This matter arose from a contract dispute involving the plaintiff’s construction of a grit, septage,
Both parties claim error. The plaintiff primarily contends that the judge erred in (1) rejecting its G. L. c. 93A claim; (2) concluding that it could not recover on the contract; and (3) denying its claim for overhead expenses. The town contends the
1. Facts. In December, 1987, the Department of Environmental Quality Engineering (DEQE) (now known as the Department of Environmental Protection) ordered the town to close its landfill septage lagoons and to construct a new treatment facility for septage and grease wastes. Pursuant to this order, the town contracted with an engineering firm, Metcalf & Eddy (M & E), to plan and to design these facilities. In October, 1989, it contracted with the plaintiff to act as general contractor for the project. The contract called for the plaintiff to complete its work by January 27, 1991, but included provisions for extending the deadline.
Deemed “primarily an equipment procurement job,” the project required the plaintiff first to submit proposed drawings and then, pending M & E’s approval, to procure several pieces of equipment for the facility. One such piece of equipment was a vertical progressive cavity pump (pump). The contract between the plaintiff and the town permitted the plaintiff to select any pump model from one of the manufacturers identified in the project specifications. The plaintiff chose a pump made by Robbins & Myers and subsequently submitted several drawings of the pump to M & E.
2. General Laws c. 93A, § 2. The plaintiff first contends that the judge erred in denying its G. L. c. 93A claim. In his final report, the master concluded that the town was engaged in “trade or commerce” when it contracted with the plaintiff, and that its refusal to declare the project substantially complete on August 30, 1991, constituted an unfair and deceptive trade practice in violation of G. L. c. 93A, § 2. The judge disagreed in part, ruling that c. 93A was inapplicable because the town was not engaged in trade or commerce when it contracted with the plaintiff. We agree with the judge.
Chapter 93A proscribes “unfair or deceptive acts or practices in the conduct of any trade or commerce.” G. L. c. 93A, § 2 (a). A party is engaging in “trade or commerce,” as required under c. 93A, when it acts “in a business context.”
In the present case, the town is a government entity that contracted with the plaintiff pursuant to an administrative order imposed by the DEQE. Such orders are enforced with the same power as statutes and, indeed, are the creations of a legislative enactment. G. L. c. Ill, §§ 160, 162, 164. 310 Code Mass. Regs. §§ 22.00 et seq. (1994). The threat of a civil administra: five penalty or other punishment for violation of the order only underscores the fact that compliance with the order is indeed mandatory.
Furthermore, the town’s waste treatment facility is not a profit-making operation.
3. Recovery on the contract. The plaintiff next claims that the judge erred in denying it any recovery on the contract. In his final report, the master recommended that the judge award the plaintiff such recovery. The judge declined to follow this recommendation, concluding instead that the plaintiff’s own breach barred recovery on the contract. On appeal, the plaintiff contends that its breach was excused because it was caused exclusively by the town’s wrongful conduct. We disagree and affirm the denial of the plaintiff’s recovery on the contract.
Contractors like the plaintiff “cannot recover on the contract itself without showing complete and strict performance of all its terms.” Andre v. Maguire,
The town argues that the judge erred in not entering judgment in its favor. Specifically, the town contends that, because
4. Recovery in quantum meruit. Although he denied recovery on the contract itself, the judge, acting pursuant to the master’s recommendation in his supplemental report, did award the plaintiff damages under a quantum meruit theory. On appeal, the town claims that this was erroneous because the plaintiff’s breach of the contract was not in good faith. We disagree.
A contractor “may recover in quantum meruit,” if he can prove both substantial performance of the contract and an endeavor on his part in good faith to perform fully. J.A. Sullivan Corp. v. Commonwealth, supra at 796, quoting Andre v. Maguire, supra at 516. Generally, “an intentional departure from the precise requirements of the contract is not consistent with good faith in the endeavor fully to perform it.” J.A. Sullivan Corp. v. Commonwealth, supra at 797, quoting Andre v. Maguire, supra. Here, the master expressly found that the plaintiff’s failure to complete the project by January 27, 1991, was an unintentional departure from the contract’s requirement. Indeed, he found that the plaintiff’s delayed performance was at least “in part” caused by the town’s improper rejection of the pumps. Pursuant to Mass. R. Civ. P. 53 (h) (1), we must accept these findings of fact unless we conclude that they are “clearly erroneous, mutually inconsistent, unwarranted by the evidence before the master as a matter of law or are otherwise tainted by error of law.” Since we do not so conclude, the judge’s award of damages in quantum meruit is affirmed.
In determining a quantum meruit recovery, the proper focus is “the value of the services rendered . . . or [] the fair value of what the defendant has received.” Ryan v. Ryan,
6. The town’s liquidated damages. The town also contends that the judge erred when he determined that the town was not entitled to liquidated damages for the plaintiff’s delayed completion of the project.
Liquidated damages are inappropriate here. This court has held that, where both the plaintiff (contractor) and the defendant (owner) were to blame for the plaintiff’s delayed completion of a project, the defendant was not entitled to liquidated damages.
