will become a part of the channel. That the plan attached shows the general elevation of the draw-span of this railroad (495) bridge the depth of the water on each side of the center pier and between it and the two end piers. That upon the plan is indicated the relative location of the center and end piers, the space left open for the passage of water craft and the depth of the water at mean low-water level. That this plan has been made after a thorough sounding and examination of the said river and the bottom thereof, and is correct. That the depth of the water between the center pier and the end pier, to the south, runs from ten feet on the southern edge to twelve feet next the center pier. That the depth of the water between the center pier and the north pier runs from twelve feet and six inches to thirteen feet; and this depth is practically maintained in the channel for a distance of about two hundred feet below the draw and for the same distance above." *377
The defendant's charter, Private Laws 1903, ch. 1, authorizes the company to construct a railroad from Raleigh in Wake County in an easterly direction * * * to or near the town of Greenville; thence on the south side of Tar River to some point on, near, across river in Pitt or Beaufort counties, above or near the town of Washington; thence to or near the town of Washington * * * as shall be determined by said board of directors." The charter was amended by the General Assembly, Private Laws 1905, ch. 5, permitting the road to be carried to Snow Hill, in Greene County; thence to Greenville; thence "to or near some point on the south side of Tar River in Pitt or Beaufort counties," etc.
Defendant alleges, and it is not denied, that prior to the amendment of its charter by the General Assembly of 1905, it "proceeded to lay out and locate its line of railroad, and determine upon crossing the said river at the point at which it now proposes to construct its bridge." That on the day the summons was issued in this action, the bridge was more than one-fourth completed. We omit any reference to the affidavit showing the progress of the work and present condition (496) of the bridge.
Before proceeding to discuss the question whether, and to what extent, the proposed bridge would impede, obstruct or interfere with navigation, we will dispose of the two preliminary questions raised by the pleadings and argued before us:
1. Are the plaintiffs or either of them entitled to sue, that is, have they alleged such special and peculiar damage, different in kind from the public generally, by reason of the construction and maintenance of the bridge, as under the settled principles of law give them a right to sue?
2. Does the charter of defendant road authorize it to construct a bridge over Pamlico River at any point, or is it restricted to the construction over Tar River?
The obstruction or interference with the navigation being a public nuisance, it is elementary learning that no private citizen may sue therefor, unless he suffers some damage which is not common to the public, or, to express it affirmatively, he may sue by showing that he sustained some special peculiar injury, different in kind from the public.Manufacturing Co. v. R. R.,
Plaintiffs Pedrick and Jones say that they own and run sailboats (497) on said river passing from the docks above the proposed bridge into Pamlico Sound, etc.
It is not clear, upon the authorities, whether the allegations bring these plaintiffs within the principle entitling a private citizen to sue in such cases. If we look beyond our own decisions, we find much conflict in the cases applying the rule. We incline to the opinion, without undertaking to discuss and reconcile them, that upon the allegations in the complaint, plaintiff Fowle is, upon the authority of Manufacturing Co. v. R. R.,supra, entitled to maintain the action. Baird v. R. R., 6 Blatchf. (C. C.) 276; Hickok v. Hine,
The right of plaintiffs Pedrick and Jones is much more doubtful. We do not very clearly perceive how their right to use the right of navigation for the purpose of having their boats to pass up and down the river differs, in kind, from that of all other persons. Mr. Wood says: "It is not enough that he has sustained more damage than another; it must be of a different character, special and apart from that which the public, in general, sustains, and not such as is common to every person who exercised the right that is injured." Nuisances, 646. InClark v. R. R.,
We are of the opinion that the plaintiffs, other than Mr. Fowle, fail to show any right to sue. It is not very clear that he has such right, but, as he alleges that he owns and operates a mill on the banks of the river and is, in that sense, an abutting owner, we think, and, for the purpose of passing upon the other questions, hold that the action will lie.
