111 Ga. App. 604 | Ga. Ct. App. | 1965
The petition affirmatively alleges and admits payment of a portion of the contract price, and seeks to recover the balance allegedly due for completion of West’s performance. We thus construe the petition as, suing for the final payment due under the agreement.
The construction contract for breach of which plaintiff seeks to recover is attached as an exhibit to the petition. It sets out an agreement that plaintiff would perform certain work “in strict accordance with” plans prepared by a firm denominated as “Architect.” Other provisions- of the contract especially material to a consideration of the defendants’ general demurrers are: “All work shall be done under the direction of the Architect and his decisions as to the true construction and meaning of the drawings and specifications shall be final . . . Contrae
If the language quoted from the contract is construed as conditions precedent, the petition is fatally defective. Where the existence of a condition precedent affirmatively appears from the petition and exhibits to the petition, the failure to allege fulfillment of the condition precedent or legal justification for nonfulfillment renders the petition subject to general demurrer. Sellers v. City of Summerville, 208 Ga. 361, 366 (67 SE2d 137); Grahn Constr. Co. v. Pridgen, 49 Ga. App. 720, 722 (176 SE 656); Jenkins v. Gordy, 105 Ga. App. 255, 256 (124 SE2d 303); 5 Williston, Contracts (3d Ed. 1961) § 674, p. 179. “Conditions may be precedent or subsequent. In the former, the condition must be performed before the contract becomes absolute and obligatory upon the other party.” Code § 20-110.
Plaintiff contends that the defendants’ promise to pay was unconditional and that the above quoted portion of the contract merely specified the time when payment should be made. We cannot agree with that contention, for as we construe the plain and unambiguous language of the agreement, there are clearly expressed conditions precedent to defendants’ liability for the final payment of the contract price.
In the construction of a contract the cardinal rule is to ascertain the intention of the parties, and the court should consider the whole contract in arriving at the construction of any part. Code §§ 20-702, 20-704 (4); e.g., Hull v. Lewis, 180 Ga. 721, 724 (180 SE 599).
The contract evinces the parties’ intentions that plaintiff’s work should conform absolutely to the specified architectural standards: Plaintiff was to perform “in strict accordance with” plans drawn by the architect; all work was to be done under the
In addition, the contract is open to the construction that possibility of the owner’s nonpayment on account of plaintiff’s work in the construction is the subcontractor’s risk rather than that of the prime contractor and that the owner’s payment to the prime contractor for the subcontractor’s work is yet another condition precedent to defendants’ liability, so that the plaintiff’s failure to- allege the owner’s payment to the prime contractor renders his petition further defective.
The trial court erred in overruling the renewed general demurrers to plaintiff’s petition. This ruling being determinative of the case it is not necessary to consider the remaining assignments of error.
Judgment reversed.