603 F.2d 171 | Ct. Cl. | 1979
delivered the opinion of the court:
The question in this case is what damage did plaintiff, a shipbreaker, suffer when the Government breached its contract to sell plaintiff a 30,000-ton surplus World War II aircraft carrier for scrapping. In an earlier decision, Peck Iron & Metal Co. v. United States, 204 Ct. Cl. 381, 496 F.2d 543 (1974), we concluded the Government had breached its contract and that plaintiff was entitled to recover. The determination of damages was reserved for further proceedings under Rule 131(c). Trial Judge Spector awarded plaintiff $565,794. Because key elements of the trial judge’s opinion are unsupported by either the findings of fact or other record evidence, that award cannot be sustained. We conclude plaintiff is entitled to recover $1,963,817 and award judgment in that amount.
Essentially there are two methods which can be used to measure plaintiffs damage in this contract breach situation. First, calculations can be performed showing the cost of dismantling the vessel and subtracting these costs from the probable value and receipts obtainable from sale of the vessel’s salvageable steel, metal, and equipment. Plaintiff submitted such a calculation at trial and it was found by the trial judge to constitute "precise and detailed proof * * * virtually uncontradicted in the record. Defendant’s response is general and largely conjectural.” The trial judge also stated that "figures pressed by plaintiff in this proceeding are the only figures in the record which are supported by detailed and specific proof.” After some minor adjustments of plaintiffs figures, the trial judge concluded that under this method plaintiff would be entitled to damages of $1,950,122.73. The second method of determining plaintiffs damage is to measure it according to the profits made by the actual salvager of the ex-Franklin, Portsmouth Salvage Company. Though it was recognized "the precise amount and even the order of magnitude of that profit is much in doubt” and that Portsmouth’s records were incomplete, the trial judge believed this calculation to be a superior gauge of what plaintiffs profit would have been. Largely on the testimony of Mr. Jacobson, Portsmouth’s president, that Portsmouth realized more than $400,000 from salvage of the carrier, the trial judge estimated Portsmouth’s profit from the ex-Franklin project to be $475,000. After an adjustment to compensate for the difference in purchase price between Peck’s breached contract and the contract performed by Portsmouth, the trial judge concluded plaintiff suffered $565,794 in damages and recommended this award. 28 U.S.C. § 2503(b) (1976); Ct. Cl. Rule 134(h).
The central issue in this case then is which method of calculation provides the most reliable method for estimating Peck’s probable profits from scrapping the ex-Franklin. Because of the particular facts and circumstances here, we believe that the best method by far is to determine the
Before proceeding to a particular analysis of Peck’s costs and benefits, it is appropriate to discuss more thoroughly the reasons for choosing this method of calculation over the alternative method selected by the trial judge, i.e., estimating what Portsmouth’s profits on scrapping the ex-Franklin actually were. Such estimating presents a host of problems which were carefully examined by the trial judge. First, it appears Portsmouth was engaged in other ventures while scrapping the ex-Franklin, including the sale of material from certain coal piers and the completion or beginning of other scrapping projects. All during the time it worked on the ex-Franklin, Portsmouth pursued its usual day-by-day business of peddling scrap. Second, it is undisputed that as of 1970, even 1976, between 40 to 55 percent of the material from the ex-Franklin still remained unsold at Portsmouth’s facilities. While this fact does not necessarily lessen the value ex-Franklin material would have had to Peck, it certainly complicates the chore of attempting to estimate what Portsmouth’s profits on scrapping the ex-Franklin were, based solely on Portsmouth’s tax returns for 1966-70. The fact of this unsold material could indicate either difficulties in sale or a