It is held by some courts, and with reason, that a court of equity will entertain a bill to enjoin a proposed public nuisance by one who might not be able to maintain an action at law. "The strictness of the original rule has been greatly modified since the days of Lord Coke," Joyce on Nuisances, sec. 424; Wiley v. Elwood,
In regard to the second question, it will be well to state, as the basis of this discussion, a few elementary principles, before proceeding to consider the peculiar language of the charter. The power to regulate the use of navigable waters in the State, subject to the power (499) in the National Government, is in the General Assembly. The law is thus stated by Battle, J., in S. v. Dibble,
It is suggested that, by a proper construction of the charter, the defendant is restricted to the construction of a bridge across the Tar River, and that the eastern terminus of this river is at Willow Point, about three miles above the town of Washington. Defendant suggests that the point is not the terminus of Tar River, but that it continues, by that name, until it reaches and passes the town of Washington. It is conceded that the eastern terminus of the river is not fixed by any legislation. We do not deem it at all decisive of the right of defendant to cross the river "near" Washington to fix the exact terminus. It is evident from the language of the records and affidavits that, *380
whatever may have been the understanding in the past, the town of Washington is now understood to be located on the Pamlico River. We note that the charter of the Washington Toll Bridge Company, granted 24 December, 1812, empowers the company "to build a bridge across Tar River, above the town of Washington, in Beaufort County, and near the said town, to commence at Bridge Street." Toll Bridge Co. v. Commissioners,
It is well known that in our State other rivers have been called by more than one name in different localities. The purpose of the Legislature was to authorized the defendant to construct a road from Raleigh to Greenville, thence on the south side of Tar River to Washington, which is on the north side of the river, the exact status of which, in respect to its name, is not ascertained. No one doubts that the road was to cross "the river in Pitt or Beaufort counties above, or near, the town of Washington, as shall be determined by the board of directors." These facts are thus settled: it was to cross the river from the south to the north side, to some point "above or near the town of Washington." It is not seriously contended that the road must cross at Willow Point, or that to cross at such point is either desirable or practicable.
We fully concur with the position of the learned counsel for plaintiff in regard to the rule by which grants of power to corporations are to be construed. The authorities cited sustain them. "All public grants are strictly construed; nothing can be taken against the State by presumption or inference." R. R. Tax, 18 Wall., 206; S. v. Freeport,
"We cannot doubt that where an unrestricted grant of power is made *381 to a corporation to construct a road between two points, it carries with it the right to cross navigable waters, if they interfere in a course or route which is otherwise reasonable and practicable, and if the road can be constructed without destruction of the public easement or seriously impairing its convenient enjoyment and use."
The power to cross the river is given by necessary implication. It would be to attribute to the Legislature either ignorance of the geography of the State or a purpose to trifle with an important subject to say that it did not know that to leave Greenville at a point on the south side of Tar River and go to Washington did not necessarily involve crossing some river "above or near Washington."
Having reached the conclusion that the defendant has, by its charter, the right to cross, that is, construct a suitable bridge over the river, the question arises, whether it is restricted to such crossing above Washington. To adopt this construction would be to eliminate the word "near." If the Legislature intended to fix the point of crossing definitely "above" Washington, it was unnecessary to use the word "near." As said by the Supreme Court of Massachusetts: "The first and most obvious suggestion is, that the Legislature did not intend to fix with absolute certainty and precision the point of departure for the new road, which the defendants were authorized to build. In using language which was so vague and indefinite as to leave open for future determination the location of this point, it is clear that, owing to the nature (502) of the ground, or for some other sufficient reason, it was not deemed expedient or necessary to fix it with accuracy. It is also clear that in thus omitting to designate it, it was their intention to delegate the power of locating it definitely to the defendants or their agents, and to vest in them the exercise of the needful judgment and discretion to carry into effect the authority which they intended to grant." Farnham on Waters, 327 (a). Thus, we find in the defendant's charter, power given the board of directors to determine the point of crossing the river — of course, to be exercised within the limits of the grant — "above, near" the town of Washington. This is the usual form in which the termini of proposed railroads are fixed. It is necessarily so, because we know from observation that the exact termini of railroads are never fixed until after the charter is granted; hence, words similar to those found here are generally used, followed by the power to the directors to fix them by survey or otherwise. Justice Bigelow, in the case cited, says: "It follows, that unless the defendants have clearly exceeded the limits of his discretion, and have acted either in bad faith or in disregard of the just limits which by a reasonable construction of the words of the statute should be put on their power to fix the terminus a quo, they cannot be deemed to have invaded the plaintiffs' rights, or be held amenable to process, *382 restraining them from prosecuting their work and constructing their road, according to the plan. * * * They are authorized to commence at a given point, or near it. If they embrace the latter alternative, a wide range is necessarily left open to them. The word "near," as applied to space, can have no positive or precise meaning. It is a relative term, depending, for its signification, on the subject-matter in relation to which it is used and the circumstances under which it becomes necessary to apply it to surrounding objects." Wood, Nuisances, sec. 274.
We think this correctly states the rules of construction, and, (503) applying it to this case, we are of the opinion that it was within the limits of the power conferred upon the directors of the defendant, acting in good faith, and a due regard to the rights of the public, to locate the bridge below the town of Washington.