7. Interest calculations. In his final report, the master awarded the plaintiff prejudgment interest at 8.2% for the “net [cjontract balance” of $180,692, pursuant to G. L. c. 30, § 39K. Its accrual date was November 3, 1991. The master also found that, under G. L. c. 231, § 6C, the plaintiff was entitled to 12% interest for the “increased field and home office overhead amount of $388,644.” The accrual date here was January 1, 1992, “being the approximate midpoint of when those [overhead] costs were incurred, i.e., 31 August 1991 through 27 April 1992.” In his first memorandum of decision and order, the judge stated only that no award of interest under § 39K was warranted because the plaintiff’s damages were in quantum meruit, not on the contract itself. Then, in his supplemental report, the master found that “[i]nterest at the statutory rate of 12% pursuant to M.G.L. c. 231 § 6C is to be applied to the net amount due and owing to Peabody of $180,692.00, commencing as of 1 January 1992. ” Finally, in his second memorandum of decision and order, the judge affirmed the master’s supplemental report, concluding that under § 6C the plaintiff was entitled to quantum meruit damages “in the amount of $266,692 plus 12% interest, commencing as of January 1, 1992 until paid.”
On appeal, both parties agree that the proper rate of interest
General Laws c. 231, § 6C, governs the calculation of prejudgment interest in contract actions. It provides in part:
“In all actions based on contractual obligations, upon a verdict, finding or order for judgment for pecuniary damages, interest shall be added ... at the contract rate, if established, or at the rate of twelve per cent per annum, from the date of the breach or demand. If the date of the breach or demand is not established, interest shall be added . . . from the date of the commencement of the action’’’ (emphasis added).
In the present case, no issue is presented to this court regarding the appropriate rate of interest to be applied under § 6C. Both parties agree that 8.2% is the appropriate interest rate under the terms of their contract. Rather, the primary issue lies in the date from which the interest accrues. Under § 6C, interest accrues “from the date of the breach or demand [if] established.” Where no demand is made and multiple breaches occur, however, interest must accrue “from the date of the commencement of the action.” There is no evidence here that any demand was made by the plaintiff. Furthermore, each party was responsible for at least one breach of the contract: (1) on January 3, 1991, when the town rejected the second formal Robbins & Myers pump submittal when such pump complied with the drawings and specifications; (2) on August 30, 1991, when the town refused
In short, the plaintiff is entitled to prejudgment interest at the rate of 8.2% from December 3, 1991. To the extent that the judge’s order is inconsistent with this conclusion, it is vacated.
8. The town’s other claimed losses. The town makes several other claims regarding the judge’s award to the plaintiff. First, the town claims that the plaintiff’s recovery should be offset in the amount of $45,000, for engineering work the town performed in preparation for the plaintiff’s planned installation of three “gate valves” at the facility.
Second, the town claims that the judge erred in including in the plaintiff’s quantum meruit award $23,092 for additional costs the plaintiff incurred in purchasing a pump to replace the rejected Robbins & Myers pump.
9. Conclusion. In total, the plaintiff is entitled to recover from the town a quantum meruit award of $266,692.
The case is remanded to the Superior Court for the entry of a judgment in the amount of $266,692 plus prejudgment interest from December 3, 1991.
So ordered.
Notes
Septage is “waste from septic systems which are not connected to sewers.” Sewer Comm’rs of Hingham v. Massachusetts Water Resources Auth.,
The agreement provided that the plaintiff could seek an extension as long as it notified the town within ten days of the beginning of the claimed delay.
This submittal, along with several others, was made months after the scheduled submission date.
Under the agreement, the plaintiff was not required to perform extra work after “substantial completion” of the contract.
As a preliminary matter, the plaintiff claims that the judge improperly supplanted the master’s findings regarding whether the town was engaged in trade or commerce for purposes of G. L. c. 93A. The master, however, correctly characterized his statement that the town was engaged in trade or commerce as a “Conclusion of Law.” “To the extent that the master’s ultimate findings are conclusions of law, they are subject to independent judicial review.” Pollock v. Marshall,
This, in turn, depends on a number of factors, including “the nature of the transaction, the character of the parties involved, and [their] activities . . . and whether the transaction [was] motivated by business or personal reasons.’’ Begelfer v. Najarian,
We have previously stated that, in the context of G. L. c. 93A, “[o]ur use of the term ‘profit’ ... is meant colloquially, in the sense of revenues that exceed expenses.” Linkage Corp. v. Trustees of Boston Univ.,
As a preliminary matter, the town contends that, because the plaintiff failed timely to object to the master’s final report, it waived any challenge on appeal to the master’s liquidated damages award to the town. Under Mass. R. Civ. P. 53 (h) (2), as appearing in
This court concluded in that case that “the delay, not having been caused by the fault or neglect of the plaintiff, would not establish any right in the town to claim or withhold anything by way of liquidated damages” (emphasis added). Morgan v. Burlington,
The amount awarded, $266,692, represents the quantum meruit award of the master, plus $86,000 which had previously been excluded by the master as
Both parties appear to agree that, because the plaintiff did not recover on the contract, an interest award under G. L. c. 30, § 39K, is improper. Assuming that § 39K applies to this project, we agree. As the Appeals Court concluded in Acme Plastering Co. v. Boston Hous. Auth.,
The master stated that the town claimed that its $45,000 loss stemmed from engineering work it performed in preparation for the plaintiff’s installation of the gate valves. On appeal the town does not argue that, because the valves were never installed, their cost should have been deducted from the plaintiff’s quantum meruit award. Consequently, we must address only the claims presented.
According to the master’s final report, the plaintiff paid $59,092 for the substitute pump, and received a credit from Robbins & Myers for $36,000 for the cancellation of the plaintiff’s order. Thus, the net additional costs incurred by the plaintiff were $23,092.
We reach this figure by subtracting the town’s previous payments to the plaintiff, $3,198,806, and the town’s previous payments of $4,000 for the plaintiff’s electricity costs from the value of material and labor supplied by the plaintiff (and the plaintiff’s other expenses), $3,469,498.