Nevertheless, the trial judge concluded Portsmouth realized a net profit of $475,000 from the scrapping of the ex-Franklin. This conclusion was drawn solely from the testimony of Mr. Jacobson, Portsmouth’s president, that Portsmouth made a profit of more than $400,000. When pressed for a more specific figure, Mr. Jacobson stated, "Now how much more, that I don’t know. I really don’t.” The trial judge reasoned that since Mr. Jacobson indicated Portsmouth’s profit was more than $400,000 he must have meant it was necessarily less than $500,000. Therefore, the trial judge concluded Portsmouth made a profit of $475,000 on salvage of the ex-Franklin. We cannot accept this logic. The court has carefully examined Mr. Jacobson’s testimony and finds it wholly insufficient to support the conclusion that Portsmouth made a profit of $475,000 from scrapping
I. Scrap Value of the ex-Franklin
The first step in determining plaintiffs damage is to calculate the value of the material and equipment obtainable from the ex-Franklin. This figure includes estimation of the weight, in tons, of the various metals and steel constituting the vessel, ferrous and nonferrous, and assigning a value per ton of available material. It is also necessary to decide what value, if any, is attributable to the fact that the Government found unsuitable for its purposes certain steel plating it had required both Portsmouth and Peck, by contract, to specially cut and return to the Government. Because the Government had no need for the steel plating, it sold it back to Portsmouth at allegedly a fraction of its market price. Plaintiff contends it deserves $106,218 for the benefit it would have received from the discovery this armor and steel plating was unsuitable for the Government’s purposes. This benefit value also includes the value of major items of salvageable equipment on board the ex-Franklin and here there are two subjects of dispute. First, plaintiff complains the trial judge failed to assign a value to a full storeroom of spare parts, allegedly
Value of metals and steel: ferrous and nonferrous. It may be thought that calculation of the kind, tonnage, and value of the metals comprising a vessel weighing approximately 30,000 tons would be a difficult task. The chore has been made easier in this case because the ex-Valley Forge, a sister carrier of the ex-Franklin, was sold for scrap to a shipbreaker in Richmond, California, in 1971. On the basis of the materials recovered from the ex-Valley Forge, a reasonable approximation can be made as to the quantities of nonferrous metals on board the ex-Franklin and available for recovery under the terms of plaintiffs contract. Had plaintiff scrapped the ex-Franklin, it would have obtained the following quantities of nonferrous metals:
Net tons
No. 1 copper. o If)
No. 2 copper. O IG i-h
Monel. 45
Cupro-nickel. 255
Hi-grade brass. o o Tf 400
Red brass. © oo 80
Yellow brass, admiralty, manganese brass.. 120
Total. 1,200
Based upon plaintiffs actual sales of metals during the period it would have scrapped the ex-Franklin and the average selling prices for the metals at that time, the quantities of nonferrous metals listed above would produce
No. 1 copper. $192,900
No. 2 copper. 167,196
Monel. 53,100
Cupro-nickel. 321,300
Hi-grade brass. 447,200
Red brass. 70,800
Yellow brass, admiralty, manganese brass.. 62,400
Total value nonferrous metals.$1,314,896
Ferrous metals. The following quantities of the comparatively less valuable ferrous metals were on board the ex-Franklin and available for recovery under the terms of plaintiffs contract:
Long Tons1
No. 1 ship scrap. 10,645
Rerolling ship plate. 7,500
Armor plate (nickel bearing). 379
Total. 18,524
Sale of these materials during the time plaintiff would have scrapped the ex-Franklin would have produced the following dollar amounts:
No. 1 ship scrap. $361,717
Rerolling ship plate. 363,075
Armor plate (nickel bearing). 56,850
Total valúe ferrous material. $781,642
Our figures estimating the quantity of ferrous metals differ from the trial judge’s in one major respect. As noted, under the terms of the contract, plaintiff was to cut and prepare but return to the Government approximately 5,000 long tons of steel plating for use as radiation shielding. When the ex-Franklin was actually scrapped, much of this "save list” steel plating was found unsuitable for use as shielding and sold back to Portsmouth. The trial judge gave plaintiff credit for some of this unsuitable steel plating, determining that approximately 2,773 long tons would be available for plaintiffs own sale. We believe the proper
The third component of value, in addition to probable receipts from disposal of nonferrous metals and ferrous metals, is the value of the salvageable equipment on board the ex-Franklin. As noted above, it was Jacobson Corporation, a sister company of Portsmouth, which sold this equipment from the ex-Franklin. Since no records from Jacobson Corporation were submitted as evidence during trial it has been necessary to rely on other evidence to ascertain the value of these items. The major items of salvageable equipment on board the ex-Franklin with ascertainable value were:
Air & refrigeration compressors. $ 7,500
Boilers (8). 22,500
Diesel pumps (4). 6,000
Distilling plants (2) 40,000 gal. per day 50,000
*48 Electric motors . 7,500
Machine tools:
14" Reed-Prentice lathes (2) .$7,500
16" Nebel machine lathe. 4,000
Cincinnati radial drill. 2,250
Kearney-Tucker milling machine.1,500
14,750
Motor generator sets, 125 kw. (2) . 6,500
Pumps (feed water, fuel, & gasoline). 12,500
Switchgear & motor controllers. 22,500
Valves:
Brass--75 net tons.$75,000
Steel — 250 net tons. 75,000
150,000
Van-axial fans. 270,000
Watertight doors. 9,000
Windlasses, winches, & capstans . 12,500
Total. $591,250
This is the finding of the trial judge, with which we agree. But plaintiff has two objections to this finding. First, plaintiff complains that no value has been assigned to a full storeroom of spare parts on board the ex-Franklin worth at least $20,000. Though plaintiff cites portions of the record allegedly supporting the $20,000 figure, a careful reading shows this value does not relate exclusively to spare parts. The most specific testimony addressing the issue was given by Mr. Jacobson who stated, "I remember in the way of big equipment we sold the machine shop for some twenty thousand dollars.” [Emphasis added.] Now the storeroom of spare parts may have been part of the machine shop, but the record does not demonstrate it was the entire machine shop. The record is unclear. Under these circumstances it was reasonable for the trial judge to refuse to assign an independent value to the spare parts storeroom.
Plaintiffs second objection relates to the value of certain "nonsave list” items associated with the "save list” turbogenerators which plaintiff was to remove and return to the Government. The facts surrounding this auxiliary equipment are detailed in the court’s first decision on
In summary, given the quantities set forth above, the average market prices during the time these metals would
Nonferrous metals. $1,314,896
Ferrous metals. 781,642
Salvageable equipment. 591,250
Nonsave list items removed by Government. 110,000
Total. $2,797,788
II. Estimated Costs of Procurement and Dismantling
The figure of $2,797,788 is only the estimate of gross receipts and total value of the material on board the ex-Franklin. To arrive at an estimate of the total benefit plaintiff would have received had the Government not breached its contract, it is necessary to subtract from this figure the sums plaintiff would have expended in purchasing the vessel, towing it to its yard and reducing it to scrap in disposable form. The procedure by which this is done is to first arrive at an estimate of how much it would have cost plaintiff, per net ton, to scrap the ex-Franklin. As illustrated below the best estimate is a cost of $23,188 per net ton. This figure is then multiplied by the total net tonnage of material (both equipment and metallics) comprising the ex-Franklin which plaintiff would have had to prepare as scrap. Finally, there is a question raised by the trial judge and disputed by plaintiff of whether the sums spent by plaintiff toward scrapping the ex-Franklin prior to the Government’s breach, $79,702.62, have been included in the cost per ton multiplied by total tonnage calculation or whether these costs are to be added on to plaintiffs cost of performance.
Contract award price and towing costs. There is no dispute that plaintiff would have been required to pay the Government, under its contract, $137,206 for the right to scrap the ex-Franklin. Nor is it questioned that plaintiff would have incurred $28,000 in towing costs to bring the ex-Franklin from its berth in Bayonne, New Jersey, to its yard in Portsmouth, Virginia.
Support for the estimate of the need for a 17-man scrapping crew is found in the fact that when Portsmouth actually performed the scrapping of the ex-Franklin it used a maximum crew of 15 men. The figure of 120 tons of scrap per week is similarly supported since when Portsmouth scrapped the ex-Franklin, it produced a minimum of 26,000 net tons of scrap in 3 % years or at a rate of 142.8 tons per week. Viewed in this perspective, the estimate of a 17-man crew producing 120 tons per week is more conservative and would in fact be a more expensive estimate of the project’s cost than as experienced by the actual scrapper of the ex-Franklin.