We are thus brought to a consideration of the question whether the location, in the light of the evidence before us and for the purpose of disposing of this appeal, is reasonably necessary to the accomplishment of the purpose for which the power is granted, and whether, in the light of such evidence, we can say that it is reasonably practicable to locate the bridge above the county bridge. We concur with the plaintiff in saying that if the location of the bridge below the town will create a nuisance, and if defendant reasonably can accomplish the same purpose by placing it above the town, the charter will be so interpreted as to confine it to such location. 16 A. and E., 1001 (1 Ed.).
In Hicks v. Hines,
We have held at this term, in Thomason v. R. R., that power conferred upon a railroad company to construct and operate a railroad must be exercised with due regard to the rights of the public and of the owners of property abutting or near to the road. In Met. Asylum Dist. *383 v. Hill, 6 L. R. (1880-81), 193, the jury, upon an issue submitted, found that the erection of the hospital for the reception of smallpox patients would be a nuisance, endangering the health of the persons living nearby. It was ruled by the House of Lords that the language of the statute did not authorize the establishment and maintenance of the nuisance.
The power being in the Legislature to authorize the obstruction of a navigable stream by the erection of another highway, as a county bridge or a railroad bridge, the courts will not undertake to control the exercise of the power. The question whether the proposed bridge, if an obstruction, is necessary for the public convenience, is for the Legislature, but in interpreting statutes, by which it is claimed the power is conferred, the courts will apply the rule of strict construction and interpret them upon the theory that the Legislature did not intend to confer power to unreasonably or unnecessarily obstruct the highway or navigation. Farnham on Waters, sec. 1296.
For the purpose of deciding the controverted questions of fact, necessary to dispose of the motion for an injunction, in no manner affecting the rights of either the State or such persons as may be entitled to sue, to have these questions in some appropriate action decided by a jury, we are confined to the complaint and answer, together with the affidavits and exhibits filed. It is not seriously contended that the proposed bridge will obstruct, that is, altogether prevent, boats, barges or rafts passing up and down the river, or that in the mode of its construction, in respect to the draw and the caisson, upon which it rests, the most (505) approved methods have not been adopted. The objection is directed to the location of the bridge, and not to its kind or construction. It is alleged, and not contradicted, that it is being constructed in accordance with the plans and specifications of the War Department and its engineers. The power to compel the management of the bridge after its construction, by requiring the draw to be kept open at all proper times, the removal of rafts or debris, the dredging of the channel, if found to fill up by reason of the caissons, and in all other respects in which the public welfare, interest and safety is involved, is ample in both Federal and State governments. We are, therefore, to eliminate all other questions and consider the testimony only in regard to the location. We find, upon an examination of the authorities, a recognition of the principle that where two rights exist, public as well as private, they must be used and enjoyed in the light of the maxim "Sic utere," etc.People v. R. R., 15 Wend., 134. The rule laid down by Mr. Farnham, and which we think correct, is: "As commerce upon land has increased and become more important, its requirements have modified to some extent the old rule which prevented any interference whatever with navigation rights, and each right modifies the other; so that the obstruction to *384
the navigation will not be regarded as unreasonable and a nuisance, unless it is material and unnecessary in view of the requirements of the land traffic." 2 Waters, 1290. He further says: "If a bridge is necessary for the convenience of the public, and does not prevent the free use of the stream as a public highway, although causing some slight inconvenience to those who had been in the habit of navigating the stream by obliging them to take some additional precautions in passing it, it is not necessarily a nuisance. The fact that the channel is somewhat abridged, or that vessels are delayed to a slight degree, does not render the (506) bridge a nuisance." Mr. Justice McLean in Works v. R. R., Fed. Cases, No. 18046, says: "A draw-bridge over navigable water, although it unavoidably occasions some delay in passing it, is not necessarily such an obstruction to the navigation as to amount to a nuisance. The delay is submitted to in consideration of the benefits conferred." The discussion of the Judge in this case is enlightening and apposite to the one before us. "To constitute nuisance, the obstruction must materially interrupt general navigation." S. v. Wilson,
We have examined with care the affidavits filed in the case. Eliminating the complaint and answer, we find an irreconcilable conflict ofopinion in the affidavits, while there is but little of fact. Seventeen persons who either own or operate sail, steam or gas vessels and boats on said river, express the opinion that the proposed bridge will seriously impede, impair and obstruct navigation. Twenty-one persons who say that they are in the same position to form opinion, are equally explicit and positive in expressing the opinion that the proposed bridge will not materially burden, impede or obstruct navigation upon the said river, nor will it seriously interfere with or tend to diminish or discourage commerce upon the said river. Each of the affiants gives the reason upon which their opinions are formed. It is impracticable for us to (507) discuss them in detail; we are not sufficiently familiar with the questions involved to do so intelligently. We take, merely as illustrating the divergence of opinion, the affidavit of Mr. Bell, who says that he is sixty-two years of age and has been for many years engaged in navigating the river. His opportunity is evidently good for forming *385 an opinion. He says that the bridge will seriously obstruct navigation, giving his reasons therefor. Captain Springer, on the other hand, says that for twenty-five years he has navigated the river. He says that in his opinion no such result will follow. Both appear, from their affidavits, to be intelligent, honest men. They are a fair sample of the other affiants. A large number of citizens engaged in all kinds of occupations and professions express divergent opinions. If we were controlled in our judgment by numbers, the defendant would have the advantage.
Recurring to the parties to the action, we note that the complaint used as an affidavit is not verified by Mr. Pedrick or Mr. Jones. The affidavit of Mr. Haines is very full and explicit; he has large opportunities for knowing the conditions, and his opinions are entitled to much weight. Mr. Packard, an intelligent and evidently well-informed man and resident engineer of defendant, says that he has unusual opportunities for observing the character and class of commerce carried on upon the river. That he has made careful sounding examinations and surveys for the purpose of ascertaining the depth, width, character and course of the channel for a distance both above and below the town of Washington. He gives the result of his work as stated herein. He says that during the month of September pilings were driven at the points at which the center pier and end piers of the draw will be located. That from the time of the driving of the pilings to that of making the affidavit there has been left open something more than half of the total space that will be provided for the passage of boats when the bridge is (508) completed; that during this time he has been daily either on the river or the shore opposite the proposed draw, and has seen every day numbers of sailing vessels, steamers, gas boats, tugs and barges and tugs with rafts of logs pass through said space without delay, hindrance of difficulty. That during said time the wind has been variable, usually heavy tides have prevailed, and for a considerable portion of the time the weather has been what is commonly called stormy. Captain Mohan says that he is engaged in navigating the river, transporting lumber and general freight to and from Washington and Philadelphia and other northern points. That his "barge is a vessel of 432 tons, 183 feet and 7 inches on keel and about 190 feet and 10 inches beam and about 12 feet deep," and one of the largest which "comes into these waters." That barges can be navigated through the draw in the proposed bridge without difficulty, and that the bridge will not impede, burden or obstruct navigation. He gives the width of draws and manner of construction of bridges over a number of navigable rivers between Washington and Philadelphia, showing that the draw in the bridge in controversy corresponds with many others. He says: "Affiant does not know of any draw-bridge across any river in North Carolina that is more easy of *386 access and less difficult to pass through, or that constitutes less of an obstruction to navigation than will the draw-bridge now being constructed by defendant."
In the light of this conflict of opinion and in view of the fact that courts of equity are cautious in interfering with a public improvement upon an allegation of apprehended injury, we would hesitate to enjoin the further construction of this bridge. Judge McLean in Works v. Junction Co., supra, a controversy much like this, says that where (509) the evidence is equally balanced "the preventive and extraordinary remedy invoked ought not to be given."
Several witnesses express the opinion that it would be practicable for defendant to locate its bridge above the county bridge. The testimony in this respect in conflicting.
In Barnes v. Calhoun,
In Attorney-General v. Lea,
There is another view of the case pressed upon our attention. It appears that the defendant made contracts for the construction of the bridge and expended large amounts of money in the preparation for its placing; that for several months it was at work thereon. That pilings were driven, the foundation of the structure made and, as one witness said, about one-fourth of the work done before any application was made for an injunction. It is said in reply to this that plaintiffs had made application to the Attorney-General to institute suit, and were awaiting action by him. While the delay in bringing the action is not controlling in our minds, we cannot disregard the facts in the record. It is manifest that the question of the location of the bridge has been (511) discussed by the citizens of Washington and the defendant for some time, and that there is a division of public opinion in regard to it. The reports of Captain Johnson of the engineer corps show this. The surveys were being made and many and most unmistakable steps were taken showing that defendant had selected the location for the construction of the bridge. The observations of the Chancellor in Eaton v. R.R., supra, in this aspect of the case, are in point. It may be proper to say that we do not concur in the view pressed by defendant, that the decision of the Secretary of War permitting the location of the bridge is conclusive. The control of its navigable waters is with the State, the authority of the General Government being only cumulative protection from an interference with commerce. R. R. v. Ohio,
Upon a careful review of the evidence and authorities, we concur with his Honor, and his judgment must be
Affirmed.
BROWN, J., did not sit on the hearing of this case.