The wages for plaintiffs employees during the year it would have been dismantling the ex-Franklin were:
*52
Based on an average of the above pay rates, these workers would have been paid the following amounts for a 40-hour week:
Hence, Peck’s direct labor costs in scrapping the ex-Franklin would have been $1,240.44 per week to generate 120 tons of scrap. To arrive at a total per ton cost figure, it is necessary to add to the direct labor costs a percentage thereof as a factor representing administrative and mechanical expenses. Then to this subtotal figure is added another percentage, which represents all other costs which would have been incurred during contract performance. Accepting the percentage figures as found by the trial judge, the following computation results:
Direct labor costs.$1,240.44
Add 20 percent administrative and mechanical expenses . 248.09
Subtotal (labor costs). 1,488.53
Add 86.93 percent of total labor costs for other expenses. 1,293,98
Total expenses per week.$2,782.51
Defendant protests strongly against acceptance of this figure of $23,188 per ton, yet does so only in general and vague terms. Defendant urges that the $50 per ton cost estimate of its expert, Boyd Outman, a consultant for scrapping operations, should be accepted instead. Mr.
Next it is necessary to multiply the cost per ton figure by the number of tons of material plaintiff would have been required to prepare as scrap under its contract. The trial judge selected a figure of 29,000 net tons, the approximate total weight of the ex-Franklin. Plaintiff protests the correct figure should be the total number of recoverable tons, a figure closer to 26,000 net tons, the difference
Net tons
Nonferrous metals. 1,200
Ferrous metals. 26,5212
Equipment. 1,1202
Total tonnage of material to prepare as scrap. 28,841
With a figure of 28,841 net tons of scrap material, we arrive at a total dismantling cost of $668,765. Thus, plaintiffs total performance costs may be summarized as follows:
Contract award price.$137,206
Towing cost. 28,000
Dismantling costs. 668,765
Total cost of performance.$833,971
To this figure the trial judge added $79,702.62, sums plaintiff expended preparing to scrap the ex-Franklin prior to the Government’s breach. The question is whether these expenses were in effect capitalized and thus already included in the figure for total costs of dismantling based on direct labor costs. Exhibits introduced at trial and trial testimony indicate this sum consisted of money for employee wages, equipment expenditures, and installation of track for preparation of the berthing and dismantling sites. They are either depreciable capital expenditures or regular expense items as wages. It has been demonstrated above that the 86.93-percent addition to direct labor costs encompasses all other expenses which Peck would have
A summary of the above figures provides the final damage sum.
I. Value of materials obtainable from scrapping the ex-Franklin under plaintiffs contract:
Ferrous metals. $781,642
Nonferrous metals.1,314,896
Salvageable equipment. 591,250
Nonsave list items removed by Government. 110,000
Total value.$2,797,788
II. Costs of procuring and dismantling the ex-Franklin:
Contract award price. 137,206
Towing cost. 28,000
Dismantling costs. 668,765
Total cost of performance. 833,971
Total damage to Peck from breach of ex-Franklin contract by the Government.$1,963,817
Award of $1,963,817 is indeed a large award. Yet if we are to base our decision on record evidence, we can reach no other conclusion. The special circumstances encountered in presentation of this case to the court, which we have reviewed, significantly affect the amount awarded. Finally, we note that the trial judge performed calculations similar to those contained herein, from which we have drawn heavily, and arrived at a similar damage figure. But the trial judge rejected this detailed evidence in favor of the comparatively weak and general testimony regarding Portsmouth’s profits given by Mr. Jacobson. This we find untenable and choose instead the more reliable method of damage calculation set forth above.
Upon the foregoing opinion, containing the necessary findings of fact which are made a part of the judgment herein, the court concludes as a matter of law that plaintiff, Peck Iron and Metal Co., Inc., suffered damages in the amount of one million nine hundred sixty-three thousand eight hundred seventeen dollars ($1,963,817) as a result of defendant’s breach of contract to scrap the ex-Franklin, and judgment is hereby entered for plaintiff in that amount.
A "long” ton equals 2,240 pounds as distinguished from a “net” or “short” ton which equals 2,000 pounds.
Figure converted from long-ton figure.